Terramin Australia Limited · ASX:TZN
Terramin Australia — Corporate Update (February 2014)
19 slides from Terramin Australia's corporate update, February 2014

Slide 1: Angas Mine – SCCC Presentation
Angas Mine – SCCC Presentation Welcome to all Current Status – Care and Maintenance as of 31st October – Maintaining all onsite infrastructure and equipment – Monitoring ground conditions and water underground – Ongoing environmental monitoring and management PEPR submitted to DMITRE with comm

Slide 2: What's happening at Angas Zinc?
What's happening at Angas Zinc? Environment, Community and Water Management staff remain on-site 5 employees on site and 2 university students gaining environmental experience Clean-up work – recycling Water and environmental management /monitoring continuing Water, Dust and Environmental

Slide 3: Mining and Underground Management (Quarter 4, 2013)
Mining and Underground Management (Quarter 4, 2013) 24,540m3 waste rock placed underground in October A total 18,445m3 of water placed underground during the quarter – storm water runoff and bore water injection Water reached the 190m RL in the decline - late January Quarterly ground control

Slide 4: Quarterly Environment Report
Angas Zinc Mine Quarterly Environment Report Quarter 4: Oct - Dec 2013 M. Daniel TERRAMIN AUSTRALIA LIMITED

Slide 5: Environmental Activities
Environmental Activities Fencing works complete to exclude hares from SEB areas Weed survey and control Supplementary watering of native seedlings Dust management Waste management – recycling campaign Monitoring water levels in mine decline TERRAMIN AUSTRALIA LIMITED

Slide 6: Underground Mine Void
Underground Mine Void 93% of voids filled with stockpiled waste rock from previous mining activities February 4th water samples from the void were taken at the 190m RL where water had risen to; from natural upwelling and pumping into void 30,151m3 of water has been sent to underground (between

Slide 7: Community Activities
Community Activities Student placements for environmental work experience Curtin University, WA University of Adelaide TERRAMIN AUSTRALIA LIMITED

Slide 8: Community Feedback & Environmental Incidents
Community Feedback & Environmental Incidents No environmental incidents were recorded during quarter 4 No registered community complaints during quarter 4 Direct seeded plants survived the hot weather TERRAMIN AUSTRALIA LIMITED

Slide 9: Noise November Monitoring - West results (Boxcut side)
dB 30 35 40 45 50 55 60 65 70 75 80 11/7/2013 17:16 11/7/2013 22:16 11/8/2013 3:16 11/8/2013 8:16 11/8/2013 13:16 11/8/2013 18:16 11/8/2013 23:16 11/9/2013 4:16 Onsite Noise Limit 11/9/2013 9:16 11/9/2013 14:16 TERRAMIN AUSTRALIA LIMITED 11/9/2013 19:16 11/10/2013 0:16 11/10/2013 5:16 LAeq 11/10/201

Slide 10: Noise November Monitoring - East results (Mill side)
dB 30 35 40 45 50 55 60 70 75 65 11/7/2013 16:56 11/7/2013 21:56 11/8/2013 2:56 11/8/2013 7:56 11/8/2013 12:56 11/8/2013 17:56 Onsite Noise Limit 11/8/2013 22:56 11/9/2013 3:56 11/9/2013 8:56 11/9/2013 13:56 LAeq 11/9/2013 18:56 TERRAMIN AUSTRALIA LIMITED 11/9/2013 23:56 11/10/2013 4:56 11/10/2013 9

Slide 11: TSF Decant Pond - Surface Area
TSF Decant Pond - Surface Area The TSF Decant pond remains in compliance (<15,000m2) Surface area 1,573m2 at RL 66.24 at the end of January 7thTERRAMIN March 2013 TSF Western AUSTRALIA LIMITED Wall 19th February 2014 TSF Western Wall

Slide 12: Rainfall (mm) TSF Decant Pond RL
Rainfall (mm) 10.0 20.0 30.0 40.0 50.0 60.0 3/02/2010 3/03/2010 3/04/2010 3/05/2010 3/06/2010 3/07/2010 3/08/2010 2010 3/09/2010 3/10/2010 3/11/2010 3/12/2010 3/01/2011 3/02/2011 rain (mm) 3/03/2011 3/04/2011 TERRAMIN AUSTRALIA LIMITED RL – 66.24m on 6th February 3/05/2011 3/06/2011 3/07/2011 2011 3

Slide 13: TSF Water Quality
TSF Water Quality pH change with recent rainfall 6.36pH before rainfall – 13/02/14 4.59pH after rainfall – 14/02/14 Cause for pH change: – Runoff from oxidised tails Surface Tails surface pH – today – Ranged from 6.2 – 8.1pH TERRAMIN AUSTRALIA LIMITED

Slide 14: Upcoming Activities for Q1 2014
Upcoming Activities for Q1 2014 TSF audit, MARCR completion Scrap metal collection – PEPR updating Cape Divine Recycling of scrap steel and plastic Ongoing TSF monitoring and water management Ongoing weed and pest management Native ‘mud matting’ General site dust, water and erosion veget

Slide 15: TSF Capping Options
TSF Capping Options Mine Closure Conference in Brisbane, presentations and follow up discussions with leading experts – including M. O’Kane, highlights many potentially superior alternatives to HDPE covers Engineered, designed soil cover is often considered superior, particularly in the long ter

Slide 16: Phytocap
Phytocap Test work completed: Fate and Transport Modelling HELP Modelling Vadose Modelling Atterberg Limit testing Geotechnical testing Emerson dispersion Compaction testing Permeability testing Source: adapted from http://www.phytolink.com.au/technology.htm, viewed 18/02/2014 TERR

Slide 17: Current position/actions
Current position/actions Currently: • Revising Mine Care and Closure Plan with TERRAMIN AUSTRALIA LIMITED comments and recommendations from DMITRE • Continuing work on Closure Plan

Slide 18: Final Closure plan / Final PEPR
Final Closure plan Final PEPR TERRAMIN AUSTRALIA LIMITED

Slide 19: Thank you
Thank you TERRAMIN AUSTRALIA LIMITED
Source: Internet Archive copy of terramin.com.au
More decks from Terramin Australia Limited
Shareholder Meeting (May 2026)15 slides · May 2026
Shareholder Meeting (May 2025)12 slides · May 2025
Shareholder Meeting (May 2022)12 slides · May 26, 2022
Investor Presentation (October 2019)23 slides · Oct 31, 2019
Investor Presentation (October 2019)22 slides · Oct 30, 2019
Technical Presentation (June 2019)20 slides · June 2019