The Lunsemfwa solar power project in Zambia, built by POWERCHINA, has received its taking-over certificate, which the company says marks the completion of construction. POWERCHINA says it is Zambia's first project to combine solar power generation with hydropower regulation.

Key details

  • The project is in Zambia's Central Province and is rated 27 MWp/20MWac, meaning 27 megawatts of peak solar panel output and 20 megawatts of alternating-current output to the grid. It has an installed capacity of 27 MW.
  • It includes a supporting 33kV-to-66kV step-up substation, which raises the voltage of the power, and two approximately 1-kilometer-long 66kV transmission lines.
  • The project uses the existing infrastructure of a hydroelectric power station to combine solar generation with hydropower regulation, an approach POWERCHINA calls a hydro-solar complementary model.
  • POWERCHINA's team worked on the design, procurement, construction and commissioning stages, and the project connected to the grid 26 days ahead of schedule.

6ix AI wrote this summary from the release below and checked it against the release.

The project is Zambia's first to combine solar power generation with hydropower regulation.

The Lunsemfwa 27 MWp/20MWac PV Project in Zambia, built by POWERCHINA, recently obtained its taking-over certificate, marking the successful completion of construction. The project is expected to play an important role in optimizing Zambia's national energy structure and promoting renewable energy development.

Located in Zambia's Central Province, the project has an installed capacity of 27 MW. It includes a supporting 33kV-to-66kV step-up substation and two approximately 1-kilometer-long 66kV transmission lines.

By fully utilizing the existing infrastructure of a hydroelectric power station, the project combines solar power generation with hydropower regulation. It is the first new energy project in Zambia to be built using a hydro-solar complementary model.

Throughout the project's design, procurement, construction, and commissioning, POWERCHINA's project team allocated personnel, equipment, and materials, optimized construction plans and workflow coordination, and ensured every stage met strict quality standards.

As a result, the project achieved grid connection 26 days ahead of schedule, earning high praise from the project owner and other stakeholders for its proactive execution and high-quality delivery.

The handover of the project further consolidates POWERCHINA's brand influence in the Zambian energy market and provides a model for the country as it explores the integrated development of traditional hydropower and new energy.

Power Construction Corporation of China, Ltd. on 6ix

Story so far

Earlier from Power Construction Corporation of China

Later from Power Construction Corporation of China

All Power Construction Corporation of China news releases