Nevada Copper Corp.

Nevada Copper — Investor Presentation (June 2018)

32 slides from Nevada Copper's investor presentation, Jun 13, 2018

  1. Slide 1: Corporate Presentation

    Slide 1: Corporate Presentation

    Corporate Presentation June 13, 2018 TSX:NCU nevadacopper.com

  2. Slide 2: Cautionary Note

    Slide 2: Cautionary Note

    Cautionary Note Forward-Looking Information Certain statements contained in this presentation constitute forward-looking statements. All statements in this presentation, other than statements of historical facts, including analysis of potential future mining operations, the likelihood of commercial

  3. Slide 3: The Right Project at the Right Time

    Slide 3: The Right Project at the Right Time

    The Right Project at the Right Time Fully-permitted, shovel-ready copper project Containing >5B lbs of copper Targeting initial production in 2019 In a world-class jurisdiction Run by a tier one team of mine builders Supported by strong copper fundamentals 3

  4. Slide 4: Nevada Copper Corporate Strategy

    Slide 4: Nevada Copper Corporate Strategy

    Nevada Copper Corporate Strategy Become Next North • Immediate focus on completion of underground construction American Copper • Leverage sunk $220M capital to reduce cost and timeline Producer • Target production in 2019 • Apply “margin-over-tons” philosophy Realize Full Potential • Re-engineer ope

  5. Slide 5: Strong Copper Market Fundamentals

    Slide 5: Strong Copper Market Fundamentals

    Strong Copper Market Fundamentals Risked Production Base Strong Demand  2017 saw first decline in copper output in 15 years  Synchronized global economic growth  958kt (5% of supply) production lost to disruptions in  New sources of demand from electric vehicles 2017, and multiple risk events up

  6. Slide 6: Capex Requirements (Next 10 Years)

    Slide 6: Capex Requirements (Next 10 Years)

    Project pipelines are sparse, incentive pricing required Copper supply built during the last cycle has been worked through, with few new projects ready to fill the gap1… Existing Projects New Projects 90 10,000 80 9,000 3-Month Rolling fwd Copper Price 70 8,000 Copper Resource Size (Mt Contained Cu)

  7. Slide 7: The Next North American Copper Producer

    Slide 7: The Next North American Copper Producer

    The Next North American Copper Producer 7

  8. Slide 8: Copperwood: Only Fully-Permitted, Shovel-Ready Copper Project in the U.S.

    Slide 8: Copperwood: Only Fully-Permitted, Shovel-Ready Copper Project in the U.S.

    Only Fully-Permitted, Shovel-Ready Copper Project in the U.S. Development Project Status(1) Permitted Feasibility Pre-Feasibility Preliminary Economic Assessment World-class, long-life copper deposit in a Tier 1 jurisdiction North Met Twin Metals Copperwood Florence Pebble Van Dyke Rosemont Black Bu

  9. Slide 9: The Right Team for the Right Project

    Slide 9: The Right Team for the Right Project

    The Right Team for the Right Project Board of Directors Management Team Stephen Gill, Non-Executive Chairman Matthew Gili, P. Eng. President and CEO  Managing Partner at Pala Investments Ltd. and former Director on various  Comes directly from Barrick, where he served as Executive General Manager

  10. Slide 10: Scale and Infrastructure on Secured Land Package

    Slide 10: Scale and Infrastructure on Secured Land Package

    Scale and Infrastructure on Secured Land Package 2 Mines 5B lbs contained Copper 300M lb annual production 23 year mine life City of Yerington Water Private Land Owned By Nevada Copper Power Paved Road Access U/G Open Pit Private Land Owned By Nevada Copper Unpatented BLM Claims Unpatented BLM Claim

  11. Slide 11: Advanced Underground Development

    Slide 11: Advanced Underground Development

    Advanced Underground Development 11

  12. Slide 12: De-risked Development and Accelerated Lead Time

    Slide 12: De-risked Development and Accelerated Lead Time

    De-risked Development and Accelerated Lead Time Combination of existing shaft, EPC build and mining contract de-risks project and shortens lead time (1)  Significant Invested Capital: US$220 million invested to date reduces upfront capital requirement  Key Construction Milestones Completed: Concre

  13. Slide 13: Economically Robust Underground Development Plan in Place

    Slide 13: Economically Robust Underground Development Plan in Place

    Economically Robust Underground Development Plan in Place (1) Underground Mine Highlights Project Robust economics Economics NPV5%/IRR: $301m / 25% (Unlevered)(2) Low upfront capex Capex Pre-production capex: US$182 million First 5 Years LOM (2) Competitive opex Opex C1: US$1.68/lb Cu AISC: US$1.86/

  14. Slide 14: Significant Underground Resource Upside

    Slide 14: Significant Underground Resource Upside

    Significant Underground Resource Upside - Large quantity of inferred mineralization presents significant opportunity to upgrade with underground drilling 14

  15. Slide 15: Large-Scale Open Pit with Substantial Upside Potential

    Slide 15: Large-Scale Open Pit with Substantial Upside Potential

    Large-Scale Open Pit with Substantial Upside Potential 15

  16. Slide 16: Open Pit Optimization Plan

    Slide 16: Open Pit Optimization Plan

    Open Pit Optimization Plan Optimization of Existing Plan Untested Private Land Acquired by NCU from Federal Internal studies indicate ability to significantly Extensions Gov’t (formerly BLM unpatented claims) North Pit improve project economics: Extensions 1. North Pit grade 40% higher than South Pi

  17. Slide 17: Open Pit 2018 Drilling

    Slide 17: Open Pit 2018 Drilling

    Open Pit 2018 Drilling North Pit NC18-10 % NC48-09 ew” NCIB-12 ncig0a NC18-17 NC1B-14 NeieYe june 2018 South Pit NEVADA COPPER Drilled @ Assays Complete

