ASCU: Parks/Salyer Exploration Opportunity Discussed

Join us for a great event!

Tue, February 15, 2022 at 10:30 AMendedReplay
ASCU: Parks/Salyer Exploration Opportunity Discussed
Company
Arizona Sonoran Copper Co., Inc.
Date
Tue, Feb 15, 2022, 10:30 AM ET
Replay
Watch the replay on this page · 40 min

On 6ix: 6ix.com/event/ascu-parkssalyer-exploration-opportunity-discussed

Replay

Transcript

Automated transcript · Written by software from the replay's audio. It can mishear names and figures; the replay is the record.

0:07 All right. Well, hello, everyone, and welcome to Arizona Sonoran Copper Company's live summit today hosted by 6. I'm pleased to introduce our speakers today. We have President, CEO and Director George Ogilvie, Chief Operating Officer Ian McMillan and Anthony Bottrell, Resource Geologist. The team is going to walk us through a company presentation and then we will be accepting questions live. So as a reminder, you can submit your questions at any time on the right hand side of the screen there, and we'll try to get to them after the presentation.

0:36 And as always, the summit is being recorded and will be available to watch afterwards on SIX.com. But without any further ado, I'll hand it over to you, George. Thank you, Dasha, and thank you, everyone, for joining us here today. Obviously, it's Arizona Sonora Copper Company, and this is an update to a presentation that we gave several weeks ago on the 6th in January of this year. We do make some forward-looking statements, so I'll draw your attention to the cautionary language. If we touch on some of the key events that we've actually delivered on over the last couple of months, I think you're going to see that we've made some significant progress here since the early part of this year. So, first of all, all of the infill drilling as part of the pre-feasibility study that's looking to move inferred resource into the indicated category was completed in late January, And we're now waiting on the final suite of assays to come back that we can then announce to the market.

1:40 We did announce late last year as well that we've started drilling at our exploration property known as Park Salier. And as part of this presentation today, we're going to discuss in a little bit more detail the first 2 holes that have been completed there. And obviously, we put those assay results out to the market last week. Early this year, we also announced that we had completed the rezoning of the LKY lands. As you remember, about a year ago the company had 2100 acres of land and in the last 12 to 15 months we've increased that land position to approximately 4700 acres. Some of that land that we acquired was zoned for residential purposes.

2:27 And I'm happy to say that early this year, the City Council of Casa Grande rezoned the land to industrial purposes. And I think the takeaway from that was that from the initial hearing, and there were 3 public hearings, there wasn't really a lot of public opposition to that. And within 6 months of making the application, we had the land rezoned. So we maintain a very strong social license in and around the Casa Grande and Pinelle County area. We will touch on this as well, but obviously as part of the press release we put out last week, we did pick up some additional land known as the Bronco Creek lands. I think that's going to be very strategic and we're going to find additional mineralization there once we begin to explore a little bit later this year.

3:18 We have strengthened the team. We brought in Nick Nicolacacus as our VP Finance and CFO. Nick has raised over $2 billion US dollars in his 27-year career, And he worked very successfully with me at Battle North Gold at our last shop. And we brought Nick in specifically with the project financing in mind at the end of this year. We're also pleased to announce that we brought in Sarah Strunk as an independent director to the board. Sarah runs a very successful legal law practice in Arizona. She's a native to Arizona. It's very well connected with the regulators and the legislature. And she was formerly the chairperson for Brio Gold before they were acquired by Leogold and ultimately Equinox.

4:09 Also happy to advise that we've now received a lifecycle report from Menviro for the PEA over 18 year life of mine plan. The company now is currently putting in place some action plans that we hope to build into the pre feasibility study. And of course, we're gonna announce that to the market at some juncture in the summer, I think specifically we're targeting July. And we do see a pathway here to net 0 carbon emissions over time. Drilling is ongoing at the site today. We're currently doing NFL drilling for the bankable feasibility study, which is due at the end of the year. And of course, that drilling is targeting the indicated resource to move it up into the measured category ahead of made in the reserves as part of the PFS and reserve updates as part of the bankable feasibility study.

