Investor Presentation
December 2024
Who we are
3
Central Puerto (NYSE: CEPU) has evolved to become the largest private Argentine generation company in terms of both installed capacity and power generation.
Central Puerto generation business at a glance
6,703 MW of installed capacity(1)(2)
A well diversified generation portfolio with 14 Power Plants
Market Share Dic-24(4)
A GT converted to CC
+ 140 MW/+60 USD MM EBITDA
Total new capacity: 421 MW Higher efficiency/dispatch
long term PPA
438 MW
Brigadier Lopez project
Thermal PPA portfolio
2,585 MW
thermal assets
largest private participant with equity stake in 3 combine cycles
Fully contracted: Renov.AR and MATER PPAs
mini-hydro assets
1 MW
a
solar assets
105 MW
wind assets
374 MW
hydro assets
1,440 MW
Steam/gas turbines(3)
2,083 MW
Combined cycles(3)
2,262 MW
Foninvemen program
Renewables portfolio
Spot portfolio(2)
Central Puerto, 15%
Pampa
Others, 45%
Energia, 11%
Genneia, 3%
Albanesi, 4%
MSU, 6%
Aes, 8%
YPF Luz, 7%
(4) Percentage share over total installed capacity as of Dec-24. Source CAMMESA
4
Source CAMMESA - corresponds to the total theoretical power of each asset. On April 26, 2024, the Secretariat of Energy requested CAMMESA to proceed with the disconnection of steam turbines COSTTV04 and COSTTV06 (470 MW in total) of Central Costanera, following a solicitation originally made by Enel, former owner of that plant, and followed up by the Company. This update has no impact on revenues: these turbines have not been operating since long time ago.
For more information, please refer to slide 18 "Annex 1 - Regulatory framework".
The 2,262 MW are remunerated under Resolution 59/23 (combined cycles).
Well diversified portfolio of generation assets
9
6
11
5
4
10
12
1 2
8 7
3
Assets in Operation
Technology
Power Capacity (MW)
Remuneration (MW)(3) PPA term
Installed(1)
Available(2)
Spot
PPA
1 Central Costanera(6) Thermal
1,789
1,692
1,692(4)
2 Central Puerto Thermal
1,747
1,645
1,645(4)
3 Piedra del Águila Hydro
1,440
1,440
1,440
-
-
4 Luján de Cuyo(5) Thermal Cogen
576
562
453(4)
109
2034
5 San Lorenzo Thermal 391 366 36 330 2035
Cogen
6
Brigadier Lopez Thermal
281
280
280
-
-
7
Genoveva I & II Wind
130
130
-
130
2040/2027
8
La Castellana I & II Wind
116
116
-
116
2038/2029
9
Guañizul II A Solar
105
105
-
105
2041
10
Manque Wind
57
57
-
57
2039
11
Achiras I Wind
48
48
-
48
2038
12
Los Olivos Wind
23
23
-
23
2030
Total
6,703
6,464
5,546
918
G E O G R A P H I C
F O O T P R I N T
Source CAMMESA, corresponds to the total theoretical power of each asset.
Net available power capacity reported to CAMMESA
MW over available capacity
PPA refers to the Res. 59/23 - For more information, please refer to slide 18 "Annex 1 - Regulatory framework".
5
The facility Includes 290 MW of combined cycles, 95 MW of cogeneration, 190 MW of gas/steam turbines and 1 MW of mini-hydro
On April 26, 2024, the Secretariat of Energy requested CAMMESA to proceed with the disconnection of steam turbines COSTTV04 and COSTTV06 (470 MW in total) of Central Costanera, following a solicitation originally made by Enel, former owner of that plant, and followed up by the Company. This update has no impact on revenues: these turbines have not been operating since long time ago.
Continuously expanding and diversifying our operated portfolio
2024 portfolio by technology
2%
6%
21%
7%
65%
Thermal Cogeneration Hydro Wind Solar
6
Installed Capacity(1) (MW)
Thermal
Hydro Renewbables
3,638 4,218
4,809
6,703
2017 2019 2021 2024
Thermal:
. Puerto Complex
. Lujan de Cuyo
Hydro:
. Piedra del Aguila
Thermal:
. Puerto Complex
. Lujan de Cuyo
. San Lorenzo Brigadier Lopez Hydro:
. Piedra del Aguila
Renewables:
. Achiras
.La Castellana I & II
. La Genoveva II
. Manque
Thermal:
. Puerto Complex
. Lujan de Cuyo
. San Lorenzo Brigadier Lopez Hydro:
. Piedra del Aguila
Renewables:
. Achiras
. La Castellana I & II
. La Genoveva I & II
. Manque
. Los Olivos
Thermal:
. Puerto Complex
. Lujan de Cuyo
. San Lorenzo Brigadier Lopez
. Central Costanera*
Hydro:
. Piedra del Aguila
Renewables:
. Achiras
. La Castellana I & II
. La Genoveva I & II
. Manque
. Los Olivos
. Guañizul II A**
(1) Source CAMMESA.
