Business

Q3 2025 Production and Operations Review

Anglo Asian Mining PLC reported record quarterly copper production of 2,287 tonnes in Q3 2025, a 250% increase compared to Q2 2025. Gold production reached 6,798 ounces and silver production totaled 41,605 ounces. For the nine months ending September 30, 2025, copper production was 3,475 tonnes, gold production was 18,912 ounces, and silver production was 103,959 ounces. Total gold bullion sales for the nine months were 14,962 ounces at an average of $3,200 per ounce. The company experienced a negative cash flow of $1.2 million in Q3, increasing net debt to $14.2 million. Revised full year guidance projects copper production of 8,100 to 9,000 tonnes and gold production of 25,000 to 28,000 ounces. Inventory was valued at $11.5 million. Disclaimer*

Anglo Asian Mining PlcOctober 16, 20254
Q3 2025 Production and Operations Review

About this update from Anglo Asian Mining Plc

  16 October 2025 Anglo Asian Mining plc Q3 2025 Production and Operations Review Two new mines entered production during 2025 Record quarterly copper production in Q3 2025 of 2,287 tonnes   Anglo Asian Mining plc ("Anglo Asian", the Group or the "Company"), the AIM listed gold, copper and silver producer focused in Azerbaijan, is pleased to provide the following production, sales and operational review for the three months to 30 September 2025 ("Q3 2025"or the "Quarter") and nine months to 30 September 2025 ("9M 2025").   Due to the increasing proportion of copper in the Group's production in accordance with its growth strategy, the Group will no longer report total production in gold equivalent ounces. Production of copper and gold will continue to be separately reported.   Record quarterly copper production in Q3 2025 ·    Copper production in Q3 2025 increased by approximately 250 per cent. compared to Q2 2025 due to the first production from Demirli and a full quarter of production from Gilar   o Copper production of 2,287 tonnes (Q2 2025: 654 tonnes) § 1,576 tonnes from Gedabek (Q2 2025: 654 tonnes) § 711 tonnes from Demirli (Q2 2025: nil) ·    Gold and silver Q3 2025 production also benefitted substantially by production from the Gilar mine o Gold production of 6,798 ounces (Q3 2024: 2,956 ounces) o Silver production of 41,605 ounces (Q3 2024: 3,315 ounces) ·    Substantial increase in production in Q3 2025 enhances 9M 2025 production o Copper production of 3,475 tonnes (9M 2024: 111 tonnes) o Gold production of 18,912 ounces (9M 2024: 7,660 ounces) o Silver production of 103,959 ounces (9M 2024: 16,061 ounces)   Key developments in Q3 2025 across the Company's portfolio    ·    First full quarter of continuous production from the Gilar mine o 239,120 tonnes of ore grading 2.34 per cent. copper and 1.65 grammes per tonne of gold produced, including: o 71,188 tonnes of ore grading 3.8 per cent. copper and 2.0 grammes per tonne of gold stockpiled at end of September for future processing ·    Demirli commenced production in Q3 2025, significantly enhancing the Company's copper output as part of the strategic shift towards copper o 4,548 dmt tonnes of copper concentrate produced containing 711 tonnes of copper o Demirli ball mill now in operation in addition to the SAG mill ·    Upgrades of the Gedabek flotation plant underway to process higher grade ores and increase operational efficiency, with the second filter press now installed   Revised full year 2025 guidance issued ·    Revised full year guidance released 9 October 2025, reflecting the impact of bringing Demirli into production during the year. The Company expects: o Copper production of 8,100 to 9,000 tonnes o Gold production of 25,000 to 28,000 tonnes   9M 2025 sales and cash update ·    Total gold bullion sales of 14,962 ounces at an average of $3,200 per ounce (9M 2024: 9,220 ounces at an average of $2,287 per ounce) ·    The Group continues to maintain a strong focus on cash and strict cost controls, with overall negative cash flow of only $1.2 million in the Quarter, increasing net debt to $14.2 million as at 30 September 2025 compared to $14.8 million at 31 December 2024 o     Negative cash flow due to start-up capital expenditure and operating expenses at Demirli until concentrate sales can commence ·    Inventory valued at $11.5 million at 30 September 2025 (30 June 2025: $7.0 million), reflecting unsold copper concentrate at Demirli o Gedabek: $7.2 million (30 June 2025: $7.0 million) o Demirli: $4.3 million (30 June 2025: nil)   Anglo Asian CEO Reza Vaziri commented: "I am delighted to report our strong performance in the nine months to end September in this transformational year. The new Gilar and Demirli mines are both performing well, with very strong grades at Gilar in particular. Reflecting these two new assets being in production, we were delighted to deliver a record quarterly copper production of 2,287 tonnes, a milestone for Anglo Asian as we transition to a production profile of mostly copper."   