5:09 Thanks, Alison. As you're all aware, the projects located at the intersection of 3 massive copper porphyry systems. We're very close to the city of Casa Grande, which has a population of 55,000 people. We're in an ideal location for a mine. We're 45 miles southeast of Phoenix with a population of 4.5 million people and about 100 miles north of Tucson. The area is very well serviced by roads and infrastructure and as everybody is aware, we already have the main power line running right through the site. As you're aware, Arizona is currently the largest domestic supplier of copper within the U.S.

5:56 And on an annual basis it continually ranks very high in the Fraser Institute rankings for mining investment. Thank you, Alison. So this is a site map looking down on the property. You can see on the left hand side Park Salier and then just to the east of that, to the right of that, you'll see 158 acres. That's the Bronco Creek property that we announced that we had picked up last week. We did that because as Antony will shortly show us, whole ECP45

6:30 was drilled about 45 meters from that eastern boundary to the Bronco Creek property. We picked up extremely strong mineralization and we believe that mineralization trend will run to the north and to the northeast and ultimately it's probably going to dissect the northwest corner of the Bronco Creek property. So, you know, picking that property up from a strategic perspective, from an exploration perspective, was obviously quite important. Plus, it adds another 158 acres of land, taking our entire land package up to 4,846 acres of land. Thank you, Alison. Just to recap, obviously this is a photograph of the site.

7:16 We have a permit to take water for the next 50 years. As you know, the PEA is an 18 year life of mine, so that permit is well in excess of the current life of mine. The permit also allows us to take water at a rate of 3,700 acre feet per year. And when we look at the current 18 year life of mine plan, the current maximum water consumption in any 1 year is 1,200 acre feet per year. So the permit in essence is 3 times greater than the current requirement for water. There's a very strong aquifer that sits 2,000 feet below the surface. We're about 1,000 feet below the current base of the pet shell. And we have wells which monitor that aquifer on a daily, annual basis. We see more than enough volume of water to satisfy all of our business needs.

8:14 Just in behind the open pit, you can see the surface stockpile. I'm happy to report that further infill drilling on the stockpile has now moved it up into the indicated category ahead of the PFS, which is important. As we said earlier, only measured and indicated resources can convert into proven and probable reserves. Thank you, Alison. And then just lastly on this slide, obviously this is the global 43-101 resource. It only shows the leachable material, which is part of our PEA and will be part of the PFS. So it doesn't include the primary chalcopyrite. But as far as the oxides and the enriched material are concerned, you can see currently we have 900 million pounds with a total soluble grade of just under 0.7%.

9:09 You can see in the inferred material there's 670 million pounds at a 0.33 total soluble percent. And then notice how when we go underground, the grades significantly improve both in the indicated category and in the third category,

9:26 somewhere between 0.9 and almost 1% total soluble copper. Those grades are quite obviously important to us once we go underground. But as you will shortly see from the current exploration programme, a lot of the new intersections that we're seeing have grades greater than 1% total soluble copper for the leachable material. Thank you, Alison. And with that, I'm going to hand over to Anthony. Thanks, George. On the next couple of slides, I just wanted to talk to the exploration opportunity of Park Salyer. Park Salyer is located to the south west of the Cactus Project and on contiguous land. We see that Park Salyer has the opportunity or the potential for a scalable underground deposit that can expand on our cactus PEA case.

10:23 But Park Salia is not actually a new exploration project. It was discovered in the 1970s and the high grade that we're following up on now is actually interpreted in the early 1980s.

10:37 We've outlined in our press release an exploration target for Park Salyer, an underground target with potential leachable material of 40 to 90 million tonnes of between 1.05 and 1.3%

10:54 soluble copper. And when we combine that in with the primary that represents a target, an underground target of between 1 to 3 billion pounds. If we just go to the next slide, Alison. Down in the bottom left-hand corner there, we actually have the holes drilled on the project to date. So in the early to, oh, sorry, the mid to late 1990s, ASARCO actually drilled holes S200 and 201 and hit good enrichment material as well as oxide. We then followed that up in 2020 with ECP 18 and 19. And we continue to see good grades and we saw improved grades and improved thicknesses heading to the north.

