Alacer Gold Corp

Alacer Gold — Q3 2016 Earnings Presentation

12 slides from Alacer Gold's earnings presentation, Oct 26, 2016

  1. Slide 1: Q3 2016 Operating & Financial Results

    Slide 1: Q3 2016 Operating & Financial Results

    Q3 2016 Operating & Financial Results Rod Antal, President & Chief Executive Officer Mark Murchison, Chief Financial Officer October 26, 2016 TSX: ASR / ASX: AQG / 1

  2. Slide 2: Cautionary Statements

    Slide 2: Cautionary Statements

    Cautionary Statements Except for statements of historical fact relating to Alacer, certain statements contained in this presentation constitute forward-looking information, future oriented financial information, or financial outlooks (collectively “forward-looking information”) within the meaning of

  3. Slide 3: Production Expected to Increase in Q4

    Slide 3: Production Expected to Increase in Q4

    Production Expected to Increase in Q4  2016 production plan weighted towards second half  Q3 production less than expected due to delays  Mitigation work for localized pit wall instability delayed access to oxide ore in Marble Pit  Late mobilization delayed re-leach program into Q4  All efforts

  4. Slide 4: Q3 2016 Highlights

    Slide 4: Q3 2016 Highlights

    Q3 2016 Highlights Strategic Operational Financial  Sulfide Project advancing on  Quarterly production of  Cash of $254M at budget, site works ramping up 23,202 gold ozs September 30, 2016  Foundations for Sulfide Project  Total Cash Costs1 of $853/oz  Operating cash flows of critical path are

  5. Slide 5: Çöpler Sulfide Expansion Project Construction Underway

    Slide 5: Çöpler Sulfide Expansion Project Construction Underway

    Çöpler Sulfide Expansion Project Pressure Oxidation Building Construction Underway  Foundations for critical path progressing, initial structural steel on site Tailings Thickener Tank  Over $300M of capital commitments in place  Project costs to date of $114M incurred  Project remains on budget

  6. Slide 6: Gediktepe Project Provides Organic Growth

    Slide 6: Gediktepe Project Provides Organic Growth

    Gediktepe Project Provides Organic Growth  PFS defined Project is technically and economically viable  Alacer will own 50% with JV Partner Lidya Mining1  Life-of-mine payable metals of 400,000 ozs of gold, 8M ozs of silver, 315M lbs of copper and 780M lbs of zinc2  Life-of-mine production >12 ye

  7. Slide 7: Gediktepe Production Profile and Life-of-Mine Project Metrics

    Slide 7: Gediktepe Production Profile and Life-of-Mine Project Metrics

    Gediktepe Project Gediktepe Production Profile (100% Basis) Life-of-Mine Project Metrics1 (100% Basis) 250 Pre-production Capital $120M Additional capital for sulfide plant $126M 200 Gold Equivalent Ounce2 (000 oz) Project payback 2.5 years 150 After-tax free cash flow $745M C22 per oz AuEq3 $613 10

  8. Slide 8: Çöpler District Rapid Development Potential

    Slide 8: Çöpler District Rapid Development Potential

    Çöpler District Rapid Development Potential  Oxide targets identified within 5-7km of Çöpler Mine  Potential to add oxide production within two years from existing Çöpler infrastructure  Step-out drilling continues to the North and South  Deliver maiden resource by end of 2016 TSX: ASR / ASX: AQ

  9. Slide 9: P&L Statement – Earnings of $3 Million

    Slide 9: P&L Statement – Earnings of $3 Million

    P&L Statement – Earnings of $3 Million Q3 2016 Q2 2016 Q1 2016 YTD 2016 Commentary ($M) ($M) ($M) ($M) Lower Q3 production than planned – delay in Total gold sold (ounces) 21,155 30,263 31,750 83,168 mining Marble Pit ore and re-leach program Average realized gold price ($/ounce) 1,324 1,252 1,187 1

  10. Slide 10: Cost Metrics

    Slide 10: Cost Metrics

    Cost Metrics Q3 2016 Q2 2016 Q1 2016 YTD 2016 Commentary 1 Production costs (Total Cash Costs (C2)) ($M) 18.0 22.8 20.9 61.7 Add: Exploration and evaluation ($M) 0.5 0.7 0.5 1.7 Includes G&A and mark-to-market Other ($M) 5.4 4.4 4.2 13.9 share-based compensation Sustaining capital expenditure ($M) 1

  11. Slide 11: Gold production catch up to meet lower end of guidance

    Slide 11: Gold production catch up to meet lower end of guidance

     Mining oxide ore from Marble Pit  Gold production catch up underway to meet lower end of guidance  Timing of some production may move into early 2017 TSX: ASR / ASX: AQG / 11

  12. Slide 12: Contact

    Slide 12: Contact

    Contact For further information, please contact: Lisa Maestas Director, Investor Relations +1-303-292-1299 TSX: ASR / ASX: AQG / 12