Copper North Mining — Investor Presentation (October 2011)
28 slides from Copper North Mining's investor presentation, October 2011

Slide 1: A New Direction
A New Direction October 2011 TSX.v:COL

Slide 2: Forward Looking Statements
FORWARD LOOKING STATEMENTS Statements contained in this presentation that are not historical fact, such as statements regarding the economic prospects of the Company’s projects, the Company’s future plans or future revenues, timing of development or potential expansion or improvements, are forward-l

Slide 3: Key Financial Information
KEY FINANCIAL INFORMATION » CASH POSITION Cash on Hand C$ 2.0 M October 2011 Short/Long Term Debt 0.0 » SHARE STRUCTURE Share Price N/A October 2011 Market Cap N/A Common Shares 46,487,785 Options TBD Warrants TBD Fully Diluted TBD » COMMON SHARES Management & Board 9% October 2011 Private Investors

Slide 4: Properties
PROPERTIES » Carmacks – 100% owned – High grade (1.04% Cu) copper oxide deposit – Permitted for construction » Redstone – 100% owned – High grade stratiform copper deposit – Drilling program planned TSX.v: COL Carmacks | 4

Slide 5: Carmacks Deposit
CARMACKS DEPOSIT TSX.v: COL Carmacks | 5

Slide 6: High Grade Copper Oxide Deposit
HIGH GRADE COPPER OXIDE DEPOSIT » Open pit mine – Heap leach, solvent extraction / electrowinning – 6+ year mine life » Prime Location – 220 km north of Whitehorse, Yukon – 400 km from year-round port of Skagway, AK – Existing road into site – 11 km from Yukon power grid » Advancing towards producti

Slide 7: Carmacks – Reserve & Resource Estimate
CARMACKS – RESERVE & RESOURCE ESTIMATE RESERVE1 RESERVE GRADE CONTAINED METAL Class Tonnes Total Copper Oxide Copper Gold Silver Cu Eq Copper Gold Silver M % % g/t g/t % M lb k oz k oz Proven 3.2 1.23 1.028 0.659 6.20 1.70 86 68 636 Probable 7.4 0.97 0.822 0.408 3.94 1.26 158 97 940 Proven + 10.6 1.

Slide 8: Property Geology
PROPERTY GEOLOGY » Carmacks deposit open at depth & oxidised to ~230m » All Resources and Reserves based on zones 1,4, 7 & 7A » Upside potential in zones 12, 13 & 14 TSX.v: COL Carmacks | 8

Slide 9: Production Profile & After-Tax Cash Flow
PRODUCTION PROFILE & AFTER-TAX CASH FLOW* *Cash flow includes operating costs (mining, processing, G&A, shipping & property tax), sustaining capex and royalties. Excludes capex ~C$151M. Spot price $3.85 (US/lb) and exchange rate 1.00 (US$:C$) - Feasibility Study $2.32 (US/lb) and exchange rate 0.85

Slide 10: Feasibility Study (May 2007)
FEASIBILITY STUDY (MAY 2007) » CAPITAL COSTS MINE CAPITAL (C$ M) 134 ACID PLANT CAPITAL (C$ M) 18 TOTAL CAPEX (C$ M) 151 SPOT LONG PRE-FEAS SEPT 2011 TERM MAY 2007 » ECONOMICS COPPER (US$/lb) 3.85 2.50 2.32 FOREIGN EXCHANGE (US$:C$) 1.00 0.90 0.85 Pre- NPV @ 8% (C$ M) 248 92 85 Tax IRR (100% equity)

Slide 11: Carmacks Progress History
CARMACKS | PROGRESS HISTORY 1993 Basic engineering study initiated 1997 Definitive capital cost estimate completed 1998 Project suspended due to low copper prices 2005 Permitting process commences Extensive exploration at Carmacks (~25,000m); Feasibility Study 2007 (NI43-101 compliant) com

Slide 12: Water Use License
WATER USE LICENSE » Key issues identified by Water Board – Heap leaching technology – Closure and reclamation of heap – Discharge management plan » Actions – Considering engineering modifications – Seeking independent engineering review – Working with Yukon Government to determine alternative ways f

Slide 13: Next Steps
NEXT STEPS » Obtain Water Use License (WUL) – Anticipate WUL will be issued in 2012 » Get Project Ready for Production – Arrange financing » Explore Opportunities – Further exploration of additional ore zones 12, 13 & 14 – Assess economics of mining and processing sulphide ore TSX.v: COL Carmacks |

