Nevada Copper — Investor Presentation (January 2023)
22 slides from Nevada Copper's investor presentation, January 2023

Slide 1: Developing a New U.S. Copper District in Nevada
DEVELOPING A NEW U.S. COPPER DISTRICT IN NEVADA JANUARY 2023

Slide 2: Cautionary Language
Cautionary Language This presentation contains “forward-looking information” and “forward-looking statements”, within the meaning of applicable Canadian securities laws concerning Nevada Copper Corp. (the “Company”) and its plans for its properties and other matters. All statements in this presentat

Slide 3: The Nevada Copper Story
The Nevada Copper Story Nevada Copper (“NCU”) owns two copper assets on a single property, Pumpkin Hollow, in the USA - an underground mine that is restarting operations and a fully-permitted, large-scale open pit project Underground Restart: Restart plan in place and underway for underground operat

Slide 4: Objectives for Next Months
Objectives for Next 12 Months • Primary focus is to complete critical development and capital projects ahead of stope Implementing mining Underground Restart Plan • Begin stope mining in H2/23; ramp up from 3,000 tpd in Q3/23 to ~5,000 tpd processed by end of 2023 Progress Open Pit • Large resource,

Slide 5: 2022/23 Underground Restart Plan
2022/23 Underground Restart Plan • The restart plan for underground operations has been carefully designed to derisk the restart and ramp-up of operations by focusing on development projects ahead of stope mining and mill restart • Three distinct phases to ensure smooth transition: Phase I – Sep 202

Slide 6: Restart Financing Package
Restart Financing Package • As disclosed in the October 28, 2022 and December 29, 2022 news releases, NCU closed a restart financing package with its key financing partners for up to US$123 million of liquidity. • A high-level summary of the components of the Restart Financing Package are as follows

Slide 7: Long-Term Strategy
Long-Term Strategy Build a new copper district through staged expansion options TSX:NCU | nevadacopper.com 1. Expand 2. Construct 3. Optimize 4. Regional and Underground Mine1 Open Pit Mine1 Open Pit Mine District Targets 1. UG PFS and OP PFS Source: “NI 43-101 Technical Report: Nevada Copper Corp.

Slide 8: Corporate Snapshot
Corporate Snapshot Capital Structure Supportive key financing partners. Ticker TSX:NCU Increased investment to fund ramp up. Share Price (12/30/2022) C$ 0.29 • Pala (45.1% of outstanding common shares) Market Capitalization C$ 191M • Mercuria (25.6% of outstanding common shares) Cash & Cash Equivale

Slide 9: Copper Market: Scarcity of ready-projects in favorable jurisdictions
Copper Market: Scarcity of ready-projects in favorable jurisdictions Significant demand for copper to build a cleaner world Copper supply is risky, and is getting riskier1 • Increasing demand for copper without ethical, environmental externalities • Focus on shortening of supply chains to reduce cos

Slide 10: Producing Green Copper
Producing Green Copper An essential metal for the energy transition Sustainable Strategy • Strategy aligns with UN Sustainable Development Goals for: 7) Affordable and clean energy 8) Decent work and economic growth 11) Sustainable cities and communities 12) Responsible consumption and production •

Slide 11: Senior Management Team
Senior Management Team Management team highly experienced in mine construction, start-up and business optimization in both majors and juniors Randy has extensive experience in underground and open pit mining operations, both in Nevada and internationally. President & Chief Most recently at Hycroft M

Slide 12: Appendices
Appendices 11

Slide 13: Operations and Strategic Position
Operations and Strategic Position Exceptional Production Growth Profile • Underground mine is operationally ready and preparing for restart • Open Pit mine permitted, with multiple potential expansion phases • Current reserves of 4.4Bn lbs Cu eq1,2 • Large 24,000-acre land holding in rare US copper

Slide 14: Organic Growth – Underground Expansion Options
Organic Growth – Underground Expansion Options Significant inferred resource upside and latent installed capacity creates attractive options expansion Excess Installed Capacity Additional 636 million lbs of inferred resource outside of UG mine plan • Major infrastructure was constructed with excess

Slide 15: Organic Growth – Open Pit Project
Organic Growth – Open Pit Project >5 billion pounds of copper resource1 Fully permitted: only permitted copper project in North America Exceptional ESG metrics (dry tailings, water management, solar option) High copper grades: 0.69% Cu eq first 5yrs1 Expandable scale: start-up at 37Ktpd, option to a

Slide 16: Organic Growth – Open Pit Optimization
Organic Growth – Open Pit Optimization Open Pit Resource Extension Open Pit reserve was previously constrained by historic land • Project upside potential from infill drilling in / on the boundary… edge of the pit • Historic land boundary limited drilling of open pit reserve, in particular Northern

Slide 17: Organic Growth – Defined Near-Mine Exploration Targets
Organic Growth – Defined Near-Mine Exploration Targets Exceptional exploration near-mine pipeline potentially offers long operational life and substantial production growth Near Mine Exploration Potential • Historic exploration was limited to Underground and Open Pit given past license limitations •

Slide 18: Organic Growth – Porphyry Target
Organic Growth – Porphyry Target Large porphyry target identified on Eastern side of property • Classic porphyry setting: Alluvial covered basin to east of exposed copper mineralization, where recent geophysical survey shows a magnetic low • Exposed mineralization: Higher levels of a copper porphyry

Slide 19: Strategic Advantage in Re-Emerging Cu District
Strategic Advantage in Re-Emerging Cu District • Significant defined copper resources in district across multiple deposits • Nevada Copper holds permits and key infrastructure within the district • Nevada Copper’s processing capability and infrastructure is key to creating a regional copper hub, unl

Slide 20: Board of Directors
Board of Directors Board of directors with exceptional depth of industry experience Stephen is a Managing Partner at Pala Investments Ltd. He has overseen many of Pala’s principal investments in the mining sector and Stephen Gill Chairman specializes in assisting companies to define and implement st

Slide 21: Resources and Reserves
Resources and Reserves1 TSX:NCU | nevadacopper.com 1. The Mineral Resources reported are inclusive of those reported in Mineral Reserves. Readers are cautioned that Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. 20

Slide 22: Developing a New U.S. Copper District
DEVELOPING A NEW U.S. COPPER DISTRICT OPERATIONS OFFICE 61 E. Pursel Lane Yerington, NV USA 89447 Phone: (775) 463-3510 Fax: (775) 463-4130 INVESTOR RELATIONS Tracey Thom – VP IR Email: tthom@nevadacopper.com Phone: (775) 391-9029
Source: Internet Archive copy of nevadacopper.com
More decks from Nevada Copper Corp.
Investor Presentation (February 2022)25 slides · February 2022
Investor Presentation (October 2021)26 slides · October 2021
Investor Presentation (December 2019)27 slides · December 2019
Investor Presentation (June 2018)32 slides · Jun 13, 2018
Investor Presentation (October 2011)46 slides · Oct 14, 2011