Unitech Limited · NSE:UNITECH

Unitech — Corporate Update (June 2012)

59 slides from Unitech's corporate update, June 2012

  1. Slide 1: Operations Update (Apr – Jun 2012)

    Operations Update (Apr – Jun 2012)

  2. Slide 2: Sales Bookings (Apr – Jun 2012)

    SALES BOOKINGS (Apr – Jun 2012) Area Launched (mn Area sold Sales Value City sq ft) (mn sq ft) (INR Cr) Gurgaon 0.00 0.14 139 Noida & G Noida 0.93 0.88 378 Chennai 0.00 0.20 59 Kolkata 0.00 0.16 79 Other Cities 0.33 0.13 45 Total 1.27 1.51 701 Area sold Booked Value Avg. Realisation Segment (mn sq f

  3. Slide 3: Regionwise Sales Bookings (Apr – Jun 2012)

    REGIONWISE SALES BOOKINGS (Apr – Jun 2012) Area sold during Apr ‐ Jun 2012 Other Cities Gurgaon 9% 8% Kolkata 11% Chennai 13% Noida & G Noida 59%

  4. Slide 4: Sales Bookings During Last Quarters

    SALES BOOKINGS DURING LAST 7 QUARTERS Sales Area Booked 5.00 1,200 1,068 1,100 4.50 1,036 4.29 1,020 941 1,000 4.00 975 Area (in Million sq ft) 900 3.50 779 3.21 800 3.00 2.78 700 INR Cr 701 2.50 600 2.20 1.97 1.90 500 2.00 1.80 1.79 1.69 1.57 1.51 400 1.50 1.27 1.18 300 1.00 0.64 200 0.50 100 ‐ ‐ Q

  5. Slide 5: Average Realization per Sq Ft During Last Quarters

    AVERAGE REALIZATION PER SQ FT DURING LAST 7 QUARTERS Average Realisation (INR per sq ft) 13000 12293 11788 11961 12000 11000 10393 10000 9395 9000 8656 INR (Price per sq ft) 8000 7000 5921 6000 5318 5361 5569 4954 5000 4709 4632 5380 4350 4000 4731 4557 4608 4232 4360 3863 3000 2000 1000 0 Q3 2010‐1

  6. Slide 6: Delivery Status of Projects

    DELIVERY STATUS OF PROJECTS Total Deliverable Area Delivered Area delivered Balance Area S No. Particulars Area During (mn sq ft) (in mn sq ft.) (in mn sq ft) Apr - Jun 2012 Projects launched 1 24.6 13.0 0.3 11.6 before Mar' 2009 Projects launched 2 25.1 0.6 0.4 24.5 since Mar' 2009 3 Leased Area -

  7. Slide 7: Construction Status of Projects Launched Before Mar '09

    CONSTRUCTION STATUS OF PROJECTS LAUNCHED BEFORE MAR ‘09 Number of Construction Stage mn sq ft % age Projects projects Gurgaon - The Close (South), The Close (North), World Spa (East), World Spa (West), Espace, Fresco, Nirvana Courtyard, Escape, Harmony, Arcadia, Handover / Finishing 22 19.5 80% Sout

  8. Slide 8: Construction Progress of Projects Launched Since Mar '09

    CONSTRUCTION PROGRESS OF PROJECTS LAUNCHED SINCE MAR’09 Number of % age of Construction Stage mn sq ft Projects projects total Handover / Finishing 4 2.0 8% Chennai - Aspen, Unihomes; Gurgaon - Commercial Tower Sec-45; Kolkata - Vistas Structure Complete, Gurgaon - Nirvana Floors, Gardens II, Reside

  9. Slide 9: Site Photographs: Gurgaon

    unitech Site Photographs Gurgaon

  10. Slide 10: The Close (North), Gurgaon – Handover

    THE CLOSE (NORTH), GURGAON – Handover in progress

  11. Slide 11: The Close (South), Gurgaon – Handover/Finishing

    THE CLOSE (SOUTH), GURGAON – Handover/ Finishing in progress

  12. Slide 12: Fresco, Gurgaon – Handover / Finishing

    FRESCO, GURGAON – Handover / Finishing in progress

  13. Slide 13: Escape, Gurgaon – Handover/Finishing in Progress

    ESCAPE, GURGAON – Handover/Finishing in Progress

  14. Slide 14: Harmony, Gurgaon – Handover/Finishing

    HARMONY, GURGAON – Handover/Finishing in progress

  15. Slide 15: Woodstock Floors, Gurgaon – Internal work

    WOODSTOCK FLOORS, GURGAON – Internal work in progress

  16. Slide 16: UW Gardens-II, Gurgaon – Structure Complete Internal work

    UW GARDENS-II, GURGAON – Structure Complete Internal work in progress

  17. Slide 17: Residences, Gurgaon – Structure / Internal work

    RESIDENCES, GURGAON – Structure / Internal work in progress

  18. Slide 18: Vistas, Gurgaon – Structure

    VISTAS, GURGAON – Structure in progress

  19. Slide 19: Sunbreeze, Gurgaon – Structure

    SUNBREEZE, GURGAON – Structure in progress

  20. Slide 20: Exquisite, Gurgaon – Piling/Structure

    EXQUISITE, GURGAON – Piling/Structure in progress

  21. Slide 21: South Park, Gurgaon – Show Flat ready

    SOUTH PARK, GURGAON – Show Flat ready

  22. Slide 22: Site Photographs: G Noida and Noida

    Site Photographs G Noida and Noida

  23. Slide 23: UGCC, Noida – Structure work in progress, Deck & Golf Course operational

    UGCC, NOIDA – Structure work of all towers in progress, The Deck & Golf Course operational