11:42 And then more recently at the end of 2021, we drilled holes ECP 42 and ECP 45, which we released last week and they continued that trend. So if we just go to the thing actually I want to highlight on this slide is there's 2 sections that I'm going to show on the next 2 slides, A to A prime and B to B prime. So A to A prime, this is actually the main trend of the mineralisation that we've been following to date. You can see ECP 42 was actually an infill hole between ECP 19 and S200. But ECP 45 was an extension of mineralisation to the north and this hole is really important to us because what it showed was if you look at the upper contact between the conglomerate and then the mineralised bedrock, there was actually quite a drop in that depth to the bedrock of about 200 feet and all of our zones are about 200 feet deeper.

12:47 The important thing about this is that what we actually saw is in ECP45, there's thicker and more continuous mineralisation. In the holes to the south, we have seen some post-enrichment localised leaching throughout the holes. And This was something that was similar to what was seen in Cactus West in the pit. But as we've come into ECP45,

13:12 that little bit of extra depth has actually kept it out of that leaching profile. And so we've seen thick mineralisation of 595 feet of 1.29% copper in the enriched and 70 feet of 1.16% copper in the oxide. And if we just go to the next slide, this is a long section through the project and through the middle there you can see Cactus West and Cactus East. Cactus East being the deeper underground portion of the deposit. That's been down dropped into a block and has thick high-grade mineralisation which forms that part of our existing resource.

14:00 We see a similar thing at Park Salyer over on the left hand side where ECP 45, we can see that drop into the next block down. The exciting thing about this hole is that it's seen mineralisation and continuous thicknesses and grades that are consistent with Cactus East and actually the thickness is even thicker than what we've seen at Cactus East. The other thing you can see just to the right of ECP 45 there is, it goes on to the Bronco Creek lands that George mentioned.

14:36 That was about 140 feet to the east of PCP 45. So we knew that as we continued drilling and we see we're seeing grade and thickness improve to the north. We also knew that part of the deposit was going to be on in the east going onto the Bronco Creek lands. And so being able to make a deal on that land is really important to us. Cause we see that about a third of that property has potential to host the contiguous Park Salyard deposit. If we just go to the next slide, this is just a couple of core shots. This is ECP45, very similar to what we see in the system at Cactus, it's hosted in granite and 2 styles of mineralisation.

15:27 So we have fine-grained disseminated mineralisation, which is quite hard to see, but very sort of small little specks of chapsite. And then you'll see some darker lines going through, which are the chapsite veinlets. And what we tend to see is that we get a base of disseminated mineralisation and where we see the really high grades is where we see an increasing density of those veinlets. And so if we come through to hole ECP 42, we can see that that had a smaller section of mineralisation, but it did have higher grade mineralisation. So the box on the right hand side is actually running just under 5% copper, has that disseminated mineralisation, as well as an increasing

16:20 density of veinlets. And there's also clots of chalk site there. Thanks, Anthony. So if we just sort of look at the company's current enterprise value, we see a value of around about 130 million US dollars. And we believe through the bankable feasibility study and the pre feasibility study with organic growth from only the leachable material that's currently in the resource model, we believe we can be looking at a production profile of between 80 to 100 million pounds of copper cathode on an annual basis. That compares obviously favorably to the current average of 56 million pounds, which is currently in the PEA.

17:11 If we start to compare that to some other of our peer groups out there, obviously you'll see that Copper Mountain is currently producing about 90 million pounds of copper cathode on an annual basis. It currently has an enterprise value of around about 800 million US dollars.

17:31 We don't know the debt to equity split yet because obviously we need median reserves as part of the PFS and a mine plan and a mine schedule therefore that we have more confidence in. But you know if you look at the relatively low capital intensity for the project and the PEA of 124 million. Obviously we know those numbers are going to escalate but we certainly believe that you know they're going to be very manageable. But we're going to be a company in the next 12 to 18 months once the project financing is in place that will have

18:06 sub 130,140 million shares issued and outstanding on a fully diluted basis and potentially have an enterprise value anywhere between 500 million to 1 billion US dollars. So, you know, if you take a look at those type of numbers and management can continue to execute on the business plan, then obviously, you know, at 2 dollars and 25, which our share price was this morning, there's a hell of a lot of upside from these levels post project financing. Thank you, Alison. So just since we completed the IPO last year in November, Today we have 70 million shares issued. The options and warrants are in the money.

