Zephyr Energy: Paradox Project update

· Issued by Zephyr Energy PLC

Summary by 6ix AI

Zephyr Energy plc, an oil and gas company, said on August 24, 2026 that its board has chosen to fund additional engineering and well work at its Paradox project in Utah, U.S., to prepare for a higher production rate in the project's initial phase. The work will be funded from the company's existing cash resources.

Key details

  • Engineering work is underway to design a modular gas processing system with up to 15 million standard cubic feet of gas per day of capacity. Chief Executive Colin Harrington said earlier base case estimates were 5 million standard cubic feet a day.
  • Gas is expected to be supplied first by the State 36-2R and Federal 28-11 wells. Well work to equip, connect and return these wells to production will start after the engineering work and final processing design are completed.
  • Enbridge has completed a required in-line inspection of its 16-inch pipeline. Its excavation and visual inspection of four short sections is ongoing, with no concerns or safety issues noted to date. Enbridge is funding all inspection work on the pipeline.
  • Zephyr has chosen preferred new well locations for follow-on drilling and will give locations and permitting details when well planning is finalised. Plans to connect the State 16-2 well will follow after first gas.
  • Zephyr continues to work on a potential farm-out (bringing in a partner to share the project) and a proposed US$15 million commodity purchase agreement, first announced on July 27, 2026.

What’s still pending

  • First gas and commercial production depend on Enbridge obtaining regulatory approval to raise the pipeline's operating pressures and carry Zephyr's gas through its 16-inch pipeline into the Williams-operated Northwest Pipeline system.
  • The timing of that regulatory approval remains uncertain.
  • Additional production from new and existing wells will follow only as cash flow, planning and regulatory approvals allow.
  • The farm-out is potential and the US$15 million commodity purchase agreement is proposed; neither is complete.

6ix AI wrote this summary from the release below and checked it against the release.

Prior to publication, the information contained within this announcement was deemed by the Company to constitute inside information as stipulated under the UK Market Abuse Regulation. With the publication of this announcement, this information is now considered to be in the public domain.

24 August 2026

Zephyr Energy plc

("Zephyr" or the "Company")

Paradox Project update

Zephyr Energy plc (AIM: ZPHR) is pleased to provide an update on current activity on its project in the Paradox Basin, Utah, U.S. (the "Paradox project").

Highlights:

·    Zephyr's board of directors (the "Board" or the "Directors") has elected to fund additional engineering and well work to prepare for a higher production rate during the initial phase of the project's development.

o  This is supported by the Board's confidence that the necessary regulatory approvals needed for up-rating the operating pressures of Enbridge-operated 16-inch pipeline will be obtained; and

o  Zephyr's additional work is progressing in parallel with the Enbridge-led regulatory approval process, and will be funded out of the Company's existing cash resources.

·    Engineering work is underway to design a modular gas processing system with up to 15 million standard cubic feet of gas per day (mmscf/d) of production capacity.  Gas will be initially supplied by the State 36-2 LNW-CC-R well (the "State 36-2R") and the Federal 28-11 well.

o  Expense related to "well work" (or "workovers") involves preparations to allow for existing wells to return to production in a timely manner.

·    Zephyr has also high-graded new well locations for follow-on drilling. Locations and permitting details will be announced as and when well planning efforts are finalised. Plans for the tie in of the State 16-2 well will be detailed after first gas is achieved.

·    Enbridge's operation to excavate and visually inspect four short sections of the existing 16-inch pipeline is ongoing, with no concerns or safety issues noted to date.

Colin Harrington, Zephyr's Chief Executive, said: "The successful completion of the Enbridge in-line inspection provided the Board with confidence that the up-rating of operating pressures required for the pipeline to accept Zephyr's increasing gas volumes will not result in any further operational hurdles.

"The Board has also gained confidence that the Enbridge-led regulatory approval process will conclude in a satisfactory manner.  The Board has therefore approved an allocation of funding for additional engineering (related to gas processing) and well work operations, with a goal to increase initial processing capacity up to 15 mmscf/d - a significant increase over earlier base case estimates of 5 mmscf/d. This work will be fully funded from the Company's existing cash resources.

