DENVER, March 21 /CNW/ - Golden Star Resources Ltd. (AMEX: GSS) (TSX: GSC) is pleased to announce the commencement of mining on its Pampe gold project in Ghana.

The Pampe project is a satellite deposit on the Akropong Trend, west of Bogoso, where we have been exploring for a number of years and have identified a 219,500 ounce mineral reserve, which was included in our year-end 2006 mineral reserve estimate for Bogoso/Prestea. Ore mining at Pampe commenced in March.

Peter Bradford, President and CEO, said, "We are very excited to announce the commencement of mining and delivery of ore to Bogoso from the Pampe project, for three reasons. First, an additional 219,500 ounces of gold Mineral Reserves is important; second, for us these Mineral Reserves are in a new mineral province, the Akropong Trend, approximately 30 kilometers west of the Ashanti Gold Belt, which potentially provides a second exploration front to support our activities at Bogoso/Prestea; and third, the additional gold mineral reserve ounces at Pampe are non-refractory and will therefore provide a source of feed for our Bogoso CIL processing plant at a very attractive average grade of 3.3 grams per tonne (g/t) gold."

LOCATION

The Pampe deposit is located 26 kilometers north-northwest of our expanded Bogoso processing plant complex and 1.7 kilometers north of the highway between Bawdie and Asankragwa in the Western Region of Ghana. The Pampe deposit lies within Lower Proterozoic Birimian volcano-sedimentary sequences dominated by a major northeast-southwest trending structural feature referred to as the Akropong Trend. The Akropong Trend runs parallel to and about 30 kilometers west of the well known Ashanti Trend and represents a major deep-seated fault system which hosts gold-rich hydrothermal systems.

OWNERSHIP

Golden Star entered into two option agreements to acquire the area covering the Pampe project area in 1999 and 2000. Under the terms of the option agreements, Golden Star had the right to acquire the area by the payment to the vendors of $8 to $10 per ounce of Proven and Probable Mineral Reserve contained within a feasibility study on the project. Based on a feasibility study completed in mid-2006, the options have been exercised at a cost of approximately $1.4 million, inclusive of all past payments.

PERMITTING AND MINING

Environmental permitting for the project was completed in late 2006 and work to construct the access roads to the proposed pit commenced immediately afterwards and is now complete. Although applications for a Mining Lease and Mining Permit are still being processed and are expected soon, we have commenced mining at Pampe pursuant to a special mining permit allowing us to mine a 100,000 tonne bulk ore sample. Consequently, waste mining commenced in February and the first ore was mined and delivered to the processing plant in March. We expect that the mining lease will be issued before the bulk sampling permit is fully utilized.

The mineralization at Pampe is non-refractory and will be processed through the Bogoso carbon-in-leach (CIL) processing plant. Testwork on the Pampe ore types indicate that gold recoveries of around 90% for the oxide material and around 83% for the fresh sulfide material are achievable.

Peter Bradford stated, "We ceased mining at the Plant-North pit in December and had expected that ore mining at Pampe would have commenced prior to now, but delays in exercising the option agreements to acquire the Property stopped this from happening. Although we are pleased that ore mining did commence in March, the delay caused us to process lower grade, lower recovery stockpiled material through the Bogoso CIL processing plant to fill the gap. This is now expected to result in Bogoso/Prestea production for the first quarter being short of guidance."

MINERAL RESERVES

Additional work on the property in the second half of 2006 has resulted in an increase in the Mineral Reserves relative to feasibility study assessment. As at December 31, 2006 a Probable Mineral Reserve of 2.06 million tonnes grading 3.31 grams of gold per tonne for 219,500 ounces of gold contained has been estimated at Pampe, and these Mineral Reserves were included in our year-end Mineral Reserve statement for Bogoso/Prestea, as tabulated below.

      Pampe Prospect - Mineral Reserves as at December 31, 2006

                                                           Contained
                         Reserve      Tonnes     Grade       Ounces
    Material Type        Category   (millions)  (Au g/t)  (thousands)
---------------------- ------------ ---------- ---------- ------------
   Oxide(1)              Probable     0.59       2.71        51.6
---------------------- ------------ ---------- ---------- ------------
   Transitional          Probable     0.30       3.03        29.6
---------------------- ------------ ---------- ---------- ------------
   Fresh(2)              Probable     1.16       3.70        138.3
---------------------- ------------ ---------- ---------- ------------
TOTAL                    Probable     2.06       3.31        219.5
---------------------- ------------ ---------- ---------- ------------

(1) Oxide material is that material that has had all sulfides leached out via weathering. These materials are softer and thus easier to process.