18:52 On a fully diluted basis, we're sitting with about 81 million shares issued. You'll see now that the company has virtually

18:59 no debt, only $1 million due to Tembo Capital. We would anticipate that in the next 6 months in preparation for the project financing and the debt component of that, we would pay that debt off so the company will have a nice clean balance sheet. We have currently 4 banks covering the company with a target price of $2.95 to $4 Canadian with a consensus at $3.15. I can tell you there are another 2 to 3 banks currently looking at the company and we would anticipate by the end of the year probably we would add at least another 2 to 3 that would have us under coverage. Again just to recap, it's always important that senior management and particularly the CEO have some real skin in the game. Since joining the company, I've put in 2.8 million Canadian dollars of my own money at a weighted average price of $2.48 Canadian.

19:58 Thank you, Alison. So just finally, why ASCU?

20:04 Well, to recap, obviously, the jurisdiction in Arizona is a Tier 1 jurisdiction. It's a brownfield site. We have access to some capital equipment already in place, infrastructure already in place. Today we have a compliant resource consisting of 1.6 billion pounds of indicated resource and 1.9 billion pounds of inferred resource. That's the oxide, the enriched and the primary material. The PEA revealed a relatively low capital intensity of only $124 million. That will rise as part of the PFS and bankable. Of course, based on what's going on with the inflationary pressures out there just in the general public. But as I said, very manageable.

20:52 We have an 18 year mine life of 56 million pounds of copper cathode production. You multiply those 2 numbers together, It's 1 billion pounds produced over 18 years from about 1.2 billion pounds of contained copper. There's still 1 billion pounds of leachable material sitting in the ground. And of course, there's over 1 billion pounds of primary chalcopyrite material still sitting there as well. The resource was ran at a conservative copper price of $3.15 a year ago. Financial and economic model was run at $3.35. And at an NPV 8 after tax, It gave us $312 million US dollars and an IRR after tax of 33%.

21:38 As you know, the entire property we have is on private land. That completely streamlines the permitting process. We've applied for an amended aquifer protection permit, which also includes not just the surface stockpile, but includes the pet layback and the underground component. That application went into the Arizona Department of Environment and Quality in mid-October of last year. And we would anticipate that based on discussions with ADEQ at some juncture towards the end of March, we will be in possession of the amended APP permit well within the 180 days period that is now currently underway.

22:21 As we've spoken about, there's huge exploration potential both at Cactus and at Park Salier and now Bronco Creek and the Northeast extension. We would anticipate with a successful initial drilling campaign in the first half of this year, we would probably want to accelerate our exploration in the second half of the year. And with that, I'm actually going to stop there and I'm going to open up the floor and take any questions that may have come through in the interim. Great, thank you so much. So if you do have a question, feel free to submit them now, but we have a few here. So with success, would you consider accelerating drilling at the Park Slayer or and also how many drill holes have been completed and how many are left in the program?

23:07 Yep, so we have $3 million US dollars in our expiration budget for Park Salier. As of this morning, 3 holes have been drilled. We've released 2 of those holes to the market last week. And with the third hole now being completed, there are 9 holes remaining in an initial 12-hole program. Remember, there were 2 holes drilled early last year and then we have access to 2 historical holes which are sarco-drilled I believe in the early 2000s. So that program will be wrapped up by the summer of this year By the time we get the assays back from the laboratory, that'll give us an internal resource model and then in all likelihood we would probably then want to accelerate the exploration campaign in the second half of the year.

23:59 The goal is to produce a maiden resource on Park Salier and probably that third of the land package at Bronco Creek at some juncture before the end of the year and incorporate that information into our bankable feasibility study on the main cactus project. Great, well, I think you just answered Eric's question, which was exactly that, but he has another one. What condition is the on-site rail spur in and is it ready for industrial usage? Ian, maybe you could answer that one. Yeah, sure. Obviously, it's there and we're certainly well aware of the opportunity that provides. At the moment, it's not operational. The spur is disconnected from the main line, which is just across to the south of the Casa Grande Maricopa Highway.

