CALGARY, AB, Feb. 6 /CNW Telbec/ - Calvalley Petroleum Inc., (TSX: CVI.A)
- Calvalley Petroleum, an international, junior oil and gas company based in
Calgary, Alberta, is pleased to provide the following update on its operations
on Block 9 in the Republic of Yemen.
Drilling & Completions
- The drilling rig was mobilized on January 4, 2006 to the eighth
horizontal Hiswah well, which was spudded on January 8, 2006. The well
was drilled with 591 meters of open hole into the oil-bearing
Saar-Naifa formation. The rig was released on January 22 and mobilized
to the ninth horizontal well, which was spudded on January 27, 2007 and
is expected to be finished drilling by the middle of February.
- Completion of the Hiswah wells 5, 7, 8 and 9, as well as, the Auqban-1
well and the Al Roidhat wells 2, 3 & 4 is scheduled to commence on
February 15, 2006. Each well will be equipped with a down hole pump and
placed on production test in preparation for full production upon
completion of the Central Processing Facility ("CPF").
- Tenders for various services including a second drilling rig, as well
as, a service rig have been received. Evaluation of the tenders is
underway with the awarding of contracts expected sometime in February.
Central Processing Facility
- Fabrication of a 20,000 barrel storage tank at the Hiswah CPF is 90%
completed.
- A Group separator with a capacity of 60,000 barrels per day is being
fabricated in Abu Dhabi and is 60% complete. The separator is expected
to be shipped to Block 9 by the end of February.
- A twenty five person living facility at Hiswah is 95 % complete.
- Site work is continuing and additional equipment is expected to arrive
mid-February.
- The Company expects to complete the CPF by March 31, 2006, at which
time production will be increased to 10,000 bbls per day (Calvalley
share 5,000 bbls per day).
Expansion of Block 18 Truck Unloading Facility
Block 18 operated by Safer Exploration Company had limited capacity to
receive trucked oil, creating a bottleneck in production and resulting in
several operational interruptions. By mutual agreement, Calvalley has
undertaken the task of designing and constructing new truck offloading
facilities adjacent to the existing Block 18 facility. Significant progress
has been made on this project including achieving the following milestones.
- Site selection and survey have been completed.
- Four 500 barrel, skid mounted storage tanks have been fabricated.
- A custody transfer meter and pump purchased in Canada have arrived in
Yemen.
- Site preparation and construction are underway and are expected to be
completed by the end of February.
- It is anticipated that the expansion of the truck offloading facility
will be completed on time, prior to end of the first quarter.
Current Production
The level of oil receipts at Block 18 has fluctuated over the past
45 days, ranging from nil to 5,000 bbls per day. Daily receipts at the Safer
facility, since deliveries began on the 15th of December 2005, have averaged
approximately 2,000 bbls of oil per day. Continuing interruptions are
anticipated until expansion is completed next month.
Transmission System
The Company is engaged in negotiations with the Ministry of Oil and
Minerals on various alternative main line transmission systems. It is expected
that the route and pipeline size will be finalized within the next month, such
that materials can be ordered and design completed. The objective is to have
the main line transmission system operational before the end of 2006, at which
time it is anticipated that production will increase to approximately
30,000 bbls of oil per day.
THE TORONTO STOCK EXCHANGE HAS NOT REVIEWED AND DOES NOT ACCEPT
RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS RELEASE.
This press release may contain forward-looking statements, including
expectations of future production, cash flow and earnings. These statements
are based on current expectations that involve a number of risks and
uncertainties, which could cause actual results to differ materially from
those anticipated or implied in the forward-looking statements. These risks
include but are not limited to: the risks associated with the oil and gas
industry (e.g. operational risks in development, exploration and production;
delays or changes in plans with respect to exploration or development projects
or capital expenditures; the uncertainties of reserve estimates; the
uncertainty of estimates and projections related to production, costs and
expenses, and health, safety and environmental risks), commodity price, price
and exchange rates fluctuations and uncertainties resulting from potential
delays or changes in plans with respect to exploration or development projects
or capital expenditures. Additional information on these and other factors
that could affect Calvalley's operations or financial results are included in
Calvalley's reports on file with Canadian securities regulatory authorities.
%SEDAR: 00001745E
Calvalley Petroleum - Yemen Operations Update For the Month of January 2006
Calvalley Petroleum Inc on 6ix
Story so far
Earlier from Calvalley Petroleum
- Calvalley Petroleum - Yemen Operations Update
- Calvalley Petroleum Announces First Production from Block 9 in the Republic of Yemen
- Calvalley Petroleum Inc. Named to 2005 TSX Venture 50
- Calvalley Petroleum appoints key Senior Managers
- Calvalley Petroleum Announces another Successful Appraisal Well at Hiswah-7
Later from Calvalley Petroleum
- Calvalley Petroleum Inc. Closes Bought Deal $58.5 Million Financing
- Calvalley Petroleum - 2005 Annual Results and Filing of Reserves Data
- Calvalley Petroleum Inc. Issues First Quarter Interim Statements
- /C O R R E C T I O N from Source -- Calvalley Petroleum Inc./
- Market Regulation Services - Trade Resumption - Calvalley Petroleum Inc. - CVI.A
Follow Calvalley Petroleum into a list and get an email when it puts out news.
Follow Calvalley Petroleum