PERTH, Western Australia, July 5 /CNW/ - Mirabela Nickel Ltd ("Company") (TSX - MNB, ASX - MBN) is pleased to announce completion of the Bankable Feasibility Study for the Santa Rita nickel sulphide project. The study confirms that the development of a 4 million tpa open pit mine and concentrator at Santa Rita is technically and commercially feasible. Highlights are as follows:
- Capital costs for development of plant and associated infrastructure
for the Project are estimated at US$263m including contingency
- The Project will initially produce approximately 16,000 tpa
(35 million lb pa) of Ni in concentrate, making Mirabela a substantial
Ni producer
- Planning for an increase in throughput to 4.6 million tpa to produce
approximately 18,500 tpa (41 million lb pa) of Ni in concentrate is
already underway
- The Project is already equity funded with US$160 million cash
available for Project construction
- Funding the balance of the Project requirements by debt appears to be
straight-forward with strong initial expressions of interest from
potential banking syndicates
- The environmental approval process is well advanced and expected to be
completed in September 2007 enabling site works to commence in October
2007
- Commissioning of the Project remains on target for 2Q 2009
- A project development team is already appointed, with extensive
experience in the development of nickel sulphide projects and the
construction of sulphide flotation plants
- The Company is already progressing with the first phase of Project
implementation, including detailed project planning and preliminary
engineering
- Significant long lead time items are already ordered - SAG mill, ball
mill and primary jaw crusher
Capital Cost Estimates
The following capital cost estimates for the concentrator and all project
infrastructure were completed by GRD Minproc Ltd:
Plant and Infrastructure (direct and indirect costs including
Port, Power and EPCM) US$239.1M
Project Contingency (8%) US$ 24.1M
Total US$263.2M
To ensure the integrity of the capital cost estimates, additional work was
undertaken beyond normal requirements for a BFS study. About 84% of equipment
pricing was based on either firm quotes or budget quotes, on a three-tender
minimum basis. GRD Minproc considers the accuracy of the capital cost estimate
to be +/- 10%.
The estimate of plant and infrastructure capital of US$239.1 million
(pre-contingency) compares with the previous published estimate of
US$223 million. Most of this increase is attributable to the use of a lower
US$/BR$ exchange rate from 2.22 to 2.05 to reflect the near term strengthening
of the Brazilian Real against the US dollar. The Company has entered into
forward conversion contracts (US$ to BR$) for a substantial part of its cash
in hand at an exchange rate of 2.05.
Approximately 80% of the capital cost estimate is derived from Brazil
based contractors or suppliers, where mining industry cost pressures and
labour shortages do not appear to be as prevalent as in some other countries.
Operating Cost Estimates
The average operating costs are estimated as follows:
Mining US$1.16 per tonne of material mined
Concentrator US$6.89 per tonne ore processed
General & Administration US$1.79 per tonne ore processed
Transport to Ilheus port US$0.68 per tonne ore processed
GRD Minproc considers the accuracy of the operating cost estimates to be
+/- 15%.
Mining cost estimates were developed by experienced Brazil based mining
consultants based on typical open pit mining conditions in Brazil, with final
review of cost models and assumptions by GRD Minproc. The mining cost estimate
includes an allowance for the capital cost of the mining fleet. The Company
intends to lease and owner-operate the mining fleet. Due to time constraints,
a contractor will be used for initial mining activities including the
pre-strip.
The concentrator operating costs are for an annual throughput of 4 million
tpa. The estimate includes an allowance for plant maintenance (sustaining
capital) based on 4.2% pa of the installed capital cost.
There are numerous options for potential concentrate sales. The base case
for the BFS is sale of the concentrate upon FOB terms from the port of Ilheus.
The above estimate is for the transport of concentrate to the port and loading
onto a ship. A capital cost estimate of US$8.0 million for concentrate storage
and shiploading facilities at Ilheus is included in the plant and
infrastructure cost estimate.
The only capital or sustaining capital requirements of the Project not
included in the above capital and operating cost estimates are US$16.5 million
in sustaining capital for progressive uplift of the tailings facility and
US$7.1 million at the end of the Project for closure and decommissioning
costs.
The operating cost estimates were prepared using an expected long term
US$/BR$ exchange rate of 2.22.
These operating costs imply average cash costs per payable Ni lb of
US$2.81 lb after credits and US$3.34 lb before credits, demonstrating that
Santa Rita will be a low cost and highly profitable Ni sulphide producer. At a
throughput rate of 4.6 mtpa, the Project will produce 27.1 million payable Ni
lbs per annum.
