Alacer Gold — FY2013 Earnings Presentation
11 slides from Alacer Gold's earnings presentation, Mar 12, 2014

Slide 1: Full-Year 2013 Financial Results
Full-Year 2013 Financial Results Rod Antal, Chief Executive Officer Mark Murchison, Chief Financial Officer March 12, 2014 TSX: ASR / ASX: AQG

Slide 2: Cautionary Statements
Cautionary Statements FORWARD-LOOKING STATEMENTS Except for statements of historical fact relating to Alacer, certain statements contained in this presentation constitute forward-looking information, future oriented financial information, or financial outlooks (collectively “forward-looking informat

Slide 3: Çöpler Providing Strong Cash Flow
Çöpler Providing Strong Cash Flow Oxide heap-leach gold production supports organic growth 300,000 1,200 250,000 54,213 $864 1,000 Production (Oz Au) All‐In Costs ($/oz) 200,000 42,500 $755 800 37,751 150,000 600 216,850 100,000 400 170,000 Çöpler Non‐Controlling 151,005 Interest (ozs) 50,000 200 Çö

Slide 4: Çöpler - 2013 Performance
Çöpler - 2013 Performance Beginning to realize benefits from operational improvements Q1 Q2 Q3 Q4 2013 Çöpler Gold Mine 2013 2013 2013 2013 Year Waste tonnes mined 4,914,386 5,241,673 4,694,066 5,833,161 20,683,286 Oxide ore mined – tonnes 1,787,169 1,773,536 1,715,571 1,397,244 6,673,520 Oxide ore

Slide 5: Financial Position
Financial Position Simplified and strengthened during 2013 December 31 December 31 Favorable 2013 2012 (Unfavorable) ($M) ($M) Variance ($M) 1 Current assets 363.9 417.1 (53.2) Current liabilities 48.7 228.5 179.8 1 Working capital 315.2 188.6 126.6 Total assets 712.2 1,460.4 (748.2) Total liabiliti

Slide 6: P&L Statement – Summary Comparison
P&L Statement – Summary Comparison Continuing Operations Full‐Year Full‐Year Favorable Key Points 2013 2012 (Unfavorable) ($M) ($M) Variance ($M) Gold sales 377.1 337.6 39.5 Increased production offset by $285/oz lower gold price Production costs 117.2 76.1 (41.1) Q4 2013 cost includes $5.3M invento

Slide 7: 2013 Income Tax Expense
2013 Income Tax Expense Two end of year adjustments contribute to increased tax expense Tax expense of $75M for 2013 Increase in the effective tax rate for Turkish operations from ≈13% to ≈20% due to: a reduction in capital asset expenditures that qualify for incentive tax credits; and reducti

Slide 8: Exploration
Exploration Significant land position in Turkey 2014 Exploration Budget $21M (100%) Exploration strategy re-focused on three priorities Çöpler District 80/20 Discover additional oxide ore Leverage existing infrastructure and support Çöpler District 50/50 Provide feed to Çöpler or standalone pr

Slide 9: Çöpler Sulfide Project
Çöpler Sulfide Project Completion of DFS will provide clear path forward DFS on whole-ore POX on-track for release in Q2 2014: Design, engineering and procurement studies nearing completion, next subject to internal review Supplemental EIA to be submitted this month Positive sulfide gold reconci

Slide 10: Alacer in a Strong Position
Alacer in a Strong Position Strategic advantage in Turkey Successful track record in Turkey Excellent local partner Low cost producer, high margin returns Sulfide DFS on track for release Q2 2014 Organic growth potential from current exploration portfolio Strong cash position of $290M1 a

Slide 11: Full-Year 2013 Financial Results
Full-Year 2013 Financial Results Leveraging Our Expertise in Turkey For further information, please contact: Lisa Maestas North America: +1-303-292-1299 Roger Howe Australia: +61-2-9953-2470 TSX: ASR / ASX: AQG / 11
Source: Internet Archive copy of alacergold.com
More decks from Alacer Gold Corp
Investor Presentation (August 2018)15 slides · August 2018
Q2 2018 Earnings Presentation12 slides · Jul 31, 2018
RBC Global Mining & Materials Conference 201817 slides · June 2018
Corporate Update (May 2017)75 slides · May 10, 2017
Q1 2017 Earnings Presentation13 slides · May 2, 2017
FY2016 Earnings Presentation14 slides · Feb 6, 2017