Turquoise Hill Resources Ltd.

Turquoise Hill Resources — Bank of America Merrill Lynch Global Metals, Mining & Steel Conference 2016

18 slides from Turquoise Hill Resources's conference presentation, May 10, 2016

  1. Slide 1: The future of Oyu Tolgoi is underground

    Slide 1: The future of Oyu Tolgoi is underground

    Bank of America Merrill Lynch Global Metals, Mining & Steel Conference MAY 10 – 12, 2016 The future of Oyu Tolgoi is underground Developing the third-largest copper mine

  2. Slide 2: Forward-looking statements

    Slide 2: Forward-looking statements

    Forward-looking statements This presentation includes certain “forward-looking information” within the meaning of applicable Canadian securities legislation and “forward-looking statements” within the meaning of the “safe harbour” provisions of the United States Private Securities Litigation Reform

  3. Slide 3: Investment summary

    Slide 3: Investment summary

    Investment summary Re-starting underground development • May 2015 - Underground Development Plan resolved shareholder issues and maintained Investment Agreement • December 2015 - Signing of project finance ($4.4 billion) • May 2016 – Notice to proceed and 2016 feasibility study approved • Targeting

  4. Slide 4: Multi-generational copper asset

    Slide 4: Multi-generational copper asset

    Multi-generational copper asset* Southern Oyu Open Pit ~1,000Mt (reserve) 0.45% copper; 0.31 g/t gold Heruga Hugo South ~700Mt (resource) ~300Mt (resource) Plant 0.42% copper 1.07% copper 0.43 g/t gold; >100Mlb moly 0.06 g/t gold Hugo North Lift 1 ~500Mt (reserve) Hugo North Lift 2 1.66% copper; 0.3

  5. Slide 5: Hugo North Lift 1 development timeline

    Slide 5: Hugo North Lift 1 development timeline

    Hugo North Lift 1 development timeline Complete Convey to Surface Sustainable Underground Production Complete Concentrator Project Start Upgrade Complete Ramp-up 1st Draw Bell Firing 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 Set-Up Excavation (Lateral / Mass / Vertical) Underc

  6. Slide 6: Medium-term timeline

    Slide 6: Medium-term timeline

    Medium-term timeline 2015 – 2016 2016 – 2021 2021 – 2026 2026 + • Project finance • Hugo North Lift 1 • First draw bell • Hugo North Lift 2 signed Construction production • Hugo South • Completed • Additional $1.6 billion • Ramp-up to full feasibility study project financing debt production • Board

  7. Slide 7: Multiple development options

    Slide 7: Multiple development options

    Multiple development options Source: 2014 Oyu Tolgoi Technical Report Production creep targeted along with expansion Actual operating performance will inform choice of expansion path A decision to expand the concentrator is not required for a couple years 7

  8. Slide 8: Project financing – flow of funds

    Slide 8: Project financing – flow of funds

    Project financing – flow of funds Today1 At project financing drawdown Payable to Turquoise Hill* Receivable from Oyu Tolgoi* Proceeds: $4.4 billion2 $4.1 billion3,4 $4.1 billion4 Shareholder loan: $7.0 billion Shareholder loan: $7.0 billion Payable to Turquoise Hill* Receivable from Oyu Tolgoi* Dep

  9. Slide 9: Production highlights

    Slide 9: Production highlights

    Production highlights Concentrator throughput Concentrate production ('000 tonnes) (‘000 tonnes) 788.5 34,537 27,872 563.6 215.5 210.3 231.8 229.5 9,025 8,632 9,369 9,662 7,512 130.9 Q1'15 Q2'15 Q3'15 Q4'15 Q1'16 2014 2015 Q1'15 Q2'15 Q3'15 Q4'15 Q1'16 2014 2015 Q1’16 throughput averaging above name

  10. Slide 10: Financial highlights

    Slide 10: Financial highlights

    Financial highlights Cash position Operating cash flow ($'000,000) ($'000,000) $1,482.2 $718.5 $1,310.4 $1,343.9 $650.5 $1,200.0 $954.2 $862.8 $239.2 $171.7 $195.9 $138.1 $101.5 Cu:$2.66* Cu:$2.77 Cu:$2.39 Cu:$2.20 Cu:$2.11 Cu:$3.10 Cu:$2.51 Au:$1,219* Au:$1,194 Au:$1,124 Au:$1,106 Au:$1,183 Au:$1,2

  11. Slide 11: Copper industry overview

    Slide 11: Copper industry overview

    Copper industry overview Post-2020 copper mine C1+sustaining normal cost curve C/lb, 2016$ 400 Third largest Oyu Tolgoi copper mine after Other Mines planned expansion1 300 Top 10 copper deposit by 200 contained reserves and resource2 One of the largest 100 gold deposits by contained reserves and re

  12. Slide 12: Long-term copper fundamentals strong

    Slide 12: Long-term copper fundamentals strong

    Long-term copper fundamentals strong Copper mine supply/demand outlook Copper market likely to see small surplus in coming years. Mt Base Highly Probable Primary Demand 30 Ongoing attrition at existing Forecast mines driven by declining grade 25 Continued demand growth 20 requires new capacity in th

  13. Slide 13: Turquoise Hill – a long-term growth opportunity

    Slide 13: Turquoise Hill – a long-term growth opportunity

    Turquoise Hill – a long-term growth opportunity Pure copper and gold exposure Positive operating cash flow and focusing on asset optimization Agreed path forward for development of the high-grade underground mine Significant growth, development and expansion opportunities Resources located near Chin

  14. Slide 14: Appendix

    Slide 14: Appendix

    Appendix

  15. Slide 15: Shaft and underground development status

    Slide 15: Shaft and underground development status

    Shaft and underground development status Shaft 1 completed in 2008, 1,385m Off-shaft lateral development 16km 2008 – Aug 2013 Shaft 2 currently 1,167m, ~100m left Shaft 5 currently 208m, ~1,000m left Extensive geotechnical data collection program Demonstrated performance and quality 15

  16. Slide 16: Ore flow

    Slide 16: Ore flow

    Ore flow APEX LEVEL Lateral Development lg UNDERCUT LEVEL ~-@ > eC Lateral Development Undercutting Undercut Mucking & Ground Support EXTRACTION LEVEL \vaa"/ «>t PB paid: Lateral Development & Ground Support Drawpoint / Drawbell Production Construction Secondary Breaking \ rere Foe: DUMP AT Fill Tru

  17. Slide 17: Oyu Tolgoi at China's doorstep

    Slide 17: Oyu Tolgoi at China's doorstep

    Oyu Tolgoi at China’s doorstep 17

  18. Slide 18: Made in Mongolia

    Slide 18: Made in Mongolia

    Made in Mongolia Mongolians now occupy 95% of Oyu Tolgoi roles Since 2010, in-country spend of $5.5 billion (Mongolian suppliers, salaries, taxes and other Government payments) Partnered with more than 800 local suppliers in 2015, accounting for over 50% of procurement spend In April 2015, Oyu Tolgo