(2) Fresh material is material found at depth that is not weathered, is non-refractory in nature and can be processed through our new BIOX(R) plant.

MINERAL RESOURCES

As at December 31, 2006, the estimated Mineral Resources, which are in addition to the Mineral Reserves, were included in our year-end Mineral Resource statement for Bogoso/Prestea and which are in addition to the Mineral Reserves, and are as follows:

  Pampe Prospect - Mineral Resources as at December 31, 2006

                            Tonnes                Grade
      Category            (millions)            (Au g/t)
--------------------- ------------------- ---------------------
      Indicated              0.29                 3.18
--------------------- ------------------- ---------------------
      Inferred               0.13                 3.42
--------------------- ------------------- ---------------------

Notes to the Mineral Reserves and Mineral Resources:

1. The stated Mineral Reserves and Mineral Resources have been prepared in accordance with Canada's National Instrument 43-101 Standards of Disclosure for Mineral Projects. Mineral Reserves are equivalent to Proven and Probable Reserves and Mineral Resources are equivalent to Mineralized Material as defined by the United States Securities and Exchange Commission (SEC) Industry Guide 7.

2. The Mineral Reserves have been prepared under the supervision of Mr. Peter Bourke, P.Eng., Vice President Technical Services for the Company. The Mineral Resources have been prepared under the supervision of Mr. S. Mitchel Wasel, Exploration Manager for the Company. Both Mr. Bourke and Mr. Wasel are qualified persons as defined by Canada's National Instrument 43-101.

3. The Mineral Reserves were estimated using a gold price of $480 per ounce, approximately the three year average price required by the SEC, and Mineral Resources were estimated using a gold price of $560 per ounce. The Mineral Reserves are based on a mine plan derived from an optimized pit shell. The Mineral Resources are contained within an optimized pit shell and are in addition to the Mineral Reserves.

4. The Pampe Project Mineral Reserves and Mineral Resources were included in the Bogoso/Prestea Mineral Reserve and Mineral Resource statement as at December 31, 2006.

5. Optimized pit parameters were based on historical mining and processing costs at Bogoso and assume haulage to the existing Bogoso CIL plant. Metallurgical testwork (AMMTEC) on the Pampe ore types indicate that they are non-refractory and gold recoveries of around 90% for the oxide material and around 83% for the fresh sulfide material are achievable. Geotechnical drilling and tests have been reviewed by SRK Consulting and their recommendations for pit wall angles have been incorporated into the optimized pit parameters. Mining dilution of 5% and mining recovery of 100% has been assumed.

6. Mineral Resources are reported using a block grade cut-off of 0.82 grams per tonne for oxide material, 0.91 grams per tonne for transitional material and 0.95 grams per tonne for fresh material. High-grade assays within the sample population were cut using an upper cut of 20 grams of gold per tonne for oxide and 30 grams of gold per tonne for transition and fresh samples.

7. Mineral Reserves and Mineral Resources are expressed on a 100% basis. Golden Star's share of the Mineral Reserves and Mineral Resources is subject to the Government of Ghana's 10% carried interest which entitles them to a 10% dividend once our capital costs have been recovered.

8. Numbers may not add due to rounding.

Quality Assurance-Quality Control (QA-QC)

Drilling of the Pampe deposit has been conducted periodically over the last two years using both Reverse Circulation (RC) and Diamond Core drilling. All diamond drill core is split at Bogoso, with half the core lengths sent to TransWorld Laboratories in Tarkwa, Ghana, for sample preparation and analysis. The remaining half or quartered (depending on metallurgical test selection) core is stored at Bogoso for future inspection and detailed logging, to provide valuable information on mineralogy, structure, alteration patterns and the controls on gold mineralization.

All RC holes are sampled in three-meter composites with all intervals exceeding 0.2 grams of gold per tonne being resampled on one meter intervals.

All sample preparation, crushing, and analysis are carried out at the TransWorld Laboratories in Tarkwa, Ghana. Samples are subjected to 12-hour BLEG (Bulk Leach Extractable Gold) Leachwell analysis of 1,000 gram sub-samples pulverized to 85% at minus 75 microns (200#) to a quoted accuracy of 10 parts per billion of gold. All analytical work is subject to a systematic and rigorous QA-QC. At least 5% of samples are blanks, duplicates and certified standards and the accuracy of the analysis is confirmed to be acceptable from comparison of the recommended and actual 'standard' results.