  18. Slide 18: Open Pit – Northern Extension Zone

    Slide 18: Open Pit – Northern Extension Zone

    Open Pit – Northern Extension Zone Northern Extension NC18-01 NC18-02 Increased grade 140’ @ 2.05% demonstrated via drilling completed post open pit FS Not Tested in view of Land Transfer that was pending South Metallurgical Drilling Expand and S-6 convert Hole projected, resources into not in secti

  19. Slide 19: Open Pit – Connector Zone

    Slide 19: Open Pit – Connector Zone

    Open Pit – Connector Zone Northern Extension Currently Waste or Inferred Not Tested in order not to complicate Land Transfer 19

  20. Slide 20: Project Exploration & Regional Potential

    Slide 20: Project Exploration & Regional Potential

    Project Exploration & Regional Potential 20

  21. Slide 21: Strong project growth and regional potential

    Slide 21: Strong project growth and regional potential

    Strong project growth and regional potential Pumpkin Hollow property and Yerington district are underexplored McArthur Bear District Cu Inventory > 33 Bn Lbs Blue Hills Ann Mason Yerington Mason Area North Mines Pumpkin E2 Nevada Copper Hollow Quaterra Mason Resources Corp. (Formerly Entree Gold) Ma

  22. Slide 22: Financing Package in Place with Flexible Balance Sheet

    Slide 22: Financing Package in Place with Flexible Balance Sheet

    Financing Package in Place with Flexible Balance Sheet 22

  23. Slide 23: Strong Balance Sheet to Support Project Development

    Slide 23: Strong Balance Sheet to Support Project Development

    Strong Balance Sheet to Support Project Development Robust and flexible balance Construction financing package Balance Sheet upside sheet  US$70 million precious metals  Pursing discussions with low-cost  US$80 million project stream project lenders financing facility in place:  US$25 million ma

  24. Slide 24: Highly Levered to Rising Copper Prices

    Slide 24: Highly Levered to Rising Copper Prices

    Highly Levered to Rising Copper Prices 10% increase in Cu price = 60% increase in after-tax NPV(1) Project NPV Sensitivity(1) $4,000 $3,459 Net Present Value 5% (US$M) $3,500 $3,000 $2,628 $2,500 $2,000 $1,781 $2,694 $1,500 $2,028 $882 $1,356 $1,000 $500 $631 $600 $765 $251 $425 $0 NPV NPV NPV NPV $

  25. Slide 25: Defined Path to Production with Multiple Near-Term Catalysts

    Slide 25: Defined Path to Production with Multiple Near-Term Catalysts

    Defined Path to Production with Multiple Near-Term Catalysts Strategy to drive near-term re-rate potential and unlock long-term value Optimization Release PFS on Complete Project Pit Drilling Underground Financing Announce Optimization Builder’s Pit Conceptual Resource Optimization Execute on Region

  26. Slide 26: Appendices

    Slide 26: Appendices

    NORTH AMERICA’S NEXT COPPER PRODUCER Appendices re a Ze:

  27. Slide 27: Company Snapshot

    Slide 27: Company Snapshot

    Company Snapshot Capitalization Items1 Share Price Performance 3 Symbol TSX: NCU 1.00 Nevada Copper Share Price (C$) 4.00 Share Price (Mar 12, 2018) C$ 0.70 0.90 Copper Spot Price (US$ / lb) 3.80 Market Capitalization C$M 312 Copper Spot Price (US$ / lb) 0.80 3.60 NCU Share Price (C$ / sh) Senior De

  28. Slide 28: Significant Re-rating Potential Independent of Copper Prices

    Slide 28: Significant Re-rating Potential Independent of Copper Prices

    Significant Re-rating Potential Independent of Copper Prices (1) Peer Comparison 1.40x 1.20x 1.15x 1.00x 0.80x 0.75x 0.66x P / NAV 0.57x 0.60x 0.46x 0.40x 0.34x 0.36x 0.24x(2) 0.26x 0.20x 0.00x Panoro Trilogy Metals Filo Polymet Mining Nevada Copper Western Copper Ivanhoe Mines Northern Dynasty NGEx

  29. Slide 29: Open Pit - Potential 30,000 TPD Layout

    Slide 29: Open Pit - Potential 30,000 TPD Layout

    Open Pit - Potential 30,000 TPD Layout 29

  30. Slide 30: Pumpkin Hollow Mineral Underground Reserves

    Slide 30: Pumpkin Hollow Mineral Underground Reserves

    Pumpkin Hollow Mineral Underground Reserves (1)(2) Nov 2017 NI43-101: Case A Underground Development Mineral Reserves – Eastern Underground Deposits (East and E2) : (Nov 2017 43-101 Technical Report: Case A) Contained Contained Contained Copper Ore Copper Gold Silver Copper Gold Silver Equiv. Classi

  31. Slide 31: Pumpkin Hollow Integrated Mineral Reserves

    Slide 31: Pumpkin Hollow Integrated Mineral Reserves

    Pumpkin Hollow Integrated Mineral Reserves (1)(2) Nov 2017 NI43-101: Case B Integrated Development Mineral Reserves North & South - Open Pit Deposits Ore Copper Gold Silver Contained Contained Contained Copper Copper Gold Silver Equiv. Classification 000's tons % Oz./ton Oz./ton 000s lbs. Ozs. Ozs.

  32. Slide 32: Nevada Copper Corp.

    Slide 32: Nevada Copper Corp.

    Nevada Copper Corp. Nevada Copper, Inc. Suite 1238, 200 Granville Street Vancouver, BC Canada V6C 1S4 T: (604) 683-8992 F: (604) 681-0122 nevadacopper.com 32

Source: Internet Archive copy of nevadacopper.com