EDMONTON, Dec. 5, 2013 /CNW/ - At its annual Investor Day conference in Toronto today, Capital Power Corporation (TSX: CPX) ("Capital Power" or "the Company") announced a number of positive corporate developments. The Company also provided financial and other targets for 2014.
Development agreement with ENMAX Corporation (ENMAX) for Genesee 4 & 5
Capital Power and ENMAX have executed a Letter of Intent to pursue joint
venture agreements to develop, construct, own and operate the Genesee 4
& 5 facility. Agreements are expected to be completed in the first
quarter of 2014.
The proposed Genesee 4 & 5 will be a natural gas-fired combined cycle generation facility that will be built on a site near Capital Power's Genesee facility west of Edmonton, Alberta. Genesee 4 & 5 will be utilizing the latest state-of-the-art high efficiency gas turbine technology and will have a generation capacity of up to 1,050 megawatts.
Capital Power will lead the construction of the project and will be the operator of the facility. Construction of the project is expected to be completed between 2018 and 2020 when additional generation is required to meet growing demand and to replace generation from the retirement of coal-fired units in the province.
"I'm excited about the prospect to have ENMAX as our partner in the Genesee 4 & 5 facility in Alberta," said Brian Vaasjo, President and CEO of Capital Power. "This agreement builds on a similar partnership that we have on the Shepard Energy Centre and reinforces our leadership position in the attractive Alberta market."
Port Dover & Nanticoke wind facility begins commercial operations
On November 7, 2013, the Port Dover & Nanticoke wind project in Ontario
began commercial operations. The 105-megawatt wind facility was
completed on time and under its $340 million budget, with final
construction costs expected to be approximately $315 million. The Port
Dover & Nanticoke wind project was awarded a 20-year power purchase
agreement in April 2010 with the Ontario Power Authority (OPA), as part
of the OPA's Feed-in-Tariff (FIT) program. The contracted price for
power at commercial operations is $144 per megawatt hour and
thereafter, 20 per cent of the contract price will escalate annually at
inflation throughout the 20-year term.
"We are excited to add another successful wind construction project to our track record," said Mr. Vaasjo. "Completing the project under budget is a testament to our strong development and construction teams, whose expertise represents a real competitive advantage for Capital Power."
Shepard Energy Centre project on schedule and below budget
Capital Power, along with its joint venture partner ENMAX, also
announced that construction of the 800 megawatt Shepard Energy Centre
is on schedule and below budget. Shepard is a natural gas combined
cycle facility located on the southeast edge of Calgary, Alberta, with
commercial operations targeted for early 2015. The construction project
is expected to be completed below budget with Capital Power's portion
reduced to approximately $821 million from its original $860 million
budget.
"The Shepard Energy Centre represents a significant part of Capital Power's expansion plans in Alberta including a unique opportunity for a contracted investment in the province," added Mr. Vaasjo. "And, with the reduction in capital costs, our long-term returns are expected to exceed our original expectations."
Outlook for 2014
At its Investor Day, the Company will review its corporate priorities
and financial targets for 2014 including:
- Operational targets of 95% capacity-weighted average plant availability, reflecting planned turnarounds at the Genesee 2 and Genesee 3 facilities, plant maintenance capital and other capital expenditures of up to $85 million, and plant operating and maintenance expenses of $165 million to $185 million.
- On-time, on-budget and safe construction of current development projects, including:
- commissioning of the Shepard Energy Centre in early 2015;
- continue with permitting process for Genesee 4 & 5 with approval targeted in the first quarter, 2015; and
- commence construction and completion of project financing for the K2 Wind project.
- 2014 financial target based on an average Alberta spot price of $57 per megawatt hour:
- Funds from operations of $360 to $400 million.
Investor Day event information
Capital Power's Investor Day event is being held today at the St.
Andrew's Club and Conference Centre (150 King Street West, 16th floor). Registration starts at 8:00 a.m. followed by executive
presentations beginning at 8:30 a.m. A live audio webcast of the event
is available on the Company's website at www.capitalpower.com. The presentation slides and webcast will be archived and accessible
for replay.
About Capital Power Corporation
Capital Power (TSX: CPX) is a growth-oriented North American power
producer headquartered in Edmonton, Alberta. The company develops,
acquires, operates and optimizes power generation from a variety of
energy sources. Capital Power owns more than 2,600 megawatts of power
generation capacity at 14 facilities across North America and owns 371
megawatts of capacity through a power purchase agreement. An additional
490 megawatts of owned generation capacity is under construction or in
advanced development in Alberta and Ontario.
Non-GAAP Financial Measures
The Company uses (i) Adjusted EBITDA, (ii) funds from operations, and
(iii) discretionary cash flow as financial performance measures. These
terms are not defined financial measures according to generally
accepted accounting principles (GAAP) and do not have standardized
meaning prescribed by GAAP and are therefore, unlikely to be comparable
to similar measures used by other enterprises. These measures should
not be considered alternatives to net income, net income attributable
to Shareholders of the Company, net cash flows from operating
activities or other measures of financial performance calculated in
accordance with GAAP. Rather, these measures are provided to complement
GAAP measures in the analysis of the Company's results of operations
from management's perspective.
Forward-looking Information
Certain information in this news release is forward-looking within the
meaning of Canadian securities laws as it relates to anticipated
financial and operating performance, events or strategies. The
forward-looking information or statements are provided to inform the
Company's shareholders and potential investors about management's
assessment of Capital Power's future plans and operations. This
information may not be appropriate for other purposes. The
forward-looking information in this news release is generally
identified by words such as will, anticipate, believe, plan, intend,
target, and expect or similar words that suggest future outcomes.
Material forward-looking information includes, among other things,
information relating to: (i) expectations regarding the finalization of
agreements with ENMAX in respect of Genesee 4 & 5 and the timing and
provisions thereof; (ii) expectations regarding the timing of, funding
of, permitting of, costs for, capacity of and technology selected for
existing and planned development projects, completed development
projects, and acquisitions; (iii) expectations regarding plant
availability and planned outages; (iv) expectations regarding future
Alberta power prices; (v) expectations regarding Capital Power's
sources of funding and the financing of existing and planned
development projects; and (vi) expectations regarding future plant
maintenance capital and other capital expenditures, operating and
maintenance expenses and funds from operations.
These statements are based on certain assumptions and analyses made by the Company in light of its experience and perception of historical trends, current conditions and expected future developments, and other factors it believes are appropriate. The material factors and assumptions used to develop these forward-looking statements relate to: (i) electricity and other energy prices, (ii) performance, (iii) business prospects and opportunities including expected growth and capital projects, (iv) status and impact of policy, legislation and regulation, and (v) effective tax rates.
Whether actual results, performance or achievements will conform to the Company's expectations and predictions is subject to a number of known and unknown risks and uncertainties which could cause actual results and experience to differ materially from the Company's expectations. Such material risks and uncertainties are: (i) changes in electricity prices in markets in which the Company operates, (ii) changes in commodity prices in markets in which the Company operates and use of derivatives, (iii) regulatory and political environments including changes to environmental, financial reporting and tax legislation, (iv) power plant availability and performance including maintenance expenditures, (v) ability to fund current and future capital and working capital needs, (vi) acquisitions and developments including timing and costs of regulatory approvals and construction, (vii) changes in market prices and availability of fuel, and (viii) changes in general economic and competitive conditions. See Risks and Risk Management in the Company's December 31, 2012 annual Management's Discussion and Analysis for further discussion of these and other risks.
SOURCE Capital Power Corporation