PERTH, Australia, Feb. 21 /CNW/ - Mirabela Nickel Limited (TSX: MNB, ASX: MBN) is pleased to announce that it has achieved another major milestone in developing its world-class nickel sulphide nickel project in Brazil with the follow-up licenses for the Santa Rita project now obtained. As previously announced, the Company was granted the principal development approval (the Installation License which incorporates environmental approval) in October last year. The follow-up licenses subsequently obtained include:
- Mining Concession - Deforestation Authorization - Water Authorization
In addition, the acquisition of all the necessary surface land rights has been completed.
"Construction of the Santa Rita project commenced last November on site infrastructure, but with the follow-up approvals now out of the way we can move to full construction on all fronts to maintain the project on schedule," said Managing Director Nick Poll. "We have worked hard to explain our intentions and the project's impact to the local communities. The resulting community support and the need for economic development in the state of Bahia have been strong drivers behind state and federal government support for the project," he said.
The Company expects to employ about 1500 people directly and indirectly from the populations of Itagiba (17,000 people) and Ipiau (43,000 people) both within 6kms of the project. "We are finding great people who live within 15 minutes drive of the project that have a good level of education and plenty of local knowledge," said Mr Poll. "The local people will always be an important asset for our project. We are pleased to be developing the local workforce and to be contributing to nearby communities," he said.
Construction commenced on the project in November 2007 with basic infrastructure such as a bridge, all-weather access roads and site offices. Much of the essential infrastructure was already in place, such as a state highway and an asphalt airstrip within 4km of the project and hydro-electric power within 6km. "In terms of pre-developed local infrastructure, it doesn't get much better," said Mr Poll.
Pre-stripping of the mine in both the Northern and Southern zones has been underway since January, as most of the project area is open farm land.
"We have made great progress over the last four months and have not had any problems obtaining heavy machinery for the site works and mine pre-strip," said Mr Poll. "Brazil has a large industrial base that allows great flexibility for acquiring equipment, because we are not competing so closely with the rest of the mining industry. For example, the trucking fleet was previously deployed on constructing a hydro-electric power dam. As a result, Brazil's mining industry is well positioned for growth when it comes to the competitive world of building and operating mining projects," he said.
Mirabela has deployed an experienced team of Brazilian project engineers led by Raphael Bloise, who previously managed construction of the Sossego project - a 13mtpa copper sulphide project in Brazil. This team is supplemented with extensive nickel processing knowledge from a team originating from Perth and including Narayan Krishnan, who was involved in the commissioning of Mt Keith, and John Knoblauch, who was involved in the commissioning of Sally Malay.
Next major milestones for the Company will be the completion of debt and off-take agreements, expected within four months. Delivery of long lead time items, including a gyrational primary crusher, sag mill and ball mill is expected in Q4 this year.
Mirabela recently announced a Proven and Probable mining reserve of 84mt grading 0.61% Ni for its open-cut pit and a throughput upgrade from 4.0 to 4.6mtpa to produce 18,500tpa of nickel in concentrate. Drilling results from immediately below the open-cut mining reserve include intersections up to 135m grading 0.83% nickel. These intersections are expected to increase open-cut mining reserves, with the next resource estimate expected in about 4 months.
Background
Mirabela Nickel is listed on the Australian and Toronto stock exchanges. With an open-cut mining reserve of 84mt grading 0.61% Ni, Santa Rita is the largest greenfields nickel sulphide discovery in the last 12 years and the third largest open-cut nickel sulphide mining reserve worldwide.
Construction of a nickel sulphide concentrator commenced in November 2007 and is progressing well. The plant is expected to produce 18,500t a year of nickel in a sulphide concentrate from one open-cut mine starting from mid 2009. At this rate of production the project is expected to have a mine life of at least 18 years. Studies are underway to increase plant capacity to 25,000t a year within the first year of production.
(signed)
Nick Poll
Managing Director
Caution Regarding Forward Looking Statements: There can be no assurance that an expanded mineral resource or reserve will be established at the Santa Rita Project. The forward-looking statements made in this news release are based on assumptions and judgments of management regarding future events and results. Such forward-looking statements, including but not limited to those with respect to the construction and development of a 18,500 tonnes per year and subsequently a 25,000 tonnes per year nickel sulphide concentrator and a nickel smelter at the Santa Rita Project and the required capital expenditures and estimated future production and operating cash costs involve known and unknown risks, uncertainties, and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any anticipated future results, performance or achievements expressed or implied by such forward-looking statements. Such factors include, among others, the actual market prices of nickel, the actual results of current exploration, the actual results of future mining, processing and development activities, changes in project parameters as plans continue to be evaluated, as well as those other factors disclosed in the Company's filed documents.