Project for the Haneda Airport Access Line(tentative name)
(Source: Annual Airport Management Report)
10,000
International
Trend in Passenger Numbers at Haneda Airport国際線利用者数
国内線利用者数
Domestic
Approx. 88.00 million people
9,000
Passengers
Passengers
Approx. 87.00 million people
8,000
Passengers (10,000 people/year)
7,000
Approx. 64.21 million people
6,000
5,000
October 2010
Domestic passengers Approx. 69.00 million people
March 2020
Domestic passengers Approx. 65.00 million people
4,000
3,000
Opening of Runway D (Re-internationalization)
New flight routes introduced
(Increase in international flight slots)
2,000
1,000
0
International passengers Approx. 3.88 million people
International passengers Approx. 17.00 million people
International passengers Approx. 23.00 million people
Growing Passenger Demand
International passengers have steadily increased since the re-internationalization in FY2011.3. In FY2020.3, international
passenger numbers were about four times higher than in FY2011.3.
FY2025.3 Passengers: Approx. 88.00 million people/year (241,000 people/day) Passenger demand is expected to continue growing as airport capacity is expanded.
FY
Rail Access to Haneda AirportHaneda Airport
Haneda Airport
Keikyu
Shinagawa (transfer)
Tokyo
Keikyu
Airport Line
(Using Keikyu Line)
JR
Tokyo
Monorail
Shinagawa
Haneda Airport
Hamamatsucho (transfer)
Hamamatsucho
Monorail
JR
Tokyo
Shinjuku
(Using Tokyo Monorail)
[Existing Rail Network Overview]
Current Rail Network to Haneda Airport
For example, traveling from Tokyo Station to Haneda Airport
requires transfers at Hamamatsucho or Shinagawa Stations.
Tokyo
Comparison with Airport Access in Other Countries (Airports approximately 10 km from city centers)
Haneda Airport takes longer travel time relative to distance compared to overseas airports. Frankfurt ⇒ Approx. 10 min
Copenhagen ⇒ Approx. 12 min Zurich ⇒ Approx. 10 min
Haneda Airport ⇒ Approx. 30 min (Tokyo)
Need to Strengthen and Enhance Access to Haneda Airport
Background and Positioning of the ProjectAug 2014 Proposal of concept by JR East at the Subcommittee of the Council for Transport Policy
Jul 2015 Tokyo Metropolitan Government Wide-Area Transportation Network Review Committee
⇒ Designated as a priority route for development
Apr 2016 Council for Transport Policy Report No.198
⇒ Recognized as a railway network project contributing to
strengthening international competitiveness
Jul 2018 JR East Group Management Vision: “Move Up” 2027
⇒ Included promotion of the Haneda Airport Access Line concept
May 2019 Submission of Environmental Impact Assessment Study Plan to
Haneda Airport Domestic Terminal
Excerpt from “Council for Transport Policy Report No. 198”
Tokyo Metropolitan Government (= start of environmental assessment)
(East Yamate route and New Access Line section)
Jan 2021 Railway project approval obtained for the New
Access Line section
Aug 2022 Environmental Impact Assessment Report published
Jan 2023 Approval obtained for railway facility modifications
for the improvement section (East Yamate route)
Mar 2023 Construction implementation approval obtained for
the construction section (New Access Line section)
Construction section location map
[Reference]
“Haneda Airport Access Line”
(tentative name)
East Yamate & New Access Line Route Overview Map
To Utsunomiya, Takasaki, and Joban Lines
Tokyo
East Yamate route
New Station
at Haneda Airport
Access New Line
New Station
at Haneda Airport
Access New Line
From the press release on the acquisition of railway project approval
Jun 2023 Construction commenced (East Yamate route and New Access Line section)
To Saikyo Line
To Utsunomiya, Takasaki,
and Joban Lines
Tokyo East Yamate route
West Yamate
route
Tamachi
Station area
Shin-Kiba
Osaki
Coastal area
route
Tokyo Teleport
Oimachi
Station area
Tokyo Freight Terminal area
Role and Synergies within the JR East GroupBasic Concept
The JR East Group will operate its unique TOD model called “J-TOD” by utilizing synergy between Mobility and Lifestyle Solutions. Through the provision of its unique services, such as Suica, and the collaboration with local administrative agencies and businesses, the Group will create diverse networks to generate network synergy.
