CALGARY, AB, April 18 /CNW Telbec/ - Calvalley Petroleum Inc.
(TSX: CVI.A)
Calvalley Petroleum Inc. (the "Company"), an international junior oil and
gas company based in Calgary, Alberta, is pleased to provide the following
update on its operations on Block 9 in the Republic of Yemen.
Production and Delivery
The Company is currently in the early oil production period that utilizes
tanker trucks for transporting the crude westward from Block 9 to Block 18.
The bottleneck at the Block 18 facility has been resolved by constructing a
new truck offloading facility. On the start-up of the new offloading facility,
oil production increased from the 2,000 barrels of oil per day ("bopd") to
5,000 bopd and is expected to reach the allowable 10,000 bopd as set by the
Yemeni Ministry of Oil and Minerals (the "Ministry") by month's end.
The Company intends to seek an approval from the applicable regulatory
bodies in Yemen to increase trucking capacity beyond the allowable limit of
10,000 bopd. The current production is currently limited to the Hiswah 3 &
6 wells. Nearby horizontal wells Hiswah-7, 8, 9 and 10 are being completed and
tied-in which will allow for the desired increase in oil production as well as
provide for additional operational flexibility.
Drilling and Completion
- The Hiswah-15th horizontal well is currently being drilled and plans
have been prepared to drill an additional six horizontal wells, with a
further ten horizontal wells being designed.
- Since January 1, 2006, five horizontal wells have been drilled and a
sixth is about to be completed. All the wells have encountered the oil-
bearing Saar-Naifa formation. These wells are expected to add new
proved reserves and will provide for an increase in the overall oil
production.
- Completion of Hiswah 7, 8, 9 & 10 wells has been accomplished with each
well equipped with a down-hole ESP pump which will be put on production
upon flowline completion.
Pipeline Gathering System
Construction of a flowline gathering system within the Hiswah field
commenced during the month of March. Hiswah 3, 6, 7, 8, 9 & 10 wells have been
constructed and final connection should be completed by month's end.
Tender Awards
Tenders for various services including a second drilling rig and a
service rig have been received. Evaluations were completed and most of the
contracts have been awarded.
Pipeline Transmission System
Preliminary design of a pipeline transmission system between Block 9 and
18 has been completed. A recommendation will be made to the Ministry to
commence with the construction of twelve inch pipeline with minimum of four
pump stations.
THE TORONTO STOCK EXCHANGE HAS NOT REVIEWED AND DOES NOT ACCEPT
RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS RELEASE.
This press release may contain forward-looking statements, including
expectations of future production, cash flow and earnings. These statements
are based on current expectations that involve a number of risks and
uncertainties, which could cause actual results to differ materially from
those anticipated or implied in the forward-looking statements. These risks
include but are not limited to: the risks associated with the oil and gas
industry (e.g. operational risks in development, exploration and production;
delays or changes in plans with respect to exploration or development projects
or capital expenditures; the uncertainties of reserve estimates; the
uncertainty of estimates and projections related to production, costs and
expenses, and health, safety and environmental risks), commodity price, price
and exchange rates fluctuations and uncertainties resulting from potential
delays or changes in plans with respect to exploration or development projects
or capital expenditures. Additional information on these and other factors
that could affect Calvalley's operations or financial results are included in
Calvalley's reports on file with Canadian securities regulatory authorities.
%SEDAR: 00001745E
Calvalley Petroleum Inc. - Yemen Operations Update
Calvalley Petroleum Inc on 6ix
Story so far
Earlier from Calvalley Petroleum
- Calvalley Petroleum - 2005 Annual Results and Filing of Reserves Data
- Calvalley Petroleum Inc. Closes Bought Deal $58.5 Million Financing
- Calvalley Petroleum - Yemen Operations Update For the Month of January 2006
- Calvalley Petroleum Announces First Production from Block 9 in the Republic of Yemen
- Calvalley Petroleum Inc. Named to 2005 TSX Venture 50
Later from Calvalley Petroleum
- Calvalley Petroleum Inc. Issues First Quarter Interim Statements
- /C O R R E C T I O N from Source -- Calvalley Petroleum Inc./
- Market Regulation Services - Trade Resumption - Calvalley Petroleum Inc. - CVI.A
- Market Regulation Services - Trading Halt - Calvalley Petroleum Inc. - CVI.A
- Calvalley Petroleum Inc. Issues Second Quarter Interim Statements
Follow Calvalley Petroleum into a list and get an email when it puts out news.
Follow Calvalley Petroleum