Nevada Copper — Investor Presentation (October 2011)
46 slides from Nevada Copper's investor presentation, Oct 14, 2011

Slide 1: Nevada Copper Corp.
Nevada Copper Corp. Nevada Copper Corp. TSX: NCU October 14, 2011 PUMPKIN HOLLOW COPPER PROJECT

Slide 2: Cautionary Note
Cautionary Note Certain statements contained in this presentation constitute forward-looking statements. Such forward-looking statements involve a number of known and unknown risks, uncertainties and other factors which may cause the actual results, performance of achievements of the Corporation to

Slide 3: Capital Structure
Capital Structure Stock Symbol: TSX: NCU Added to S&P/TSX Small Cap Index on September 16, 2011. Shares Outstanding: 72.8 Million 12% Held by Directors & Officers. Approximately 67% Held by Institutions. Fully Diluted: 79.6 Million 6.3 million stock options @ $3.35; 464,000 warrants @ $5.05

Slide 4: Investment Highlights
Investment Highlights 100% Owned Pumpkin Hollow Copper. NI 43-101 Compliant Resource (0.20% Copper Cutoff): M&I Resources > 5.9 Billion pounds of Copper Inferred Resources > 3.7 Billion pounds of Copper PLUS Gold, Silver and Iron. Resource Upside – Current Drilling Continues to Expand Deposit

Slide 5: Nevada Copper Team
Nevada Copper Team Giulio T. Bonifacio President & CEO Robert McKnight Executive Vice President Gregory French Vice President, Senior Project Manager Timothy M. Dyhr Vice President, Environment & External Relations Timothy Dake General Manager, Project Construction Joe Chan Vice President, CFO Hank

Slide 6: Location Map
Location Map 6 PUMPKIN HOLLOW COPPER PROJECT

Slide 7: Land Position
Land Position Yerington Pumpkin Hollow Mining Claims & Private Lands 22 square miles Pumpkin Hollow Project Office Pumpkin Hollow Private Lands 7 PUMPKIN HOLLOW COPPER PROJECT

Slide 8: District Summary
District Summary 1.9 Billion pounds of copper produced at 0.54% Cu grade; Anaconda Copper Mine - 1953 to 1978. 13 Billion pounds of copper found in other porphyry deposits in the district. At Pumpkin Hollow: 5.9 Billion pounds of copper in M&I and 3.7 Billion pounds of copper in Inferred; high grade

Slide 9: Western/Eastern Deposits
Western/Eastern Deposits Outline of Patented Claims (Note: Property extends off the map in all directions) EAST ZONE NORTH ZONE High Grade Underground Copper Deposits JK-34 ZONE Copper - Iron Open Pit Deposits SOUTH ZONE E-2 ZONE SOUTHEAST ZONE 0ft 2,000ft 3,000ft 9 PUMPKIN HOLLOW COPPER PROJECT

Slide 10: Total Resource
Total Resource NI 43-101 Compliant Estimate (As at March 2011) MEASURED RESOURCES Cutoff Avg. Contained Avg. Avg. Grade Tons Grade Lbs Cu Grade Au_oz Grade Ag_oz Category (%Cu) (000) (%Cu) (000) Au opt (000) Ag opt (000) Measured 0.20 155,898 0.59 1,853,025 0.003 520 0.076 11,823 Measured 0.30 107,6

Slide 11: 2011 Iron Resource
2011 Iron Resource NI 43-101 Compliant Estimate (As at March 2011) IRON RESOURCES WESTERN DEPOSITS Iron Iron % Tons Tons Iron Category Grade Cutoff (000s) (000s) % Measured 20 205,836 34.6 71,162 Measured 30 123,627 41.1 50,857 Indicated 20 135,062 29.6 39,926 Indicated 30 53,740 37.9 20,356 M&I Tot

Slide 12: Step Out/ Open Targets
Step Out/ Open Targets 56,000 N East Ground Mag North Deposit East Deposit Open Mineral East Ext. Targets & NE Ext. Anomalies 1,500 FEET SE Ext. 52,000 N BC / East Area 1 ½ Mi. East South Deposit Ext. (East 1 Mi) E-2 Deposit 48,000 N Southeast 54,000 E 50,000 E 58,000 E Deposit 12 PUMPKIN HOLLOW COP