* TOD=Transit Oriented Development
[Three Types of J-TOD] [Synergies between Mobility and Lifestyle Solutions]
[Network Synergies]
Enriching Lifestyles of All People
Regional network Corporate network Logistics network
Railway network
Suica network Energy network
Network Synergies
5
Positioning and Synergies within the JR East Group[Mobility]
Development of the Haneda Airport Access Line(tentative name)
Synergies within the business
Increasing the value of the Tokyo metropolitan area
Revitalizing the commercial use of the areas along railway lines
[Lifestyle Solutions]
Synergies between businesses
Collaboration with the Tohoku Shinkansen and other lines at Tokyo Station increases usage not only on the sections directly served by the Haneda Airport Access Line(tentative name)but across the Group’s mobility services.
Realize direct access to Haneda Airport from multiple lines, including the Utsunomiya, Takasaki, and Joban Lines.
Enhance city–airport connectivity through coordination with the Tokyo Monorail.
Increasing the use of airport transportation of the JR East Group
Strengthen town development along railway lines, such as the Greater Shinagawa Area
Increasing tourist traffic into the JR East areas
6
Overall Overview of the Haneda Airport Access Line (tentative name)To accommodate future growth in air passenger traffic and further improve convenience, leverage the existing railway network and infrastructure.
⇒ Consider the development of a new railway networkto Haneda Airport.
West Yamate route
East Yamate route
Coastal area route
Shinjuku
Tokyo | ||
Tokaido Line (Ueno-Tokyo Line) (Tamachi Station area) Oshio Short-Circuit Line Oshio Line Tokyo Freight Terminal New Access Line Haneda Airport | ||
Shin-Kiba | ||
Rinkai Line Tokyo Teleport Rinkai Line Rinkai Connecting Line Tokyo Freight Terminal New Access Line Haneda Airport | ||
Saikyo Line
Osaki
Rinkai Line
(Between Oimachi and Shinagawa Seaside)
Higashi-Shinagawa Short-Circuit Line
Tokyo Freight Terminal
New Access Line
Haneda Airport
Between Shinjuku and Haneda Airport | Time required | No.of transfer |
West Yamanote route | Approx.23 min. | > |
Between Tokyo and Haneda Airport | Time required | No.of transfer |
East Yamanote route | Approx.18 min. | > |
Between Shin-Kiba and Haneda Airport | Time required | No.of transfer |
Coastal area route | Approx.20 min. | > |
Construction commenced in 2023 7
Relationship with the Tokyo MonorailFrom the press release
From the press release
Access to Terminal 3 and other areas is planned to be enhanced through coordination between the Haneda Airport Access Line(tentative name) and the Tokyo Monorail.
Furthermore, the Tokyo Monorail is expected to remain an important transportation service rooted in the local community, supported not only by airport access demand but also by commuter demand along the Line, as well as anticipated increases in ridership associated with redevelopment around Hamamatsucho Station and growing usage in the Haneda Airport area.
Cross-sectional passenger volume on the outbound line (people/year)*
Tennozu Isle
Oi Keibajo Mae
25,000,000
20,000,000
15,000,000
* Commuter and non-commuter usage combined
Tokyo Monorail
10,000,000
From the Tokyo Monorail website
Ryutsu Center
5,000,000
Showajima 0
Seibijo
Tenkubashi
Shin Seibijo
Cross-sectional passenger volume of the Tokyo Monorail in FY2020.3 (Source: 2021 Annual Report on Urban and Regional Transportation)
8
Overview of the Haneda Airport Access Line(tentative name): East Yamate Route OverviewLegend
Project section (Construction section) Project section
(Improvement section)
Ground level Viaduct Retaining wall
Cut-and-cover tunnel Shield tunnel
Shaft location
Planned Opening: FY2032.3
Estimated Construction Cost: Approx. 280 billion yen
(Including approximately 70 billion yen for the tunnel construction and other related works as part of the airport development project.)
Airport Development Project Area
Tokyo Freight
Terminal
Box Structures on the Airport Island
Station
Tamachi
Cross Section
Legend
Planned Existing
Installation of Detention Lines and Other
Relocation Works
Modification of Existing Lines, etc.
9
Underground Relocation
New Access Line Section : Image of the New Airport StationImage taken near the control tower
Runway C
Terminal 2
P3 Parking
Tokyo
Monorail [B2F]
New station
Metropolitan Expressway
Bayshore-Route
* Ventilation facilities and similar components are not shown in this image.