Significant drill intersections are summarized in the following table with a complete set of intersections available on our web site www.gsr.com. Additional drilling is planned for 2007 to test some of the higher grade shoots that exhibit widths and grades which could be exploitable via underground mining methods.

Pampe South Prospect Significant Reverse Circulation and Diamond Drill
                                Results


                                  NORTH    EAST   Elevation From To
           Hole ID                 (m)      (m)      (m)    (m)   (m)
------------------------------  --------- ------- --------- ---- ----
PPSDD002                          23,586  28,026     5,098   66   84
PPSDD004                          23,731  27,950     5,139  188  196
PPSDD004                          23,731  27,950     5,139  214  225
PPSDD007                          23,489  27,925     5,122  116  145
PPSDD007                        Including                   123  129
PPSDD007                        Including                   131  139
PPSDD009                          23,489  27,875     5,148  153  160
PPSDD010                          23,423  27,925     5,148  233  255
PPSDD011                          23,436  27,900     5,147  182  214
PPSDD012                          23,467  27,825     5,174  146  158
PPSDD013                          23,484  27,947     5,120  165  177
PPSDD017                          23,533  27,925     5,112   54   79
PPSDD020                          23,478  27,775     5,181  128  137
PPSDD021A                         23,492  27,756     5,080  124  131
PPSRC006                          23,569  28,000     5,098   87  111
PPSRC006                        Including                    95  100
PPSRC008                          23,535  27,950     5,105   80  131
PPSRC008                        Including                    92   97
PPSRC008                        Including                   110  117
PPSRC009                          23,536  27,847     5,147   15   27
PPSRC009                                                     50   56
PPSRC011                          23,530  27,750     5,192   48   56
PPSRC011                                                     63   76
PPSRC023                          23,508  27,775     5,178   75   85
PPSRC024                          23,556  27,775     5,190    8   29
PPSRC026                          23,563  27,924     5,109   17   57
PPSRC026                        Including                    21   25
PPSRC026                        Including                    35   40
PPSRC026                                                     84   89
PPSRC027                          23,579  27,950     5,108   11   27
PPSRC027                        Including                    23   27
PPSRC028                          23,654  28,000     5,110   57   65
PPSRC028                                                     72   97
PPSRC030                          23,532  27,819     5,161  112  133
PPSRC030                        Including                   113  121
PPSRC031                          23,560  27,823     5,163   32   43
PPSRC032                          23,544  27,875     5,127   24   46
PPSRC032                                                     67   85
PPSRC034                          23,481  27,851     5,162  138  147
PPSRC035                          23,495  27,750     5,180   83   91
PPSRC037                          23,530  27,772     5,186   44   64
PPSRC039                          23,616  28,050     5,090   29   38
PPSRC040                          23,641  28,070     5,088   13   23
PPSRC041                          23,579  28,050     5,089   81  106
----------------------------------------------------------------------


                                                         Approx.
                                                 Drilled  True   Grade
                                Dip     Azimuth   width   Width   Au
          Hole ID            (degrees) (degrees)   (m)     (m)   (g/t)
---------------------------- --------- --------- ------- ------- -----
PPSDD002                          -52        97    18.0    12.2   2.6
PPSDD004                          -52       281     7.6     5.2   6.3
PPSDD004                          -52       281    11.0     7.5   6.6
PPSDD007                          -45       106    29.4    22.5  12.2
PPSDD007                          -45       106     6.0     4.6  39.0
PPSDD007                          -45       106     8.0     6.1   9.3
PPSDD009                          -58        92     6.9     4.2  10.0
PPSDD010                          -43        93    21.5    17.0   5.9
PPSDD011                          -49        93    32.2    23.2   2.9
PPSDD012                        -53.5        91    12.0     8.0   4.7
PPSDD013                        -50.5        93    12.0     8.4   7.3
PPSDD017                          -50        90    25.0    17.7   2.7
PPSDD020                          -52        94     9.0     6.1   8.8
PPSDD021A                         -64        88     7.0     3.6   8.7
PPSRC006                          -50        90    24.0    17.0   6.0
PPSRC006                          -50        90     5.0     3.5  13.0
PPSRC008                          -51        96    51.0    35.4   4.4
PPSRC008                          -51        96     5.0     3.5   9.1
PPSRC008                          -51        96     7.0     4.9   8.7
PPSRC009                          -50        90    12.0     8.5   4.0
PPSRC009                          -50        90     6.0     4.2  16.7
PPSRC011                          -50        89     8.0     5.7   8.1
PPSRC011                          -50        89    13.0     9.2   8.9
PPSRC023                          -52        98    10.0     6.8  11.0
PPSRC024                          -51       100    21.0    14.6   5.4
PPSRC026                          -50        96    40.0    28.3   5.0
PPSRC026                          -50        96     4.0     2.8  10.6
PPSRC026                          -50        96     5.0     3.5  12.8
PPSRC026                          -50        96     5.0     3.5  13.1
PPSRC027                          -50        90    16.0    11.3   7.5
PPSRC027                          -50        90     4.0     2.8  20.8
PPSRC028                          -49       279     8.0     5.8   6.8
PPSRC028                          -50       278    25.0    17.7   2.2
PPSRC030                          -60        94    21.0    12.0   2.3
PPSRC030                          -60        94     8.0     4.6   4.4
PPSRC031                          -50        99    11.0     7.8   5.3
PPSRC032                          -52        95    22.0    15.0   3.4
PPSRC032                          -52        95    18.0    12.3   3.6
PPSRC034                          -52        91     9.0     6.1   5.8
PPSRC035                          -45        96     8.0     6.1   8.5
PPSRC037                          -50        88    20.0    14.1   6.9
PPSRC039                          -50        87     9.0     6.4  10.8
PPSRC040                          -50        90    10.0     7.1   9.5
PPSRC041                          -50        97    25.0    17.7   2.5
----------------------------------------------------------------------