Investor presentation Alongside this announcement, the Company will provide a live presentation via Investor Meet Company on 16 October 2025 at 11:00am BST. Stephen Westhead, Vice President, and Bill Morgan, CFO, will host the presentation which is free to register for and can be accessed here: https://www.investormeetcompany.com/anglo-asian-mining-plc/register-investor   Note that all references to "$" are to United States dollars. Market Abuse Regulation (MAR) Disclosure Certain information contained in this announcement would have been deemed inside information for the purposes of Article 7 of Regulation (EU) No 596/2014, which was incorporated into UK law by the European Union (Withdrawal) Act 2018, until the release of this announcement.   For further information please contact:   Anglo Asian Mining plc Reza Vaziri, Chief Executive Officer Tel: +994 12 596 3350 Bill Morgan, Chief Financial Officer Tel: +994 502 910 400 Stephen Westhead, Vice President Tel: +994 502 916 894 Amir Vaziri, Chief Business Development Officer Tel: +1 (301) 332 9938 SP Angel Corporate Finance LLP (Nominated Adviser and Broker) Ewan Leggat Adam Cowl Tel: +44 (0) 20 3470 0470 Hudson Sandler (Financial PR) Charlie Jack Harry Griffiths   Tel: +44 0)  20 7796 4133   Notes to editors   Anglo Asian Mining plc (AIM:AAZ) is a copper and gold producer with a high-quality portfolio of production and exploration assets in Azerbaijan. The Company produced 377 tonnes of copper and 15,073 ounces of gold for the year ended 31 December 2024. In the nine months to 30 September 2025, the Company produced 3,475 tonnes of copper and 18,912 ounces of gold.   The Company's strategic plan for growth shows a clearly defined path for the Company to transition to a multi-asset, mid-tier, copper and gold producer by 2030, by which time copper will be the principal product of the Company, with forecast annual production of around 50,000 to 55,000 tonnes of copper. It plans to achieve this growth by bringing into production three new mines during the period 2027 to 2030 at Xarxar, Garadag and Zafar, in addition to the newly opened Gilar and Demirli mines. Production commenced at the Gilar mine in May 2025 and Demirli in July 2025.  https://www.angloasianmining.com/   Q3 2025 production overview ·    Copper production of 2,287 tonnes (Q3 2024: 11 tonnes): o 1,576 tonnes from flotation and SART at Gedabek o 711 tonnes from flotation at Demirli ·    Gold production of 6,798 ounces (Q3 2024: 2,955 ounces): o 5,814 ounces contained within gold doré o 984 ounces from flotation and SART production ·    Silver production totalled 41,605 ounces (Q3 2024: 3,315 ounces): o 4,654 ounces contained within gold doré o 36,951 ounces from flotation and SART processing   Q3 2025 sales overview ·    Total gold bullion sales of 5,181 ounces at an average of $3,430 per ounce (Q3 2024: 3,220 ounces at an average of $2,497 per ounce) ·    Total concentrate sales at Gedabek of 5,979 dry metric tonnes ("dmt") with a value of $15.5 million (Q3 2024: nil dmt, $nil) o No sales were made by Demirli in the Quarter but inventory contained 4,547 dmt tonnes of concentrate containing 711 tonnes of copper awaiting sale   Q3 2025 financial overview ·    Cash of $10.4 million ( $11.1 million at 30 June 2025) including restricted cash ·    Debt (including advance from Trafigura) of $24.6 million ( $24.1 million at 30 June 2025) ·    Net debt of $14.2 million ($13.0 million at 30 June 2025) ·    Unsold gold doré and copper concentrate inventory of $11.5 million at 30 September 2025   Ore mined during 9 months to 30 September 2025   Gedabek 12 months to  31 December 2024 6 months to 30 June 2025 3 Months to 30 Sept 2025 Mine Ore mined Average gold grade Ore mined Average gold grade Ore mined Average gold grade   (tonnes) (g/t) (tonnes) (g/t) (tonnes) (g/t) Open pit 443,611 0.73 529,034 0.23 82,993 0.44 Gadir - u/g 167,121 1.58 12,325 2.21 - - Gilar - u/g - - 106,510 1.23 