Boldt has completed hundreds of projects for General Motors over the years.
This project consisted of the construction of a new 380,000 SF expansion to their Wentzville Assembly Center. The new 33-foot-tall structure adds 186 bays for the assembly of the mid-size Chevrolet Colorado pick-up truck.
In addition to the construction of the building core and shell, the project included 15 roof-mounted air supply houses, weld water, chilled water, domestic water, three cooling towers, compressed air, natural gas and a siphonic roof drain system. Electrical elements include a two-bay penthouse for the building substation equipment, busways for welding and tooling equipment and a Motor Control Center.
Several years after its completion, General Motors engaged Boldt again to expand the facility by another 46,575 SF, adding an additional 23 bays.