Synex International Inc.TSX: SXI

Synex International Inc. update on Cypress Creek Hydro Project

· Issued by Synex International Inc. via CNW

TSX: SXI

VANCOUVER, Oct. 22 /CNW/ - Synex International Inc. announces that its wholly owned subsidiary, Synex Energy Resources Ltd., has entered into a loan agreement with the Canadian Western Bank. The amount to be advanced under the loan is $3,529,945 and the use of funds is for the completion of construction of the 2.8 MW Cypress Creek Hydro Project (the "Project"). The first advance under the loan agreement is anticipated to occur in November 2007. The Project is located near the existing 3.8 MW Mears Creek plant on Vancouver Island, British Columbia.

Construction of the Project is about 60% complete. Work is continuing on each of the intake, penstock and powerhouse substructure. The scheduled completion date is during March 2008, which is about the time that BC Hydro is expected to make available its Standing Offer Call for proposals for electricity purchase agreements. The Company intends to submit a proposal promptly after the Standing Offer is available.

Synex International Inc. is a public company listed on the TSX with businesses that cover the development, ownership and operation of electrical generation facilities and the provision of consulting engineering services in water resources, particularly hydroelectric facilities.

"signed"

--------------------------------------

Greg Sunell, President

Synex International Inc. on 6ix

Earlier from Synex International

Later from Synex International

All Synex International news releases