Note: The above cash costs estimates are calculated by the Company by
taking the costs per tonne described above (assuming an average strip
ratio of 7.7 to 1) and dividing by the estimated net payable lbs of Ni
production per tonne (assuming average head grade of 0.60% Ni, recovery
of 67.4%, payability of 70% and royalty of 5.51%). The after credits
calculation deducts estimated credit revenue per tonne from the costs.
These assumptions are subject to important risk factors and
uncertainties, in particular the Company is yet to finalise an off-take
agreement which will determine the payability for Ni and other credits.
Royalties
The government and landowner royalties payable under Federal law total 3%
of net revenue from the sale of concentrate less transport, insurance and
taxes on sales. An additional 2.51% royalty on revenue from the sale of
concentrate is payable to CBPM, the original vendor of the Project.
Metallurgical Recoveries and Concentrate Specifications
Assuming an average head grade of 0.60% Ni, average Ni recovery over the
life of the operation is estimated to be 67.4%. Average Cu recovery is
estimated at 82%. The Project is expected to produce a mixed Ni-Cu-Co-PGM-Au
concentrate grading 13% Ni, 3.5% Cu, 0.22% Co and 4.9 g/t combined PGMs and
Au.
Throughput
The Project is currently designed for a 4.0 mtpa throughput rate. Ramp up
to 90% of nameplate throughput is expected to occur within the first six
months of operation.
Following the recent announcement of a 40% increase in the Potential Mill
Feed resource (see Resource below), the Company is undertaking a detailed
study of the requirements to expand the throughput rate to 4.6 mtpa. This
review is focussed on obtaining the additional throughput with the existing
planned SAG and Ball mill configuration. The increased throughput will be
based mainly on optimising the plant availability and grind size, and
incorporating a pebble crusher. Minor modifications to the flotation circuit
to allow for the additional material flow are likely.
It is anticipated that the increased throughput could be achieved after a
year of operations for an additional capital cost of about US$10 million.
Funding requirements
The Company currently has US$183 million cash in hand. About US$23 million
will be reserved for activities outside of Santa Rita project construction,
including resource drilling, land acquisition and project management at Santa
Rita, ongoing exploration across all Mirabela's projects, smelter feasibility
work, saprolite project work and corporate overheads.
This leaves US$160 million of cash in hand to be spent on Santa Rita plant
and infrastructure against a requirement of US$260 million, being US$263
million (as set out above) less US$3 million already spent on long lead items.
The balance of the Project funding requirements will be met by debt
funding. The debt requirement is estimated to be US$100 million for plant and
infrastructure and approximately US$50 million for working capital including
pre-strip. Securing this debt funding appears to be straight-forward with
strong initial expressions of interest from potential banking syndicates. The
commencement of draw down on the debt funding is not expected to be required
until July 2008.
The Company recently obtained an estimate of the forward Ni price
currently available from hedging over the first 4 years of the planned Project
life, i.e. the period 3Q 2009 to 2Q 2013 inclusive. An average hedged Ni price
of US$11.25 per lb is currently available over that 4 year period (this is
after the recent fall in the spot Ni price). This is well in excess of
analysts current Ni price forecasts for this period. The likely requirement
for a prudent level of hedging as part of planned debt arrangements does not
cause the Company any concern.
Resource
The Company recently announced the following Potential Mill Feed resource
estimate for Santa Rita under the JORC code (this is the estimated resource
available as mill feed based upon a pit optimisation study):
- Measured and Indicated - 69.2 million tonnes grading 0.61% Ni
(925 million lbs)
- Inferred - 6.8 million tonnes grading 0.53% Ni (79 million lbs)
- Indicative strip ratio 7.7:1
Note 1: Inferred resources (which comprise 9% of the above resource
estimate) are, by definition, of insufficient confidence to have economic
considerations applied that would enable them to be categorised as
mineral reserves, and there is no certainty that preliminary assessments
will be realised in respect of such resources.
Note 2: The Company is yet to incorporate this updated resource estimate
into the BFS and to update the 43.101 report for Santa Rita, this work is
presently underway.
The Company has commenced an Extended Deeps drilling program to convert
the Inferred portions of the Potential Mill Feed resource estimate to
Indicated status and to further extend the mineral resource in the Southern
Deeps area where drilling is still relatively shallow. This program will
comprise about 22 holes for 8,500m and take about 2 months to complete.
