VANCOUVER, July 26 /CNW/ - Synex International Inc. announces that its wholly owned subsidiary, Synex Energy Resources Ltd., has provided notice of termination to BC Hydro in respect of the Electricity Purchase Agreement (the "EPA") for the McKelvie Creek Hydro Project (the "Project"). The EPA was originally executed on August 31, 2006. Since August 31, 2006, the Project has encountered appreciable projected cost increases due to unforeseen design and land tenure issues. The Company is intending to continue to advance a revised project for the site including the possible upgrade of the plant capacity to 5 MW from 3.4 MW and expects that the revised project will be financially viable under current electricity purchase prices which are higher than the price included in the EPA.

Construction of the 2.8 MW Cypress Creek Hydro Project is advancing with the recent commencement of concrete work at the intake. The Cypress Project does not have an existing electricity purchase agreement and the Company intends to submit an application to BC Hydro for an electricity purchase agreement under the upcoming Standing Offer. BC Hydro has recently stated that the Standing Offer is expected to be available during the first quarter of calendar 2008.

Synex International Inc. is a public company listed on the TSX with businesses that cover the development, ownership and operation of electrical generation facilities and the provision of consulting engineering services in water resources, particularly hydroelectric facilities.

"signed"

--------------------------------------------------

Greg Sunell, President

Synex International Inc. on 6ix

Earlier from Synex International

Later from Synex International

All Synex International news releases