Aurelia Metals said on June 16, 2026 that it has completed a prefeasibility study (an early-stage engineering and economic study) for its New Occidental Tailings Retreatment Project at its Peak Operation near Cobar, New South Wales, and declared a first Ore Reserve of 2.3Mt (million tonnes) at 0.64g/t Au (grams of gold per tonne).

Key details

  • Aurelia Metals also declared a first Mineral Resource Estimate of 2.6Mt at 0.65g/t Au for the New Occidental Tailings stockpiles.
  • The project involves reclaiming and retreating two historical gold-bearing dry-stacked tailings (leftover processed material) stockpiles approximately 3km north-west of the Peak processing plant. The tailings were originally processed in the late 1980s.
  • Tailings will be transported along an existing haul road and processed through Peak's existing carbon-in-leach circuit (a gold recovery process) alongside lead and zinc ore campaigns, using existing capacity including a tertiary ball mill being installed under the Cobar Optimisation Project.
  • The project is forecast to produce approximately 32koz (thousand ounces) of saleable gold over 10 years, and has been modelled to deliver a post-tax net present value (NPV8, a measure of a project's value in today's money) of $42 million at an average gold price of A$5,017/oz, with an internal rate of return of 258%.
  • Aurelia Metals says the retreatment is expected to reduce long-term rehabilitation requirements at the New Occidental site by moving the material into the existing Peak Tailings Storage Facility.

What’s still pending

  • The project has moved into the feasibility study stage; detailed engineering and permitting are planned for the first half of Aurelia's financial year 2027 (H1 FY27).
  • Construction is targeted for the second half of Aurelia's financial year 2027 (H2 FY27).
  • Production is expected to start in Aurelia's financial year 2028 (FY28).
  • Gold output, net present value and rate of return figures are forecasts and modelled results.

6ix AI wrote this summary from the release below and checked it against the release.

New Occidental Tailings Project Pre-Feasibility Study and Maiden Ore Reserve

On 16 June 2026, Aurelia Metals announced the completion of a Prefeasibility Study (PFS) for its New Occidental Tailings Retreatment Project at the Company's Peak Operation near Cobar in central west New South Wales.

The Company also declared a maiden Mineral Resource Estimate of 2.6Mt at 0.65g/t Au and a maiden Ore Reserve Estimate of 2.3Mt at 0.64g/t Au for the New Occidental Tailings stockpiles.

The Project involves reclaiming and retreating two historical gold-bearing dry-stacked tailings stockpiles located approximately 3km north-west of the Peak processing plant. The tailings were originally processed during the late 1980s before being deposited into the stockpiles.

Significantly, the Project leverages existing infrastructure and processing capacity at Peak, including the tertiary ball mill currently being installed as part of the Cobar Optimisation Project. Tailings material will be transported along an existing haul road and processed through the existing carbon-in-leach circuit alongside Pb/Zn ore campaigns.

The Project is forecast to produce approximately 32koz of saleable gold over a 10-year period and has been modelled to deliver a post-tax NPV8 of $42 million using an average gold price of A$5,017/oz and an IRR of 258%.

The retreatment of the historical tailings is also expected to deliver environmental and rehabilitation benefits by reducing long-term rehabilitation requirements at the New Occidental site through relocation of material into the existing Peak Tailings Storage Facility.

Managing Director and Chief Executive Officer, Bryan Quinn said the Project is a great example of Aurelia's technical and operational teams continuing to unlock additional value from existing infrastructure at Peak.

"The Project capitalises on recent optimisation initiatives, particularly the installation of the tertiary ball mill from Dargues, which creates the opportunity to process the tailings material concurrently with Pb/Zn ore processing campaigns at low incremental capital and operating costs," Bryan explained.

"In addition to generating gold production and cash flow, the Project also delivers rehabilitation and environmental benefits, while the maiden Mineral Resource and Ore Reserve provide another source of operational flexibility within Aurelia's Cobar region strategy.

"Finally, I'd like to acknowledge the significant work from teams across the business in progressing the PFS and supporting today's announcement. Outcomes like this are only possible through strong collaboration and a continued shared commitment to unlocking value across our operations," Bryan concluded.

Aurelia has now gated the Project into the Feasibility Study stage, with detailed engineering and permitting planned for H1 FY27, construction targeted for H2 FY27 and production expected to commence in FY28.

Further Project details are available in the ASX announcement: New Occidental Tailings Prefeasibility Study and Maiden Ore Reserve.