*:acquired by mid-Feb-23
**:acquired by mid-Oct-23
Availability of thermal units(1)
Steam & Gas turbines (%)
88%
86%
77%
74%78%
62%
65% 68%
74%
65%
50%
53%
96% 96% 95% 93% 97%
2020 2021 2022 2023 LTM4Q24
Puerto ComplexLujan de CuyoBrigadier LopezCostanera ComplexCombined Cycles (%)
89%
75%
91%
88%
91%
91%
86%
71%
68%
35%
93% 93% 97%99%
98%99%
2020 2021 2022 2023 LTM4Q24
Puerto ComplexLujan de CuyoSan LorenzoCostanera Complex(1) Availability reported by CAMMESA, calculated based on the total installed capacity of each power plant.
7
Renewables Energy Portfolio
RenovAr Program
Term Market (MATER)
La Castellana I
Achiras
La Genoveva I
Guañizul II A
La Castellana II
Manque
Los Olivos
La Genoveva II
Technology
Wind Farm
Wind Farm
Wind Farm
Solar farm
Wind Farm
Wind Farm
Wind Farm
Wind Farm
Capacity
100.8 MW
48 MW
88.2 MW
104.6 MW
15.2 MW
57 MW
22.8 MW
41.8 MW
Capacity factor(2)
45.2%
49.5%
50.4%
33.0%
54.1%
49.1%
52.9%
50.2%
Status
In Operation
In Operation
In Operation
In Operation
In Operation
In Operation
In Operation
In Operation
COD
August 2018
September 2018
November 2020
July 2021
July 2019
Dec-19 /Jan-20
February 2020
September 2019
Equipment
32 Units
15 Units
21 Units
358,560 Units
4 Units
15 Units
6 Units
11 Units
Awarded Price
Starting
61.5 US$/MWh
59.4 US$/MWh
40.9 US$/MWh
50.0 US$/MWh
nder MATER:
Adjustments
Annual adjustment factor + incentive factor
Main clients u
PPA Signing Date
January 2017
May2017
July 2017
July 2021
Term
20 years starting on COD
Equity stake in wind farms La Castellana I, Achiras I, La Genoveva I, La Castellana II, Manque, Los Olivos, La Genoveva II, owned through CP La Castellana S.A.U., CP Achiras S.A.U., Vientos La Genoveva S.A.U., CPR Energy Solutions S.A.U.; CP Manque S.A.U., CP Los Olivos S.A.U. and Vientos La Genoveva II S.A.U, respectively.
8
Calculated from CAMMESA data as total energy generated over theoretical energy production, for the quarter ended Jun-24. It includes losses and scheduled and non-scheduled maintenance.
Installed Capacity(3) MW 6,703 | Energy Generation | Revenues | Adj.EBITDA(4) | Net Income | Net Debt |
TWh | US$ MM | US$ MM | US$ MM | US$ MM | |
FY24 4Q24 | FY24 4Q24 | FY24 4Q24 | FY24 4Q24 | 4Q24 | |
21.6 5.4 | 671 168 | 288 65 | 52 (28) | 132 | |
+4% Y/Y +5% Y/Y | +25% Y/Y +71% Y/Y | 4% Y/Y 44% Y/Y | (73%) Y/Y (118)% Y/Y | -US$154 mm vs Dec-23 |
The results presented for the annual period 2023 and 4Q23 are negatively affected at a non-cash level as a consequence of the sharp devaluation of the local currency occurred in mid-December 2023. Given that the functional currency of the company is the Argentine peso, our Financial Statements are subject to inflation adjustment, while Company's figures are converted into US dollars using the end of period official exchange rate. Thus, given the significant disparity between inflation and devaluation for the period, it might affect comparability.
The FX rate used to convert Argentine Pesos to U.S. dollars is the reference exchange rate (Communication "A" 3500) reported by the Central Bank for U.S. dollars as of 31/12/24 or 31/12723, as appropriate. Annual figures are the sum of the quarterly results converted to dollars at the EOP FX rate of each period.