Slide 13: Open Target Areas
Open Target Areas NC11-17 (155 ft. @ 0.59% Cu) Open Target Areas NC11-23 (126 ft. @ 0.30% Cu) NC11-16 (779 ft. @ 0.53% Cu) Pit Data from 2008 Preliminary Economic Assessment 13 PUMPKIN HOLLOW COPPER PROJECT

Slide 14: Eastern - Underground
Eastern - Underground NI 43-101 Compliant Estimate (As at March 2011) MEASURED AND INDICATED RESOURCES Cutoff Avg Contained Avg Avg Grade Tons Grade Lbs Cu Grade Au_oz Grade Ag_oz Category (%Cu) (000) (%Cu) (000) Au opt (000) Ag opt (000) Measured 1.00 9,206 1.81 333,324 0.011 104 0.240 2,205 Measur

Slide 15: Western - Open Pittable
Western - Open Pittable NI 43-101 Compliant Estimate (As at March 2011) MEASURED AND INDICATED RESOURCES Cutoff Avg Contained Avg Avg Grade Tons Grade Lbs Cu Grade Au_oz Grade Ag_oz Category (%Cu) (000) (%Cu) (000) Au opt (000) Ag opt (000) Measured 0.30 88,997 0.64 1,144,204 0.003 230 0.071 6,356 M

Slide 16: Ideal Development Site
Ideal Development Site Yerington Nevada – Mining Friendly Full Services Resource on Private Land No Neighbors to N,S & E Power Water Supply Available Paved Access 16 PUMPKIN HOLLOW COPPER PROJECT

Slide 17: PEA Profile – March 2008
PEA Profile – March’ 08 Integrated open pit and underground operation. Throughput, 60,000 tpd, 90% open pit, 10% underground. Single copper concentrator. Producing 85,000 to 125,000 tons copper per year. Gold, silver and iron by- products. Mine life 24 years. 17 PUMPKIN HOLLOW COPPER PRO

Slide 18: PEA (March 2008 - Integrated)
PEA (March 2008 - Integrated) Highlights of PEA(NI 43-101 Compliant) - See Cautionary Note (In Millions of US Dollars and Imperial Units) Base Case Alternative Case (3) Copper Price ($/lb) $2.50 $3.00 $2.50 $3.00 Annual Copper Production 200-250 million pounds 225-275 million pounds Copper Equivalen

Slide 19: PEA Summary Information
PEA Summary Information Open Pit Underground • 52,500 tons per day • 7,500 tons per day • Truck and Shovel Mining • Bulk Long-hole Mining • Avg. 2.9:1 w/o Ratio • Shaft Access • 320 ton Class Equipment • 8.5 - 6 yard Class Equipment • 432,000,000 tons Ore • 28,000,000 tons Ore • Cu equiv. grade 0.62

Slide 20: Proposed Site Layout
Proposed Site Layout 20 PUMPKIN HOLLOW COPPER PROJECT

Slide 21: 2011 Results/Activities
2011 Results/Activities Delineation Drilling - 50,000 meters – Updated Resource - Complete Detailed Hydrogeology, Geochemistry & Geotechnical - Complete Expansion/Step Out Drilling Program – Increased from 20,000 to 50,000 meters. Advanced Exploration Permits for Underground Access Lyon Coun

Slide 22: Land Transfer
Land Transfer City Of Yerington, Lyon County And Nevada Copper Propose To Transfer BLM-administered Federal Lands To City Of Yerington. Transfer Will Expedite Mine And General Economic Development, And Provide Lands For Open Space Buffers And Recreational Purposes. Lyon County Formally Support

Slide 23: Land Transfer
Land Transfer City of Yerington and Nevada Copper Propose to Transfer BLM-administered Federal Lands to City. Implement Via Congressional Action. Lyon County Formally Supports Transfer and Annexation to the City. Consistent With BLM Policy To Transfer Lands To Local Rural Communities For Eco