Airport New Station Area: Conceptual Station LayoutB1
Multi-story Parking Lot
Multi-story Parking Lot
2
1
New Station at Haneda airport
Tokyo Monorail
Haneda Airport
Terminal 1 Station
B1
B2
Connecting Passage
Tokyo Monorail
Haneda Airport Terminal 2 Station
B3
Keikyu Line Platform
B2
B3
Space Available for Station
Construction
Keikyu Terminal 1 and 2 Station
Platform located on Basement Level 1 (same level as Terminal 2)
To Terminal 2
Tokyo Monorail Terminal 2 Station
B1
B2
Platform B1
New Station
Bridge
Foundation
Terminal 2
Tokyo Monorail
P3 Parking Lot
A
Airport Road
National Route 357
New Station
A’
Shuto Expressway Bayshore Route
1
2
Haneda Airport Terminal 1 Station
Terminal 1
Haneda Airport Terminal 2 Station
Multi-story Parking Lot
Terminal
Connecting Passage
Keikyu Line
Parking Access Road
Internal Loop Road
National Route 357
Shuto Expressway Bayshore Route
Shuto Expressway Bayshore Route
Expressway Tollgate Lane
National Route 357
Internal Loop Road
Parking Access Road
Keikyu Airport Line
Haneda Airport Terminal and Station
Terminal
[Simplified Cross Section]
Haneda Airport Access Line(tentative name)OverviewAirport Development Project Area
Box Structures on the Airport Island
城南島
起点方
立坑 終点方
立坑 第2タ ーミナル
野鳥公園
清掃工場
京
急駅
京浜島
第1ターミナル
Jonan Island
Waste Incineration
Plant
Side Shaft
Starting-
Wild Bird Park
Keihin Island
Tokyo Freight Terminal
Ota Market
[Track Longitudinal Profile]
Wild Bird Park
Tokyo Freight Terminal Ota Market
Outside the Airport Island
Tsubasa Park Waste Incineration Plant
Direction
Excavation
Canal
Within the Airport Island
Created by our company based on GSI Map Data(GSI Maps)
Cut-and-Cover Section
Terminal-Side Shaft
Canal
Connecting Passage KeiKyu Line
Excavation
Direction
Excavation Direction
Starting-Side Shaft
Overall Layout of the Tokyo Freight Terminal[Tokyo Freight Terminal (Overall Layout)]
NアewクAセccスes新s L線ine ((to羽H田an空ed港a A方irp面or)t)
Shinagawa Ward Ota Ward
Oi Wharf
Rinkai Line Train Depot
Tokaido Freight Line (Outbound)
Coastal area route
Tokaido Freight Line (Inbound)
Departure Track
Shield Launch Shaft
Ota Market
(to Shin-Kiba)
Tokyo Freight Terminal
East Yamate route (to Tokyo)
Shinagawa Ward
Ota Ward
West Yamate route
(to Shinjuku)
Created by our company based on GSI Map Data(GSI Maps)
Inspection Site (2) Tokyo Freight Terminal – Construction Status↑ To Haneda Airport
Inbound Line Outbound Line
Train Stabling Track
Maintenance Depot
Maintenance Depot
Road Viaduct
Road Viaduct
Inbound Line
Oshio Line Improvement Section – Existing Viaducts and BridgesEffective Utilization of Existing Structures on the Suspended Freight Line (Oshio Line)
For use, reinforcement works are being carried out for incomplete repairs and seismic retrofitting of various facilities.
Aerial Photo
(Tamachi – Tokaido Line Connection Section – Oshio Line Improvement Section – Tokyo Freight Terminal)
Oshio Line
Tokyo Freight
Terminal Station
Tamachi Station
Photo (1)
Photo (2)
Created by our company based on GSI Map Data(GSI Maps)
Oshio Line
Repair Work Status
Tokaido
Shinkansen
Oshio Line
Parapet Handrail Improvement (Completed)
About the Oshio Line1973: Oshio Line opened
(Shiodome Station – Current Tokyo Freight Terminal Station)
To Takasaki
To Kuroiso
Environmental Changes after Opening
⯁ Declining demand for rail freight transport due to the
rise of truck transport
⯁ Provision of part of the Shiodome Station site for the Tokaido Shinkansen
1986: Shiodome Station closed
Tachikawa
Shin-Tsurumi
Shinjuku
Shinagawa
Oshio
Tokyo
Shiodome
(Freight)
Omiya
Tabata (Yard)
Ueno
Sobu Main Line
To Chiba
1990: Car Train service* commenced
Ofuna
(Yard)
Tsurumi
Kawasaki
Line
Function Transfer
Keiyo Line
To Soga
(from Hamamatsucho Station via the Oshio Line)
1997: Car Train service discontinued
To Atami
Main Freight Routes
Tokyo Freight Terminal
1998: Oshio Line operations suspended
(Hamamatsucho Station – Tokyo Freight Terminal Station)
