Project Update

· Issued by PLS Group Limited

Filed with ASX · · 7 pages · English

First spodumene concentrate on track for late Q2 with Stage 1 plant construction and mine development advancing rapidly; establishment of DSO operation underway with first sales expected early Q2 Highlights • Plant construction progressing rapidly on multiple fronts. • Civil works well advanced with over 3,800m3 of concrete poured. • Structural steel erection commenced in January with over 1,100 t