Galan Lithium LimitedASX: GLN

Hombre Muerto West Project Update

· Issued by Galan Lithium Limited via ACCESS Newswire

Summary by 6ix AI

Galan Lithium Limited said the production ramp-up of its Hombre Muerto West (HMW) Phase 1 lithium chloride operation in Catamarca, Argentina continues. It said first lithium chloride concentrate sales remain on track for delivery in the fourth quarter of calendar year 2026.

Key details

  • Galan expects to reach its initial targeted throughput rate of 4ktpa LCE (4 thousand tonnes a year of lithium carbonate equivalent) in the first half of calendar year 2027, as warmer seasonal conditions arrive.
  • The nanofiltration plant, which removes impurities from the brine before further concentration, has recorded over 3 months of data with 98% or greater rejection of sulphate. Galan says impurity separation and recoveries to date support upgrading the concentrate to up to the targeted 6% lithium content.
  • The Puna region, where HMW is located, had a severe winter with heavy snowfall and wind. HMW operations continued, with minor periods when they were suspended.
  • Authium Limited plans to build and bring to site an additional pressure vessel skid to add to the existing Phase 1 plant capacity, intended to make operations more resilient through future winters.
  • Earthworks have started for the expansion of HMW Phase 1 to 5.2ktpa (5.2 thousand tonnes a year).

What’s still pending

  • First lithium chloride concentrate sales are expected to be delivered in the fourth quarter of calendar year 2026.
  • The initial 4ktpa LCE throughput rate is expected in the first half of calendar year 2027.
  • The higher production volumes from the 5.2ktpa expansion are expected in the second half of calendar year 2027.
  • The additional pressure vessel skid is planned by Authium Limited and has not yet been built.

6ix AI wrote this summary from the release below and checked it against the release.

WEST PERTH, AU / ACCESS Newswire / September 23, 2026 / Galan Lithium Limited (ASX:GLN) (Galan or the Company) is pleased to provide the following update on the production ramp-up of its Hombre Muerto West (HMW) Phase 1 lithium chloride operation in Catamarca, Argentina.

Figure 1. Aerial view of HMW Phase 1 final evaporation ponds

Production Ramp-Up and First Sales

The ramp-up of the HMW Phase 1 operation continues to progress, with the productivity of the nanofiltration plant keeping pace with current site evaporation rates. First LiCl concentrate sales remain on track for delivery in Q4 CY2026. Galan is confident that, as the warmer seasonal conditions arrive over the coming months, the initial targeted throughput rate of 4ktpa LCE should be achieved in the first half of calendar year 2027.

Figure 2. LiCl concentrate pond following impurity removal.

Figure 3. Aerial view of the HMW site

The nanofiltration plant, which removes impurities from the HMW brine ahead of further concentration, continues to perform in line with piloting results and Company expectations. The plant has recorded over 3 months of data with a 98% or greater rejection of sulphate. Impurity separation and recoveries achieved to date support the upgrading of LiCl concentrate to up the targeted 6% Li content.

The Puna region in the Andes, where HMW is located, has endured one of the most severe winter periods in recent history with significant snowfall and wind. Notwithstanding, HMW operations have continued safely with minor periods where operations were suspended. To provide greater operational resiliency through future winters, Authium Limited plans to construct and mobilise to site an additional pressure vessel skid which would augment the existing Phase 1 plant capacity. Additionally, earthworks associated with the expansion of Phase 1 HMW to 5.2ktpa have commenced at site, with the higher production volumes expected to be realised in the second half of calendar year 2027.

Galan's Managing Director Juan Pablo Vargas de la Vega commented:

"We are pleased with the continued progress of the ramp-up at Hombre Muerto West. The nanofiltration plant is performing in line with our expectations, and the additional pressure vessel capacity being installed by Authium will further strengthen the plant's resilience. With productivity continuing to improve and warmer conditions approaching, we remain confident in reaching our initial 4ktpa throughput target and delivering first LiCl concentrate sales in the fourth quarter of this year."

For and on behalf of the Galan Board.

For further information contact:

COMPANYMEDIA
Juan Pablo ("JP") Vargas de la VegaMatt Worner
Managing DirectorVector Advisors
jp@galanlithium.com.aumworner@vectoradvisors.au
+ 61 8 9214 2150+61 429 522 924

SOURCE: Galan Lithium Limited

View the original press release on ACCESS Newswire