Slide 24: Land Transfer - Development Area
Land Transfer - Development Area Proposed Total Land Transfer - 11,630 Acres. 1,560 acres of Private Patented Lands – Current. 3,800 acres of Land Transfer for Pumpkin Hollow Mine Development for total of 5,360 acres(1,560+ 3,800 = 5,360) creating contiguous block subject only to State and loc

Slide 25: Preliminary Timeline
Preliminary Timeline 2010 2011 2012 2013 2014 2015 1st 2nd 3rd 4th DESCRIPTION Qtr Qtr Qtr Qtr Infill and Step out Expansion Drilling Preliminary Studies (PEA, Follow-up Test Work, Hydrology Studies) Definitive Feasibility Study Advanced Exploration Construction & Underground Development Private Lan

Slide 26: Peer Group Comparables
Peer Group Comparables Market Value per pound of Copper in situ ($Cu Eq. cents per lb) Copper Mountain 20.8 20.8 Norsemont * 9.7 20.00 9.7 Augusta 4.9 4.9 4.6 Antares * 4.6 1.7 10.0 0.00 Copper Norsemont Augusta Antares Nevada Mountain Copper Nevada Copper 1.7 * Acquired Group Average: 10 cents per

Slide 27: Appendix
Appendix Additional Information, Photos & Cross Sections 27 PUMPKIN HOLLOW COPPER PROJECT

Slide 28: Nevada Copper Team
Nevada Copper Team Giulio T. Bonifacio - Over 26 years in senior executive positions in the mining industry. Founder, President & CEO of Nevada Copper with a successful track record of raising equity and project capital for projects of merit. Professional accountant with extensive experience and kno

Slide 29: Nevada Copper Team
Nevada Copper Team Timothy Dake - General Manager, Project Construction - Mr. Dake has over 30 years of experience in the mining and construction industries. He has worked in diverse capacities in mining and mineral processing in Indonesia, Chile, Russia and Brazil as well as Montana, Arizona, Alask

Slide 30: Directors
Directors Giulio T. Bonifacio – See Previous Brian Kirwin - Accomplished mining executive in leadership positions with over 25 years experience evaluating deposits, mines and risk worldwide. Formerly with Placer Dome and Vengold Inc in senior roles. Holds a Master of Science degree in Geology. Paul

Slide 31: Core Processing Facility
Core Processing Facility 31 PUMPKIN HOLLOW COPPER PROJECT

Slide 32: Premier Development Site
Premier Development Site Project Site 32 PUMPKIN HOLLOW COPPER PROJECT

Slide 33: Western - North Deposit View
Western - North Deposit View North Deposit Office Looking North 33 PUMPKIN HOLLOW COPPER PROJECT

Slide 34: Eastern & Western (South)
Eastern & Western (South) East Deposit E-2 Deposit South Deposit Looking East 34 PUMPKIN HOLLOW COPPER PROJECT

Slide 35: East Deposit Section
East Deposit Section Secction 54700N East Deposit EAST E2 SECTION 49600N 35 PUMPKIN HOLLOW COPPER PROJECT

Slide 36: East Deposit – 54700N
East Deposit – 54700N East Deposit NC10-11 33.5 feet @ 2.76% Cu 27.8 feet @ 2.71% Cu 35.2 feet @ 2.21% Cu 102' 97.5' 2.56% Cu NC07-21 114' 4.18% Cu 33.5' 102 feet @ 2.56% 3.20% Cu 2.76% Cu 56 feet @ 4.34% Conglomerate Tertiary Volcanics 54' 27.8' NC10-05 Limestone/Marble 3.38% Cu 2.71% Cu 54.0 feet

Slide 37: East Deposit - Hole NC07-21
East Deposit - Hole NC07-21 1708’-1713’ @ 6.40% Cu; 0.014 opt Au, 0.56 opt Ag 37 PUMPKIN HOLLOW COPPER PROJECT