24:55 So there's some work to do there to reinstall that connection to the spur. And then as part of feasibility studies, understand if we use that spur, where it goes and how we connect it to the site. So some work to do there. Thank you. And what is your cash burn this year? And when will you need to raise cash again? Well we're fully funded through to the end of the year for the basic budget. So there's about $22 million being spent out at the site this year and then over and above that there's a $7.5 million land payment to be made to LKY, which actually the company made last week to LKY.

25:42 So we're fully funded through to the end of the year and the bankable feasibility study and hopefully we'll be announcing the project financing at that juncture in time. Thank you. Are you drilling Cactus East and the Cactus Northeast extensions in advance of updated resources and reserves? Ian, do you want to take that one? Yeah, we're absolutely drilling Cactus East as well as Cactus West. As Eric and George articulated earlier, we completed sort of the indicated drill program for both of those facilities and now we moved on into the measured side of things in anticipation of BFS activity. We haven't put together a plan yet to drill the Northeast extension, other than to say that it's definitely on the radar.

26:36 And we're reviewing that opportunity at the moment. So there's 4 historicals on there that we have data on, and we'll build a plan off of that. Great. Thank you. Harry is asking, what are your thoughts about alternative leaching technologies such as, for instance, being developed by Jetty Resources? Is that something that could impact your project? Ian, why don't you take that one? Sure. Absolutely. We've given much thought to alternative leaching resources. Without getting into the details, we actually have a testing agreement in place with JETI at the moment, and we're doing some work on that to understand potential leaching over chalcopyrite ores.

27:23 Now, all that being said, we're likely not in the position to disclose much by, say, PFS timeframe, but we do have a view towards having something disclosed with respect to calcifier leaching by the time BFS is wrapped up. So yeah, we're working on that at the moment. John's asking what does Cactus East underground contribute to the production profile? Does Park Slayer have the same potential? And if the drill out proves target, when would it fit on expansion? Ian, why don't you take that one? Yep. Yeah, Cactus East is, per our current integrated PEA, Cactus East is certainly the prize at the moment, if you will.

28:19 Parts of it are double and near triple the grade of cactus west. With, you know, call it three quarters of the material being enriched or calcicide material. So As far as the plan is concerned from the integrated PEA, it is over half of total production. The remaining production coming from obviously Cactus West layback and the stockpile resource. So Cactus East is a big part of our production plan and it's certainly a focus as we go through the studies we're currently conducting. And then what were the other parts of that question? So we saw Park Salyer and the potential that it could provide as well. Obviously drilling will play that out.

29:11 But you saw that ECP 45 and call it 600 feet of plus 1% enrichment material, which was a big surprise to us and obviously a nice surprise. So we'll play that out this year when we act upon our drilling program and see what we can come up with for Park Salire. But Anthony gave sort of the high level numbers of the potential there. So we're pretty excited about it, and we'll see what happens. Thank you. John's asking how much is the estimated capital costs to start up first output, and also the estimated expo, admin, and other expenses not capitalized on in the interim prior to profitable output. Ian, you want to take that one?

29:58 Yeah. Estimate, I mean, John, from the integrated PEA, we see a capital intensity of about, it's about 70 to 80 million to get going. The total development capital over the year, over the life is, actually, sorry, initial capital is $124 million to get going. And that includes building leach pads, obviously the SXCW, and a pitch strip startup. Obviously, there's sustaining capital layered in as life goes on, but as George mentioned earlier, we do see that sort of $125 million going up in PFS, The details of which obviously we're working through at the moment.

30:50 And the other thing to point out is that capital supports a certain size plant, which we're reviewing at the moment as well. So that all feeds into how we approach PFS expenditures and what's the ultimate size of that plant going to be and then the leach pads and other ancillary development capital that goes along with it. As far as I think the question is towards GNA, and I think, George, if I'm right, it's about 4 million a year on an annualized basis for GNA for items that are not included in that capital number. Yeah, it's a little bit higher than that, but yeah, that's close. Yeah. Great, thank you. Eric's asking, what are the host rocks and are they similar to cactus and cactus northeast?

