TORONTO, May 14, 2012 /CNW/ - Liberty Mines Inc. (TSX: LBE) ("Liberty" or the "Company") today reported its financial results for the 3-month period ended March 31, 2012. All amounts are in Canadian currency.
"Our first quarter was marked by our most significant milestone since we began our turn-around strategy nine months ago," said Mr. Chris Stewart, President and CEO of Liberty Mines. "With the re-start of mining and milling operations now behind us, we can focus our efforts on maximizing production of our nickel concentrate, and continuing to add to our resources and reserves through a strategic exploration program. These efforts will not only generate improved financial results in the near term through increased revenue and cash flow, they will also effectively position us for future long-term growth."
Q1 2012 Operational Highlights
-
Commissioned the Company's mill and concentrator at Redstone and resumed
production effectively March 31, with cash flow from operations
expected to resume in the second quarter.
-
Announced operational and strategic targets for 2012, including
production of 4 million pounds of nickel, which will be supplied by the
Company's McWatters mine.
-
Received a $5,000,000 loan from Jien International Investments Ltd., the
Company's controlling shareholder. The loan provided working capital
to address requirements stemming from resumption of mining activities.
-
Executed the right to purchase half of the two percent Hart net smelter
royalty (NSR) from Canadian Arrow Mines (CAM) for a lump sum payment of
$1 million. The purchase represents a strategic decision to minimize
royalty payments as Liberty realizes the full potential from its
property.
-
Announced plans to proceed with the development of a feasibility study
on the Company's Hart Project after encouraging preliminary results
from internal assessments. The feasibility study is expected by late
2012.
- On March 30, 2012 Liberty Mines received the Angus D. Campbell safety award from the Porcupine Mines Safety Group. The award recognized Liberty Mines for having zero (0) lost time injuries in the year 2011.
Highlights Subsequent to Quarter End
- Resumed shipment of concentrate produced at the Company's Redstone Mill to the Xstrata smelter in Sudbury.
- Appointed David Birch as the Company's Chief Financial Officer effective June 1, 2012.
Selected financial highlights
| All amounts in thousands except share data | March 31, 2012 | March 31, 2011 |
| Revenue | $19 | $2,119 |
| Cost of sales | $4,815 | $5,183 |
| Net (loss) income | $(7,990) | $(5,130) |
| Basic earnings (loss) per share | $(0.04) | $(0.03) |
| March 31, 2012 | December 31, 2011 | |
| Cash and Cash Equivalents | $547 | $1,304 |
| Total Assets | $91,505 | $84,265 |
| Total Liabilities | $105,852 | $91,064 |
Review of Q1 Financial Performance
Revenue for Q1 2012 was $19,240 down from $2.1 million for Q1 2001. The
year-over-year decline was due to a shut-down of mining and milling
operations initiated by the Company in February, 2011. Mining and
milling operations were effectively re-started on March 31, 2012.
Given the timing of the start date, the company expects revenue and
cash flow from operations to resume in Q2 2012. Revenue generated in Q1
2012 stemmed from the final settlement on precious metals shipped in
2011.
Net loss for Q1 2012 was $8.0 million or $0.04 per basic and fully diluted share. The loss included amortization expenses of $1.4 million, interest on long-term debt of $2.2 million and dividends on preferred shares of $0.3 million. In the same period of 2011, Liberty recorded a net loss of $5.1 million or $0.03 per basic and fully diluted share. Liberty's mining and milling operations were partially functional in Q1 of 2011.
At March 31, 2012, Liberty had cash and cash equivalents of $546,600. This compares to $1.3 million at year end 2011.
Liberty's financial statements for the period ended March 31, 2012 are available at www.libertymines.com and www.sedar.com. The financial statements should be read in conjunction with the accompanying notes and management's discussion and analysis.
Outlook
"The ongoing shipment of concentrate to Xstrata since re-starting
operations, and the encouraging results of our drilling activities add
to our recent momentum," Mr. Stewart also said. "We believe that this
progress will be sustained through 2012 as we target production of 4.0
million pounds of nickel and the development of a feasibility study at
our Hart Project by year end."
About Liberty Mines Inc.
Liberty Mines Inc. is a mid-tier producer of nickel and is focused on
the exploration, development and production of nickel, copper, cobalt
and platinum group metals from its properties in Ontario, Canada. It
owns and operates the only nickel concentrator in the Shaw Dome, a
prospective nickel belt region near Timmins, Ontario. With a new
management team in place, Liberty is focused on growth initiatives not
only through a more aggressive exploration program on its current
properties but also through potential acquisition or partnership
opportunities beyond its core Timmins area projects.
CAUTIONARY STATEMENT
No stock exchange, securities commission or other regulatory authority
has approved or disapproved the information contained herein. This News
Release includes certain "forward looking statements". All statements
other than statements of historical fact included in this release,
without limitation, statements regarding future plans and objectives of
Liberty, are forward looking statements that involve various risks and
uncertainties. There can be no assurance that such statements will
prove to be accurate and actual results and future events could differ
materially from those anticipated in such statements. Important factors
that could cause actual results to differ materially from Liberty's
expectations are: exploration risks; commodity prices; regulatory
approvals; receipt of mining permits and leases; and assumed startup
and operating costs detailed herein and from time to time in the
filings made by Liberty with securities regulators. Forward-looking
statements speak only as of the date on which they are made. The
Company undertakes no obligation to publicly update any such statement
or reflect new information or the occurrence of future events or
circumstances, except where required by securities regulations.
Accordingly, readers should not place undue reliance on forward-looking
statements.
Chris Stewart, President & CEO
Liberty Mines
(416) 226-4360 ext 203
cstewart@libertymines.com
Joe Racanelli
TMX Equicom
416 815 0700 ext 243