Kuya Silver Reports Growing Silver Production at the Bethania Project in Q1 2026
Exits Q1 with 100 Metric Tonnes Per Day Production and Confirms Plan to Achieve 350 Metric Tonnes Per Day by the End of 2026 Kuya Silver to Report Q4/Year End

About this update from Kuya Silver Corporation
Exits Q1 with 100 Metric Tonnes Per Day Production and Confirms Plan to Achieve 350 Metric Tonnes Per Day by the End of 2026 Kuya Silver to Report Q4/Year End Financial Results Prior to Market Open on Friday, April 24 and Hold a Conference Call Webinar on April 28, 2026 to Update Investors All references to dollar amounts are references to U.S. Dollars, unless otherwise stated Toronto, Ontario--(Newsfile Corp. - April 22, 2026) - Kuya Silver Corporation (CSE: KUYA) (OTCQB: KUYAF) (FSE: 6MR1) (the "Company" or "Kuya Silver") is pleased to report record quarterly production and provide an operational update for the first quarter of 2026 at the Bethania silver project, which delivered record daily and quarterly production rates as the ramp-up continued to track higher during the three month period. In light of the significant progress to date, the Company continues to expect the completion of its Phase 1 ramp-up, achieving 350 metric tonnes per day ("tpd") production, by the end of the year. Operational Highlights 3,076 metric tonnes of mineralized material mined at Bethania, a significant improvement over Q4 2025 Milestone 100 tonne per day (tpd) throughput achieved at the end of March and early April, 2026 Continued strong underground development with record 398 meters advanced and 1,967 metric tonnes of development material moved to continue expansion of underground mining operations 91% of record quarterly revenue from Bethania came from silver in the quarter with an average selling price of $82/oz. Announcement of fully funded letter of intent to acquire the Camila plant to improve silver recoveries and operational control of material processing Cash position at the end of Q1 2026 of approximately $27 million Kuya Silver On Track To Achieve 350 tpd Production Rate At Bethania By The End of 2026 Given the successful mine development to date, and strong financial position, Kuya Silver expects to complete its Phase 1 ramp-up at the Bethania silver project by the end of this year. The Company plans to keep the market informed of the progress and will continue to provide details on the production growth on a timely basis. Christian Aramayo, Kuya Silver's Chief Operating Officer commented, "Another pivotal quarter for Kuya Silver. We achieved 100 tpd in March and have sustained it into April — a clear proof point in our ramp-up. With continued investment in d...
View stock analysis, news, and events for Kuya Silver Corporation