31:42 Maybe Anthony can jump in there. Yeah, the host rocks are granite and porphyry, fairly simple geology, and it's actually part of the same deposit as cactus. So the entire deposit was actually formed further to the south west and later was moved along a basement fault to the north east. So it's actually the same deposit that's been dislocated towards the north east. You might see the same ice drops in more cases and the same mineralisation structures. And white rocks in cases and same in polarization. All right.

32:27 Lucas has a question. He is asking, Can you speak to the hypogene sulfide mineralization intersected at Park Slayer and if the company will be targeting this or focusing more on the leachable material? Yeah, obviously we're going to be focused primarily on the enriched supergene material, the chalcocite. It's the same style of mineralization that we see at Cactus West and Cactus East and probably the Northeast extension. So that's our primary plan for the PEA, PFS and Bankable Feasibility Study. But as Ian has already alluded to, we do have a CA with Jeti Technologies. So, you know, as part of the drill program, we won't just be drilling the enriched material.

33:17 We will also be drilling out the primary material as well to add the chalcopyrite into an updated maiden resource on Park Salier at some juncture before the end of the year. If the JETI technology proves favourable and ultimately there's, you know, we can take that mineralisation and make it economically viable, then it makes sense now to drill it while we're there. Thank you. Paul is wondering who are your nearest comparable producers of the same size? Ian, do you want to take that one? I think we had a graph up earlier of our peers. If I think about Arizona, we have Carlotta that's obviously on the downswing, but sort of the same size as footprint wise.

34:17 But I can't think of a competitor close by that's sort of in that range within Arizona. They're usually much larger than that. So you're talking about your free ports and resolution, that sort of thing. All right. Thank you. Does your company aspire more to build mines and produce yourself or would you rather sell it to a larger copper miner, John is asking? Yeah, look, I think our business model is built around actually de-risking the project from a technical side, getting the project financing in place. The skill set of the board and the management team is definitely one of managing and operating minds and ultimately that's our goal here is to turn this into a very solid copper, you know, mid tier company with assets and the heartland of the Arizona copper belt in a very safe jurisdiction.

35:18 Thank you. Harry is asking, can you talk about what your thoughts are on how much of the CAPE Act would be covered by debt financing? Would you lean towards loans, streaming or venturing out part of the project? Yeah, on the project financing, as I said earlier, we don't really have haven't seen the maiden reserves yet and therefore, you know, the mine plan that we currently have is built around the PEA with with inferred resources. So until we see the maiden reserves and a mine plan that we have more confidence in, it's difficult to say what will be the split between debt to equity. But I can say that at the moment we've been approached by many debt providers, including commercial banks, some of the private debt lenders as well. So we're going to have many, many options and lots of flexibility when it comes to the project financing and specifically the debt on this one towards the end of the year.

36:22 Thank you. And what will be the approximate timeline to get into production? Well, the PEA currently shows that once the project financing is in place, then it's an 18-month construction and development period. And of course, that's also contingent upon having the necessary permits in place. As I said earlier, we will have the amended APP permit by the end of March. As we move into the second quarter, we would then apply for the construction and industrial permit and the mine land reclamation permit. We're giving ourselves at least a couple of months to have those administratively accepted by the regulators.

37:10 And then once that occurs, the clock then starts ticking, there's 180 day period, whereby the regulator must give us a response to our application. And within that 180 days, there's a 30 day public consultation period. So if we make an application in the second quarter, it's administered and it'll be accepted by the beginning of the third quarter. That tells us that by the end of the calendar year we should be in possession of the construction and industrial permit and the mine land reclamation permit which are going to be then essential to be shovel ready in the first half of 2023. If we have the project financing in place and the permits are there, and the PEA says 18 months construction development, which gives us first production before the end of calendar 2024.