"Initial gas volumes would be provided by the State 36-2R and the Federal 28-11 wells, with additional production from new and existing wells to follow as cash flow, planning and regulatory approvals allow.

"Our aim is to progress operational work in parallel with the Enbridge-led regulatory approval process, in order to expedite the timing for first gas and commercial production.  While the timeline for Enbridge's approval process remains pending, Zephyr's goal is to be prepared to deliver first gas and commercial production as soon as possible once approvals are secured.

"The Company also continues to progress both the potential farm-out and the proposed US$15 million commodity purchase agreement (as announced on 27 July 2026). Further updates will be provided in due course."

Background

In relation to the Paradox project gas transportation, Enbridge continues to execute on its workstream to obtain the necessary regulatory approval needed to export Zephyr's natural gas through its 16-inch pipeline and into the Williams-operated, Northwest Pipeline system.

As indicated previously, regulatory approval remains a critical item for Zephyr to achieve first gas and commercial production from the Paradox project. To date, Enbridge has successfully completed a mandatory in-line inspection of the pipeline, and the process of excavating and visually inspecting four short sections of pipeline is well underway.  Enbridge views such inspections as routine and they are not considered a risk to achieving first gas.  All inspection work on the 16-inch pipeline is being funded by Enbridge.

Zephyr is highly confident that regulatory approval for gas export will be granted, although the exact timing for such approval remains uncertain. The Company will continue to keep shareholders updated as Enbridge completes its inspection process and the timing for the regulatory approval process becomes better defined.

In the interim, the Board has elected to fund additional engineering and operations work to prepare for the initial phase of commercial production. Detailed engineering work related to design of a modular gas processing system with up to 15 mmscf/d of production capacity is underway, with gas expected to be initially supplied by the State 36-2R and the Federal 28-11 wells. Well work to equip, tie-in, and return the 36-2 and the 28-11 wells to production will commence after the engineering work and final processing design has been completed.

The Company has also high-graded future well locations for follow-on drilling, and will announce locations and permitting details when well planning efforts are finalised.

The State 36-2R well was drilled and production tested by Zephyr in 2025. The production test achieved a peak flow rate of 2,848 barrels of oil equivalent per day, with no material drop in bottom hole pressure, and without the use of any fracture stimulation, suggesting that the well ranks in the top 6% of gas wells across the Lower 48 U.S States.

The Federal 28-11 well was drilled in 2008, and was subsequently shut-in due to pipeline and infrastructure constraints. Prior to shut-in, the well produced over 0.36 billion cubic feet of natural gas and circa 93,000 barrels of oil. The well was acquired by Zephyr in 2022 (as announced on 22 September 2022). In 2023, the Company briefly and successfully recommenced production in order to understand the well's potential to contribute to future field production.

Contacts

Zephyr Energy plc

Colin Harrington (CEO)

Chris Eadie (Group Finance Director and Company Secretary)

Tel: +44 (0)20 3475 4389

Allenby Capital Limited - AIM Nominated Adviser

Jeremy Porter / Vivek Bhardwaj

Tel: +44 (0)20 3328 5656

Turner Pope Investments - Joint-Broker

Guy McDougall / Andy Thacker

Canaccord Genuity Limited - Joint-Broker

Henry Fitzgerald-O'Connor / Charlie Hammond

Celicourt Communications - PR

Mark Antelme / Kristina Qevani

Tel: +44 (0)20 3657 0050

Tel: +44 (0)20 7523 8000

Tel: +44 (0) 20 7770 6424

Notes to Editors

Zephyr Energy plc (AIM: ZPHR) is a technology-led oil and gas company focused on responsible resource development in the Rocky Mountain region of the United States.

Its flagship operated asset is the circa 70,000-acre Paradox project in Utah.  An independent 2025 Competent Persons Report by Sproule International of the Company's White Sands Unit (20,000 acres) confirmed 2P reserves of 35.3 million barrels of oil equivalent ("boe") and total recoverable resources of 74.2 million boe within the White Sands Unit.

Zephyr also holds a portfolio of non-operated production interests across the Williston and other Rocky Mountain basins, supported by a US$100 million strategic partnership designed to accelerate growth and enhance cash flow.