CALGARY, Jan. 11 /CNW Telbec/ - Calvalley Petroleum Inc. (TSX: CVI.A)
Calvalley Petroleum Inc. ("Calvalley" or the "Company"), an international, junior oil and gas company based in Calgary, Alberta, is pleased to provide the following update on its operations on Block 9 in the Republic of Yemen.
Drilling & Completion
- Three year contracts were signed for an additional drilling rig and one
service rig. The drilling rig is presently undergoing modifications and
is expected to be mobilized to Block 9 in the latter part of January
subject to a satisfactory final inspection. The service rig is expected
to arrive at Block 9 on January 21st;
- Since the Company's last operational update, Calvalley has continued
drilling development wells in the Hiswah field. Hiswah 18, 19, and 20
have been drilled and the rig is currently drilling Hiswah 21; and
- Hiswah 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, and 18 have all been
completed and equipped with down hole pumps.
Central Processing Facility (CPF)
- Fabrication of a 40,000 barrel of oil storage tank at the Hiswah
facility has been completed; additionally, two 10,000 barrel storage
tanks are 85% complete;
- A group separator, two oil treaters and all associated oil treating
equipment is currently on site; and
- Piping construction is well under way to tie all existing components
in.
Pipeline Construction
- Gathering lines from twelve Hiswah wells have been completed.
Construction is currently underway to connect the remaining Hiswah
wells to the CPF; and
- The Company has advertised in major downstream international magazines
and local newspapers with respect to the solicitation for tenders
relating to pipeline management services for the construction of the
crude oil pipeline. The Company has asked potential bidders to
acknowledge interest in order to commence the prequalification process
with Calvalley.
Production
The level of oil production has recently fluctuated between 5,000 to 8,000
barrels per day. Interruptions to oil production continue due to construction
activities at the Hiswah field.
Marketing
The Block 9 Joint Venture partners (Calvalley (50%), HoodOil Ltd. (25%),
and Reliance Industries Limited (25%) ) sold 120,000 barrels of Marib Light
crude oil during the month of December 2006 and have negotiated a further sale
of 60,000 barrels to be lifted in January. These sales are net of oil
production that is allocated to the Yemen government and its agencies as
royalties, share of profit oil and share of joint venture oil.
THE TORONTO STOCK EXCHANGE HAS NOT REVIEWED AND DOES NOT ACCEPT
RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS RELEASE.
This press release may contain forward-looking statements, including
expectations of future production, cash flow and earnings. These statements
are based on current expectations that involve a number of risks and
uncertainties, which could cause actual results to differ materially from
those anticipated or implied in the forward-looking statements. These risks
include but are not limited to: the risks associated with the oil and gas
industry (e.g. operational risks in development, exploration and production;
delays or changes in plans with respect to exploration or development projects
or capital expenditures; the uncertainties of reserve estimates; the
uncertainty of estimates and projections related to production, costs and
expenses, and health, safety and environmental risks), commodity price, price
and exchange rates fluctuations and uncertainties resulting from potential
delays or changes in plans with respect to exploration or development projects
or capital expenditures. Additional information on these and other factors
that could affect Calvalley's operations or financial results are included in
Calvalley's reports on file with Canadian securities regulatory authorities.
Edmund M. Shimoon, CEO
Calvalley Petroleum Inc.
Tel: (403) 297-0491 Fax: (403) 297-0499
%SEDAR: 00001745E