38:02 Great. Thank you. And is the permanent process of the newly leased Bronco Creek land any different? No, it's not. It will follow exactly the same process that I've just described. And obviously we're dealing with all the same regulators, the Arizona Department of Environment Quality and the Arizona State Lands Department. Excellent. Well, thank you all so much. That concludes the Q&A for today. I want to thank everyone who joined and asked great questions and also to George, Ian, and Anthony for joining us and taking us through the presentation and the Q&A. If you do think of another question after this summit, feel free to reach out directly to Arizona Sonoran Copper team, their contact information is on the slide here. You can also find more information on their website, ArizonaSonoran.com.

38:56 And again, this has been recorded and you can rewatch it on SIX.com afterwards. But I'll pass it back to you, George, if you have any final closing remarks. Well, for those of you that have followed the company, and obviously we've been on 6 for a couple of presentations now, I think this is our third one, you'll have seen if you go back to those old presentations that we outline what our plans are. And I think you'll have seen since the company IPO some 4 months ago, we've made great progress. We've delivered on our milestones and our objectives and we continue, we will continue to do that throughout the year. At $2.25 Canadian share price, I certainly believe that there's a lot of upside as we continue to de-risk the project. I'd like to thank everybody today for jumping on the call and following the company and I look forward to updating you a little bit later in the year with some more exciting news.

Follow Arizona Sonoran Copper Co., Inc. into a list and get an email when it puts out news.

Latest news releases

Companies on this call

Speakers

Speaker profile George Ogilvie

George Ogilvie

President, CEO & Director at Arizona Sonoran Copper Company

George Ogilvie, has over 32 years of management, operating and technical experience in the mining industry. Mr. Ogilvie was until most recently the President & CEO of Battle North, a position he was appointed to, in 2016 whilst the company was under financial insolvency & restructuring proceedings. During his 5 year tenure at Battle North, Mr. Ogilvie and his team successfully completed a turnaround of the company resulting in an increase in the resource base from 400 k ounces Au to approximately 1.3 million oz Au, completion of a positive bulk mining reconciliation program resulting in de-risking of the project, delivery of a preliminary economic assessment and follow on feasibility study in relation to the project with a post-tax IRR of 50% and completion debt and equity financing of over C$100m associated with project construction. Battle North was acquired by Evolution Mining Limited in May 2021 at a 45% premium to the prevailing spot price. Prior to this, Mr. Ogilvie was the CEO of Kirkland Lake Gold Inc. where he and his team implemented a turnaround strategy which included, amongst other items, improving operations at the Macassa Mine and the acquisition of St. Andrew Goldfields, resulting in significant returns for shareholders. Previously, Mr. Ogilvie was the CEO of Rambler Metals and Mining PLC, where he and his team guided the evolution of the company from grassroots exploration to a profitable junior producer. Mr. Ogilvie began his mining career in 1989 with AngloGold in South Africa and he subsequently held other roles at the Ruttan Mine in Northern Manitoba for HudBay Minerals Inc., the McCreedy West Mine and also as Area Manager for Dynatec Corporation. Currently, Mr. Ogilvie also serves on the board of Rupert Resources Ltd. Mr. Ogilvie received his B.Sc. (Hons.) in Mining and Petroleum Engineering from Strathclyde University in Glasgow, Scotland. He is a Professional Engineer and also holds his Mine Managers Certificate (South Africa).

Speaker profile Anthony Bottrill

Anthony Bottrill

Resource Geologist at Arizona Sonoran Copper Company

Anthony is a Consulting Resource Geologist with over 22 years of experience in the mining industry and expertise across numerous countries and a range of commodities: from low tonnage high grade precious metals to bulk tonnage base metals. He provides resource modeling and technical services consulting skills for underground and open pit projects, from exploration and development through to production. Anthony was previously the Corporate Mineral Resource Manager for Klondex Mines Limited and has worked for various mining companies including BHP Billiton and Newmont. Anthony is the Principal Resource Geologist for InterGEO Resource Consulting based in Brisbane Australia, He has a bachelor’s degree in Geology with Honours in Structural Geology from the University of Adelaide and is a member of the Australian Institute of Mining and Metallurgy (AusIMM).