Slide 38: E-2 Deposit - Section 16NE – GT01
E-2 Deposit - Section 16NE – GT01 38 PUMPKIN HOLLOW COPPER PROJECT

Slide 39: North Deposit Sections
North Deposit Sections Surface 0.2% Copper Shell Section 47600E Section 49000E Section 47700E 39 PUMPKIN HOLLOW COPPER PROJECT

Slide 40: North Section - 48100 E - GT09
North Section - 48100 E - GT09 N92-5 GT10-09 North NC10-21 USS-32 GT10-10 NC10-20 USS-84 4500' 60' 0.48% Cu 315' 0.80% Cu 4000' 33.5' 1.00% Cu 1190.6' USS-67 0.49% Cu 418' 0.57% Cu 437' Conglomerate 0.57% Cu Tertiary volcanics Open 3500' 426' Limestone, marble 0.60% Cu 170' 0.52% Cu Mesozoic Hornfel

Slide 41: North Deposit - 47800E
North Deposit - 47800E NC10-62 NC10-38 USS-39 North USS-95 USS-72 4500’ 182' 0.59% Cu 235' 1.16% Cu 4000’ 25.5' 622' 1.03% Cu 0.73% Cu 68.5' 751.5' Conglomerate 0.52% Cu 0.59% Cu Tertiary Volcanics 3500’ Limestone/Marble 90.5' Mesozoic Hornfels 1.37% Cu Magnetite Skarn 520' 0.67% Cu Calc-silicate Sk

Slide 42: North Deposit - 47600 E
North Deposit - 47600 E North Deposit 144' 79' 1.43% Cu 0.37% Cu 130.5' NC10 – 31 0.83% Cu 98' 130.5 feet @ 0.83% Cu 23' 0.82% Cu 1.43% Cu 25.0 feet @ 0.85% Cu 25' 275.5 feet @ 0.98% Cu 0.85% Cu 155.0 feet @ 0.82% Cu 194' 126' 4.15% Cu 1.73% Cu 88' 0.45% Cu Conglomerate Tertiary Volcanics 248' 275'

Slide 43: North Deposit - 47700E
North Deposit - 47700E 54500N 54000N 53500N 53000N 52500N North 4800’ NC07-9 99-4 USS-70 USS-46 24.9’ 99-2 USS-76 3.38% Cu Tertiary volcanics 12.5’ 4000’ USS-95 2.53% Cu Limestone, Marble Mesozoic Hornfels Magnetite skarn 99-3 42’ Cal-silicate skarn 2.49% Cu Intrusive + 1% Cu 109.9’ USS-41 + 2% Cu 3

Slide 44: North Deposit - 49000E
North Deposit - 49000E USS-53 NC08-08 USS-92 NC08-46 NC08-20 NC08-40 North 773’ 212’ 1.03%Cu 0.64%Cu 15’ 0.81% Cu 272’ 0.58%Cu 739’ 0.62% Cu 44 PUMPKIN HOLLOW COPPER PROJECT

Slide 45: North Deposit - Hole NC08-20
North Deposit - Hole NC08-20 NORTH NC08-20 1203-1211.5 0ft 2000ft 45 PUMPKIN HOLLOW COPPER PROJECT

Slide 46: North Section 48200 E
North Section 48200 E NC11-14 USS-30 USS-67 NC08-22 North USS-88 4500 323' 1.82% Cu USS-69 USS-89 79' 0.95% Cu 437' 4000 0.57% Cu 30' USS-56 1.12% Cu 467' 1.05% Cu 270' 1.12% Cu GT10-09 Open USS-79 98' 105' 3500 Conglomerate 1.12% Cu 190' 0.33% Cu 0.49% Cu Tertiary volcanics 259' 0.69% Cu Limestone,
Source: Internet Archive copy of nevadacopper.com
More decks from Nevada Copper Corp.
Investor Presentation (January 2023)22 slides · January 2023
Investor Presentation (February 2022)25 slides · February 2022
Investor Presentation (October 2021)26 slides · October 2021
Investor Presentation (December 2019)27 slides · December 2019
Investor Presentation (June 2018)32 slides · Jun 13, 2018