Construction Plan Overview – Tokaido Line Connection Section (Tamachi Station Area)Overall Layout
Viaduct Improvement Section
Tamachi
Musubu
Shibaura Canal
Tokyo High School
Institute of Science
Tamachi Station
Reinforced Soil Retaining Wall Section
Cut-and-Cover Tunnel Section
Launch Shaft
Fuda-no-Tsuji
Bridge
: Tokaido Shinkansen
: JR East Conventional Lines
Shield Tunnel Section
Overall Longitudinal Section
(Starting Point Side)
Shibaura Section
(Terminal Side)
To Tokyo
Shield Tunnel Section(L=593.7 m)
Cut-and-Cover Tunnel Section (L=185.5 m) Reinforced Soil Retaining
Viaduct Improvement
To Shinagawa
Shield Tunnel Countermeasure Works
Cut-and-Cover Tunnel U-Type Retaining Wall
Wall Section (L=120.5 m)
Section (L=121.8 m)
Arrival Shaft
Tokaido Shinkansen Protective Works
Tamachi Station Connecting Passage
Launch Shaft
Sewers
Construction Plan Overview – Tokaido Line Connection Section (Tamachi Station Area)[Before Construction]
[Plan]
Cut-and-Cover Tunnel (Single Track)
[Section A–A]
STEP 1 (Track switching completed in April 2025)
Abolition of the pull-out track
Track relocation of the Keihin-Tohoku Line (Southbound) and the Yamanote Line outer track
Removal of the Yamanote
TurnbackTrack
Cut-and-Cover Tunnel
(Single Track)
Public Passageway
Shield Tunnel beneath the Tokaido Shinkansen (Single Track)
Tsuji Bo
Fuda-no-
Track relocation of the Tokaido Line (Inbound)
Keihin-Tohoku Line (Northbound)
Yamanote Line Inner Track
Yamanote Line Outer Track
Keihin-Tohoku Line (Southbound)
Tokaido Line (Inbound)
Tokaido Line (Outbound)
Tokaido Shinkansen (Inbound)
Tokaido Shinkansen (Outbound)
Oshio Line
STEP2
Zakoba Bv
Shibahashi Bv
Keihin-Tohoku Line (Northbound)
Yamanote Line Inner Track
Yamanote Line Outer Track
Keihin-Tohoku Line (Southbound)
Tokaido Line (Inbound)
Tokaido Shinkansen (Inbound)
Tokaido Shinkansen (Outbound)
To Hamamatsucho
To Shinagawa
A
Tokaido
Shinkansen
Tokaido Line (Outbound)
To Tokyo
STEP3
Station
Tamachi
Curve realignment and turnout installation on the Tokaido Line (Outbound) After that, the planned line (single track) will be constructed between the Tokaido Line tracks.
A
Keihin-Tohoku Line (Northbound)
Yamanote Line Inner Track
Yamanote Line Outer Track
Keihin-Tohoku Line (Southbound)
Tokaido Line (Inbound)
Planned
Line
Tokaido Line (Outbound)
Tokaido Shinkansen (Inbound)
Tokaido Shinkansen (Outbound)
Track Relocation
Track Switching Work (April 2025)④Girder shifting (Zakoba Railway Underpass) (Shift distance: 1.3 m) | ①Track relocation: Approx. 200 m (Maximum lateral shift: Approx. 2.6 m) | ||
⑤Platform reduction: Approx. 75 m (Maximum width: Approx. 0.6 m) | |||
①Track relocation: Approx. 290 m (Maximum lateral shift:
Approx. 2.5 m)
③Track relocation: Approx. 90m (Including two turnouts)
←To Tokyo
Old-Kaigan Dori Ave.
Zakoba Passageway
awa→
Yamanote Line Outer Track
Keihin-Tohoku Line (Southbound)
K ne
②Track relocation: Approx. 150 m (Maximum lateral shift:
Approx. 2.3 m)
②Track relocation: Approx. 80 m (Maximum lateral shift:
Approx. 2.1 m)
⑥Platform widening: Approx. 65 m (Maximum width: Approx. 1.3 m)
(Outbound)
(Inbound) eihin-Tohoku Li (Southbound)
Yamanote Line (Outer Track)
(Inner Track)
Keihin-Tohoku (Northbound
To Shinag
Tokaido Line
STEP 1 (Track switching completed in April 2025)
Line
)
Track relocation Sliding of the existing girderAbolition of the pull-out track
Track relocation of the Keihin-Tohoku Line (Southbound) and the Yamanote Line outer track
Keihin-Tohoku Line (Northbound)
Yamanote Line Inner Track
Yamanote Line Outer Track
Keihin-Tohoku Line (Southbound)
Tokaido Line (Inbound)
Tokaido Line (Outbound)
Tokaido Shinkansen (Inbound)
Tokaido Shinkansen (Outbound)
Oshio Line
Platform modification After switching(test train operation)From April 18 to April 20, 2025, services on parts of the Yamanote Line and Keihin-Tohoku Line were suspended, and a 35-hour track switching operation was carried out.
The construction work and inspections were successfully completed. 19