239,120 1.65 Total 610,732 0.96 647,869 0.43 322,113 1.34   Demirli 12 months to  31 December 2024 6 months to 30 June 2025 3 Months to 30 Sept 2025 Mine Ore mined Average copper grade Ore mined Average copper grade Ore mined Average copper grade   (tonnes) (%) (tonnes) (%) (tonnes) (%) Open pit - - - - 423,631 0.43   Gedabek processing and production in 9M 2025   Ore processed by leaching   Quarter ended Ore processed Gold grade of ore processed Heap leach pad crushed ore (tonnes) Heap leach pad ROM ore (tonnes) Agitation leaching plant* (tonnes) Heap leach pad crushed ore (g/t) Heap leach pad ROM ore (g/t) Agitation leachingplant* (g/t) 31 March 2024 120,528 - - 0.68 - - 30 June 2024 110,225 9,698 - 0.59 0.52 - 30 September 2024  110,152 - 18,009 0.65 - 1.93 31 December 2024 79,835 - 128,387 0.53 - 1.54 FY 2024 420,740 9,698 146,396 0.61 0.52 1.58 31 March 2025 106,429 - 149,763 0.40 - 1.16 30 June 2025 133,153 - 154,948 0.40 - 1.13 H1 2025 239,582 - 304,711 0.40 - 1.14 30 Sept 2025 47,202 - 156,773 0.4 - 1.52   * includes previously heap leached ore.   Ore processed by flotation Quarter ended Ore processed Gold content Silver content Copper content   (tonnes) (ounces) (ounces) (tonnes) 31 March 2024 - - - - 30 June 2024 - - - - 30 September 2024 - - - - 31 December 2024 73,990 285 3,985 363 FY 2024 73,990 285 3,985 363 31 March 2025 155,406 535 9,516 729 30 June 2025 166,135 1,193 30,537 900 H1 2025 321,541 1,728 40,053 1,629 30 Sept 2025 156,773 3,185 85,123 1,793     Gold and silver produced as gold doré Quarter ended Gold produced* Silver produced* Gold sales** Gold Sales price   (ounces) (ounces) (ounces) ($/ounce) 31 March 2024 2,259 1,512 3,925 2,080 30 June 2024 2,433 1,532 2,075 2,350 30 September 2024 2,955 1,979 3,220 2,497 31 December 2024 7,280 6,974 6,031 2,655 FY 2024 14,927 12,007 15,251 2,432 31 March 2025 5,758 8,212 4,753 2,843 30 June 2025 5,624 6,699 5,028 3,299 H1 2025 11,382 14,911 9,781 3,077 30 Sept 2025 5,814 4,654 5,181 3,430   Note * including Government of Azerbaijan's share ** excluding Government of Azerbaijan's share   Gold and silver produced by leaching   Quarter ended Gold Silver Agitation leaching (ounces) Heap leaching (ounces) Total   (ounces) Agitation leaching (ounces) Heap leaching (ounces) Total   (ounces) 31 March 2024 - 2,259 2,259 - 1,512 1,512 30 June 2024 - 2,433 2,433 - 1,532 1,532 30 Sept 2024 606 2,349 2,955 415 1,564 1,979 31 Dec 2024 5,231 2,049 7,280 5,006 1,978 6,984 FY 2024 5,837 9,090 14,927 5,421 6,586 12,007 31 March 2025 4,017 1,741 5,758 5,717 2,495 8,212 30 June 2025 3,936 1,688 5,624 4,632 2,067 6,699 H1 2025 7,953 3,429 11,382 10,349 4,562 14,911 30 Sept 2025 4,681 1,133 5,814 3,735 919 4,654   Copper concentrate production and sales   Concentrate Copper Gold Silver Concentrate   Concentrate   production* content* content* content* sales** sales**   (dmt) (tonnes) (ounces) (ounces) (dmt) ($000) Quarter ended             31 March 2024 89 54 7 4,893 71 295 30 June 2024 77 46 5 4,809 260 1,002 30 September 2024 19 11 1 1,336 - - 31 December 2024 1,672 266 133 5,213 1,173 1,493 FY 2024 1,857 377 146 16,251 1,504 2,790 31 March 2025 3,072 534 271 22,109 2,030 3,616 30 June 2025 3,523 654 462 25,334 3,402 6,299 H1 2025 6,595 1,188 733 47,443 5,432 9,915 30 September 2025 6,769 1,576 984 36,951 5,979 15,500   * including Government of Azerbaijan's share ** excludes Government of Azerbaijan's share   Demirli processing and production in 9M 2025       Processed     Unit July to September 2025 Ore feed to plant dry metric tonnes 292,950 Grade per cent. 0.45 Copper content tonnes 1,307 Production Copper concentrate tonnes 4,548 Copper content tonnes 711   Q3 2025 Financial review The Company's net debt increased from $13.0 million at 30 June 2025 to $14.2 million at 30 September 2025 as follows:   Q1 2025 Q2 2025 Q3 2025 $m $m $m $m $m $m Start of quarter   (14.8)   (13.8)   (13.0) Revenue 17.5 23.1 27.8 VAT refund 0.2 1.8 1.6 Interest income 0.2 0.2 0.6 Operating costs (15.2) (18.6) (22.7) Capital expenditure (1.4) (1.5) (3.9) Demirli expenditure - (3.8) (4.3) Debt servicing (0.3) (0.4) (0.3) Inflow / (outflow) in the quarter     1.0   0.8     (1.2) End of quarter    (13.8)*    (13.0)*   (14.2)* *includes net advance from Trafigura of $4.9m at 30 September 2025 (30 June 2025: $4.4m; 31 March 2025: $5.0m).

View stock analysis, news, and events for Anglo Asian Mining Plc

More from Anglo Asian Mining Plc

All Anglo Asian Mining Plc news →