On February 22, 2024, it was published in the Official Gazette of the Republic of Argentina, the request submitted by Central Costanera for the decommissioning of steam generation units COSTTV04
and COSTTV06, for a total installed capacity of 120 MW and 350 MW, respectively. This was a request originally made by Enel, former owner of that plant, and followed up by the Company. This update has no impact on revenues since these turbines have not been operating since long time ago.
See "Disclaimer-EBITDA & Adjusted EBITDA" on slide 2 for further information. 4
+50 | |||
Adj. EBITDA | |||
by regulator | |||
8% | PPA - M | ||
18% | |||
PPA - Re | |||
35% | |||
PPA - T | |||
30% | Leagcy | ||
Legacy | |||
9% | |||
LTM 4Q24
| |||
contribution
of Operating Cashflow is secured by long term contracts in dollars with protection mechanisms
+US$ 74 MILLION
y framework
LTM 4Q24 collections under CVO
ATER (1)1
novAr (2)
hermal Units
- Res. 59 (3)
- Spot
61%
of Adj.EBITDA Through long term contracts, with prices set in US$ dollars
5 years -term Contracts partially set in US$ dollar
CVO receivables amount to approximately US$198 million as of Dec 31, 2024.
Interest: 30 days SOFR + adj. spread + 5%.
Pending collections: 41 monthly principal and interest installments due
May 2028.
LTM 3Q24
ts
10
(3) The percentage represents the total EBITDA generated by the combined cycles under Res 59. For more information, please refer to slide 18 "Annex 1 - Regulatory
framework".
Low leverage ratio and manageable short-term maturities
Debt Maturity schedule(1)(2) (US$ mm.)
Net Debt/ Adj.
EBITDA(3)
0.5x
130
50
82 83
16 06 | 24 56 | 47 23 12 | 29 17 12 | 30 18 12 | 30 12 | 56 28 |
4Q24 | 2025 | 2026 | 2027 | 2028 | 2029 | (+)2030 |
As of September 30th, 2024.
20
Considers only principal maturities. Does not considering accrued interest.
Net Debt/ Adj.EBITDA = US$149 mm / US$273mm
6%
4%
11%
69%
10%
Other
865 MW combined cycle COD: 2010
Transfer: 2020
Arg. Gov.
San Martín
7%
12%
5%
65%
11%
Other
873 MW combined cycle COD: 2010
Transfer: 2020
Arg. Gov.
Manuel Belgrano
US$ 238 million to be collected (SOFR+spread)
Central Puerto has a control stake in the operating company
56%
44%
Other
847 MW combined cycle COD: 2018
Transfer: 2028
Vuelta de Obligado
12
Shareholders
Facilities
The largest private player in the FONI Program, with 2,585 MW combined cycle plants
Brigadier López Closing cycle project
The project contemplates the addition of a heat recovery steam generator and a steam turbine to the existing dual fuel Siemens gas turbine of 281 MW, increasing the plant's capacity by approximately 140MW, reaching a total installed capacity of 421 MW, enough to supply more than 300,000 houses throughout the country.
Estimated CAPEX: US$150 mm.
Steam turbine remuneration: 10-year PPA with CAMMESA
Estimated recurring EBITDA: ~US$60 mm.
421
+140 MW
MW
281
MW
+ Steam Turbine
+ Res.59 for gas turbine
+ Efficiency and higher dispatch
Gas Turbine Combined Cycle
13
Forestry asset's location
Concordia
San Miguel Concepción
Saladas San Roque
Virasoro
La Cruz Paso de los Libres
Concordia
La Cruz
Paso de los Libres
3
Virasoro
San Roque
2
San Miguel Concepción
Saladas
1
14
Central Puerto has become the largest forestry player in Argentina
The future development of the industry will allow the group to explore new business models focusing on increasing and diversifying revenue sources, generating exports, and evaluating the feasibility of developing carbon credits and energy generation from biomass.
160.453 hectares(1) distributed in:
11.037 Ha.
Property Infrastructure
58.195 Ha.
Natural Reserves
44.880 Ha.
Pine
26.049 Ha.
Eucalyptus
20.293 Ha.
Forest Lands
7of the8total fore%stry areaInvestor Presentation
December 2024
Thank You
Investor Presentation
December 2024
Contact Us
Central Puerto
Phone Number
(5411) 4317 5000
Web / E-mail
https://www.centralpuerto.com inversores@centralpuerto.com
Location
Av. Tomas Alva Edison 2701 Dársena E Puerto de Buenos Aires.
| Attention: This is an excerpt of the original content. To continue reading it, access the original document here. |