COMPANY PROFILE

Golden Star holds a 90% equity interest in the Bogoso/Prestea and Wassa open-pit gold mines in Ghana. In addition, Golden Star has an 81% interest in the currently inactive Prestea Underground mine in Ghana and various property interests elsewhere in the country, as well as other gold exploration interests in West Africa and in the Guiana Shield of South America. Golden Star's gold production is expected to increase to 390,000 ounces in 2007, nearly doubling gold sales relative to 2005 and 2006. Golden Star has approximately 232 million common shares outstanding.

Note regarding Canada's National Instrument 43-101: The above disclosure has been reviewed by our Qualified Persons, Mr. S. Mitchel Wasel, Exploration Manager in Ghana, and Mr. Peter Bourke, P.Eng., Vice President Technical Services.

Cautionary Note to US Investors concerning estimates of Measured and Indicated Mineral Resources: US investors are advised that while the terms "measured mineral resources" and "indicated mineral resources" are recognized and required by Canadian regulations, the US Securities and Exchange Commission does not recognize them. US investors are cautioned not to assume that any part or all of the mineral deposits in these categories will ever be converted into reserves.

Cautionary Note to US Investors concerning estimates of Inferred Mineral Resources: US investors are advised that while the term "inferred mineral resources" is recognized and required by Canadian regulations, the US Securities and Exchange Commission does not recognize it. "Inferred mineral resources" have a great amount of uncertainty as to their existence, and great uncertainty as to their economic and legal feasibility. It cannot be assumed that all or any part of an inferred mineral resource will ever be upgraded to a higher category. Under Canadian rules estimates of inferred mineral resources could not form the basis of feasibility or other economic studies. US investors are cautioned not to assume that part or all of the inferred mineral resource exists, or is economically or legally mineable.

Statements Regarding Forward-Looking Information: Some statements contained in this news release are forward-looking statements within the meaning of the Private Securities Litigation Reform Act of 1995. Investors are cautioned that forward-looking statements are inherently uncertain and involve risks and uncertainties that could cause actual results to differ materially. Such statements include comments regarding anticipated increases in production, receipt of a Mining Lease and Mining Permit for the Pampe deposit, gold recoveries from Pampe ore, the establishment and estimates of mineral reserves and non-reserve mineral resources, the recovery of any mineral reserve, planned operations, production, grade, recoveries, and planned exploration activities. Factors that could cause actual results to differ materially include timing of and unexpected events during exploration, construction and start-up; variations in ore grade; variations in relative amounts of refractory, non-refractory and transition ores; variations in tonnes mined, crushed or milled; delay or failure to receive board or government approvals; including the Mining License and Mining Permit for the Pampe deposit; technical or permitting issues, and fluctuations in gold price and costs. There can be no assurance that future developments affecting the Company will be those anticipated by management. Please refer to the discussion of these and other factors in our Form 10-K for 2005.

Golden Star Resources Ltd on 6ix

Earlier from Golden Star Resources

Later from Golden Star Resources

All Golden Star Resources news releases