Breedon Group PLCLSE: BREE

Breedon invests £4m in new Northumberland asphalt plant amid increasing demand

· Issued by Breedon Group PLC

Summary by 6ix

Breedon Group plc, a construction materials provider, has invested £4m in a new asphalt plant at Cragmill Quarry in Belford, Northumberland, in response to growing demand from customers across the region. After initial accreditation, the plant is now fully operational.

Key details

  • The plant brings asphalt production back to Cragmill for the first time in more than a decade, replacing a plant decommissioned by the quarry's former operator. The 12-month works involved demolishing the original plant, reconfiguring the site and building a new facility.
  • The plant is designed to make a full range of asphalt materials, including Breedon Performance Asphalt.
  • Breedon says the plant runs on LPG (liquefied petroleum gas) for a cleaner fuel burn and reduced carbon output. It can also mix Recycled Asphalt Planings recovered from existing roads into new asphalt, and has 120 tonnes of mixed material storage.
  • The plant will serve customers across Northumberland, extending south towards Newcastle and north into the Scottish Borders. It offers collection and delivery and can operate 24/7.

What’s still pending

  • The plant expects to produce 50,000 tonnes of asphalt per year.

6ix wrote this summary from the release below and checked it against the release.

Essential construction materials provider Breedon Group plc has announced a £4m investment in a new asphalt plant in Northumberland, in response to growing demand from customers across the region.

The new plant at Cragmill Quarry in Belford brings asphalt production back to the site for the fi rst time in more than a decade, replacing a previous plant that had been decommissioned by the quarry's former operator.

The works, which took place over a 12-month period, involved demolishing the original plant, reconfi guring the site and constructing a modern new facility.

Following initial accreditation, the plant is now fully operational and expects to produce 50,000 tonnes of asphalt per year. The plant has been designed to manufacture a full suite of asphalt materials, including Breedon Performance Asphalt.The new facility runs on LPG for a cleaner fuel burn and reduced carbon output, as well as being WMA and RAP-enabled, allowing Recycled Asphalt Planings (RAP) recovered from existing roads to be incorporated into new asphalt mixes.

It also has 120 tonnes worth of mixed material storage allowing quicker turnaround of materials for our customers and reduced waiting time at the plant for our haulage.

James Macintosh, Area Director at Breedon, said: "Bringing asphalt production back to Cragmill signifi cantly strengthens our ability to supply customers across Northumberland and the Scottish Borders, giving us greater capacity and fl exibility in this part of the region.

"The location means we can provide a strong service to customers, while also supporting our Surfacing Solutions teams with the materials they need to deliver projects across the region."

"Importantly, the new plant also gives us room to scale. We can increase production as demand grows and continue to broaden the range of materials available from Cragmill over time."

Located close to the Scottish border, the new plant will serve customers acr§oss Northumberland, extending south towards Newcastle and north into the Scottish Borders. With both collection and delivery available, alongside the capability to operate 24/7, the facility will provide greater fl exibility and product availability for customers across the region.

ENDS