Slide 14: Redstone Project
REDSTONE PROJECT TSX.v: COL Redstone | 14

Slide 15: Redstone
REDSTONE » Underground Mine – Sediment-hosted stratiform deposit » A Mining District of the Future – Redstone Copper belt Nahanni Mining District, NWT – 300km north of Watson Lake, YT » Mineral Resource Tonnes Copper Silver Cu Eq Copper Silver M % g/t % B lb M oz *Inferred 34 3.92 9.0 4.0 2.9 9.8 *S

Slide 16: Redstone claims and leases
REDSTONE » Redstone Project consists of 13 claims (blue) and 5 leases (red) extending NW-SE over 160 km TSX.v: COL Redstone | 16

Slide 17: Redstone Progress History
REDSTONE | PROGRESS HISTORY The Redstone property underwent extensive drilling by Redstone 1960 - 1980 Mines Ltd., Cerro Mining Company of Canada and Shell Canada Resources 1990 Redstone Mines Ltd. carried out a complete data review Lumina Resources Corp. completed a regional geological 2005 e

Slide 18: Redstone Work Plan
REDSTONE » Work Plan – Develop drilling program for 2012 – Submit application for exploration permit – Continue regional geological study of the Redstone Copper belt TSX.v: COL Redstone | 18

Slide 19: Summary
SUMMARY » Copper North owns a 100% interest in two high grade copper deposits in northern Canada – Carmacks: permitted for construction (Proven & Probable Reserves of 10.6Mt @1.04% Cu) – Redstone: significant upside potential (Inferred Resource of 34Mt @3.92% Cu & 9.0g/t Ag) » Resolve issues identif

Slide 20: Management & Board
MANAGEMENT & BOARD Dale Corman, P. Eng. – Non - Executive Chairman – Over 40 years’ experience as a senior corporate officer of publicly listed companies. Extensive expertise in mineral exploration & development, financing, property evaluation and acquisition. Formerly Chairman & CEO of Western Silv

Slide 21: Appendix
APPENDIX TSX.v: COL Appendix | 21

Slide 22: History of Copper North
HISTORY OF COPPER NORTH – In October of 2011, Western Copper Corporation (WRN) spun-off by plan of arrangement Copper North Mining Corp (COL). and NorthIsle Copper & Gold Inc. (NCX) – Western Copper issued 46,487,785 common shares to Copper North, representing 0.5 Copper North share for each Western

Slide 23: Redstone
/OMILE: Pes | FLUME LINE, mre 008 s CYNTHIA Oe iron oxide breccias/vein Z\. matficlultramafic associated YUKON OLYMPIC : CQ. mississippi valley type MICHELLE Pelly Crossing CLEAR CREEK © a UREKA _ ‘i a rein — | ANDREW” / CLEAR LAKE Va 8 2 DRAGON are Kiwi G7 pRouect jaro << TIMBER CHARLOTTE : eee § ,

Slide 24: Water Use License – Reasons for Decision
WATER USE LICENSE – REASONS FOR DECISION » Summary from Decision Document related to Carmacks’ Water Use Application – Yukon Water Board, May 2010 In its deliberations for the Water Use Application, Yukon Water Board focused on following key issues: – Use of unproven technology – Likelihood of Succe

Slide 25: Yukon Permitting Process
YUKON PERMITTING PROCESS 1) YUKON ENVIRONMENTAL & SOCIO- ECONOMIC ASSESSMENT • Conducted by Yukon Socio-economic Assessment Board (YESAB) • YESAB is an independent Yukon Agency comprised of Federal, ASSESSMENT STAGE Territorial and First Nation Governments (One window process) Identifies environment

Slide 26: Northwest Territories Permitting Process
NORTHWEST TERRITORIES PERMITTING PROCESS » Board-style governance Preparation and Feasibility and – Independent boards and submission of project environmental agencies description baseline studies » Initiatives underway to improve processes and timelines Preliminary screening – Actions under Federal

Slide 27: Notes
NOTES 1. CARMACKS RESERVE ESTIMATE – Technical Report: May 2007 – Qualified Person: M.Hester, FAusIMM – Cu Eq Metal prices: US$2.00/lb copper, US$875.00/oz gold, US$11.25/oz silver – Includes mining dilution 2. CARMACKS RESOURCE ESTIMATE – Technical Report: Wardrop, December 2007 – Qualified Person:

Slide 28: 2050 – 1111 West Georgia Street Vancouver, BC V6E 4M3 T:
2050 – 1111 West Georgia Street Vancouver, BC V6E 4M3 T: 604.638.2505 F: 604.669.2926 www.coppernorthmining.com info@coppernorthmining.com October 2011 TSX.v:COL
Source: Internet Archive copy of coppernorthmining.com