  24. Slide 24: Unihomes, Noida – Structure complete, internal work

    UNIHOMES, NOIDA – Structure complete, internal work in progress

  25. Slide 25: Unihomes 2, Noida – Structure

    UNIHOMES 2, NOIDA – Structure in progress

  26. Slide 26: Uniworld Gardens, Noida – Structure in Progress

    UNIWORLD GARDENS, NOIDA – Structure in Progress

  27. Slide 27: Heights, Greater Noida – Handover / Finishing

    HEIGHTS, GREATER NOIDA – Handover / Finishing in progress

  28. Slide 28: Horizon, Greater Noida – Handover/Finishing

    HORIZON, GREATER NOIDA – Handover/ Finishing in progress

  29. Slide 29: Cascades, Greater Noida – Handover / Finishing

    CASCADES, GREATER NOIDA – Handover / Finishing in progress

  30. Slide 30: Habitat, Greater Noida – Handover / Finishing

    HABITAT, GREATER NOIDA – Handover / Finishing in progress

  31. Slide 31: Verve, Greater Noida – Structure complete, Internal work

    VERVE, GREATER NOIDA – Structure complete, Internal work in progress

  32. Slide 32: Site Photographs: Mohali

    unitech Site Photographs Mohali

  33. Slide 33: Executive Floors, Mohali – Structure complete, internal work

    EXECUTIVE FLOORS, MOHALI – structure complete, internal work progress

  34. Slide 34: UW Gardens, Mohali – Structure work

    UW GARDENS, MOHALI – Structure work in progress

  35. Slide 35: Unihomes, Mohali – Structure Complete, Internal work

    UNIHOMES, MOHALI – Structure Complete, Internal work in progress

  36. Slide 36: Aspen Greens, Mohali – Development work

    ASPEN GREENS, MOHALI – Development work in progress

  37. Slide 37: Site Photographs: Chennai

    unitech Site Photographs Chennal

  38. Slide 38: Unihomes, Chennai – Handover / Finishing

    UNIHOMES, CHENNAI – Handover / Finishing in progress

  39. Slide 39: Palm Villas, Chennai – Structure Complete, Internal work

    PALM VILLAS, CHENNAI – Structure Complete, Internal work in progress

  40. Slide 40: Aspen Greens, Chennai – Handover

    ASPEN GREENS, CHENNAI – Handover in progress

  41. Slide 41: UW Gardens, Chennai – Structure work

    UW GARDENS, CHENNAI – Structure work in progress

  42. Slide 42: Brahma - North Town, Chennai – Structure work

    BRAHMA - NORTH TOWN, CHENNAI – Structure work in progress

  43. Slide 43: Ananda - North Town, Chennai – Internal work

    ANANDA - NORTH TOWN, CHENNAI – Internal work in progress

  44. Slide 44: Gulmohar Avenue - North Town, Chennai – Structure Complete, Internal work

    GULMOHAR AVENUE - NORTH TOWN, CHENNAI – Structure Compete, Internal work in progress

  45. Slide 45: Chaitanya - North Town, Chennai – Piling / Structure work

    CHAITANYA - NORTH TOWN, CHENNAI – Piling / Structure work in progress

  46. Slide 46: Site Photographs: Kolkata

    unitech Site Photographs Kolkata

  47. Slide 47: Downtown, Kolkata – Structure complete, internal work

    DOWNTOWN, KOLKATA – Structure complete, internal work in progress

  48. Slide 48: Cascades, Kolkata – Handover / Finishing in Progress

    CASCADES, KOLKATA – Handover / Finishing in Progress

  49. Slide 49: Harmony, Kolkata – Structure work

    HARMONY, KOLKATA – Structure work in progress

  50. Slide 50: Vistas, Kolkata – Handover / Finishing in Progress

    VISTAS, KOLKATA – Handover / Finishing in Progress

  51. Slide 51: Air, Kolkata – Structure Complete, Internal work

    AIR, KOLKATA – Structure Complete, Internal work in progress

  52. Slide 52: Fresco, Kolkata – Structure work

    FRESCO, KOLKATA – Structure work in progress

  53. Slide 53: Heights, Kolkata – Handover / Finishing

    HEIGHTS, KOLKATA – Handover / Finishing in progress

  54. Slide 54: Site Photographs: Bhubaneswar

    Site Photographs Bhubaneswar

  55. Slide 55: Bhubaneswar One, Bhubaneswar – Piling / Structure work

    BHUBANESWAR ONE, BHUBANESWAR – Piling / Structure work in progress

  56. Slide 56: Site Photographs: Bhopal

    unitech Site Photographs Bhopal

  57. Slide 57: Unihomes, Bhopal – Structure Complete, Internal work

    UNIHOMES, Bhopal – Structure Complete, Internal work in progress

  58. Slide 58: The Great India Place, Bhopal – Piling / Structure

    THE GREAT INDIA PLACE, Bhopal – Piling / Structure in progress

  59. Slide 59: Thank You

    Thank You