The Company intends to convert the Potential Mill Feed resource to a
Proven and Probable reserve upon completion of the Extended Deeps program.
Accordingly, finalization of the pit model and scheduling and announcement of
a mineable reserve is expected to be completed in 3 to 4 months time.
Based on resource studies to date, it is expected that almost all of the
Indicated resource will be converted to Probable reserve status. Dilution and
ore loss through the mining process are already incorporated into the
Potential Mill Feed resource estimate.
Tax regime
A detailed assessment of the tax regime applicable to the Santa Rita has
been completed by Brazilian project taxation specialists. The details of the
applicable tax regime are subject to ongoing negotiations in relation to
various tax incentives. The Company is presently targeting an effective income
tax rate of less than 20%.
Project Schedule
The Project is on schedule for commissioning in 2Q 2009 based on the issue
of the appropriate environmental permits in 3Q 2007.
The Company brought forward components of the detailed engineering to
enable the early placement of orders for critical long lead time items. To
date orders have been placed for the SAG mill, Ball mill and the primary
gyratory crusher which are the principal critical long lead time items in
determining the project delivery schedule.
The SAG and Ball mills were ordered from Outokumpu Technology Pty Ltd in
April 2007 and delivery is scheduled for late in 4Q 2008. The order for the
gyratory crusher was placed with Metso Minerals' subsidiary in Brazil in May
2007. Additional major equipment items to be ordered within the next two
months are the power transformers and concentrate filters.
GRD Minproc commenced preliminary engineering on the Project in May 2007.
Detailed project planning is currently underway in Brazil involving a mix of
Australian and local Brazilian engineers and civil construction groups to
ensure an appropriate mix of nickel sulphide experience and local knowledge is
applied to the Project implementation.
The Project Director is Mr Raphael Bloise and the Project General Manager
is Mr David Black. Mr Bloise has extensive project management experience and
previously was Project Manager for CVRD for the construction and commissioning
of the Sossego copper project in Para State, Brazil (15mtpa sulphide
flotation). Mr Black most recently managed the brownfields upgrade of the
Maggie Hays nickel sulphide plant in Western Australia. The incumbents bring
to the Company extensive experience in sulphide and nickel flotation plant
construction and commissioning, both within Brazil and internationally.
Environmental permitting is well advanced with issue of the project
installation license (Licenca de Instalacao, LI) expected in 3Q 2007, which
will enable the commencement of site construction activities shortly
thereafter. The basis for this license is principally the further detailing
and presentation of the environmental management plan for the installation and
operating phases of the Project. Arcoverde Consultoria e Projetos, who
assisted Mirabela in successfully obtaining the preliminary environmental
licenses in December 2006, has continued to work on this process.
Smelter study being advanced
The Company is actively pursuing the option of producing a high-grade
Ni-Cu matte to optimise the returns from the Project and leverage off the
excellent facilities in the Ipiaú region. WorleyParsons Services Pty Ltd was
recently commissioned to complete a Scoping level evaluation (+/-50%) of the
capital and operating costs of constructing and operating a smelter and
related infrastructure located adjacent to the Santa Rita concentrator. This
study is scheduled to be completed by mid-September 2007.
Nick Poll
Managing Director
Technical Information: Technical information in this news release has
been reviewed by Nicholas Poll, who is a Member of The Australasian
Institute of Mining and Metallurgy. Nicholas Poll is the Managing
Director of the Company.
Forward looking statements: Certain of the statements made in this news
release, including any information with respect to the Company's plans to
develop the Santa Rita Project, may be forward-looking and subject to
important risk factors and uncertainties, many of which are beyond the
Company's ability to control or predict. Forward looking statements are
necessarily based on estimates and assumptions and are subject to
significant business, economic and competitive uncertainties and
contingencies. Known and unknown factors could cause actual results to
differ materially from those projected in the forward-looking statements.
Such factors include, among others: fluctuations in metals prices,
including the price of nickel; differences between actual and estimated
capital costs and the possibility of cost overruns; differences between
actual and anticipated operating costs, resources, metallurgical
recoveries and production levels; changes in national and local
government legislation, taxation, controls regulations and political or
economic developments; the speculative nature of mineral exploration and
development; the risk of not obtaining necessary licences or permits on a
timely basis; additional funding requirements; as well as those factors
described or referred to in reports filed by the Company with Canadian
securities administrators. Accordingly, readers should not place undue
reliance on forward-looking statements.