Meeka Metals Limited · ASX:MEK

Meeka Metals — Australian Gold Conference (August 2024)

21 slides from Meeka Metals's conference presentation, Aug 28, 2024

  1. Slide 1: High Margin, Expandable Gold Operation

    High Margin, Expandable Gold Operation Development underway, first gold mid-2025 Tim Davidson | Managing Director ASX:MEK August 2024 meekametals.com.au

  2. Slide 2: Important Information Disclaimer

    IMPORTANT INFORMATION Disclaimer This information contained in this presentation is issued by Meeka Metals Limited (“Meeka” or the “Company”). The information contained herein is confidential and proprietary to the Company and is provided to recipients on the terms and conditions set out in this dis

  3. Slide 3: High Margin, Straightforward, Expandable Development

    High Margin, Straightforward, Expandable Development Tier 1 mining jurisdiction of Western Australia. DFS completed May ’24, low-capex restart, up to 64,000oz pa. First gold targeted for mid-2025. Undiscounted pre-tax free cash flow of $577M, NPV8% $344M, IRR 127% and 7-month payback. Processing cap

  4. Slide 4: Corporate Snapshot

    Corporate Snapshot $0.07 12.0 $0.06 $0.058 10.0 1,235m $0.05 Price (A$/share) 8.0 SHARE PRICE Volume (m) (26 August 2024) SHARES $0.04 6.0 $0.03 4.0 $0.02 $72m 113M $0.01 2.0 MARKET CAP OPTIONS $- - $3.0m $2.2m CASH Ownership (30 June 2024) DEBT (August 2024) 7.7% 10.6% $71m Board & Management Insti

  5. Slide 5: Leadership

    Leadership Have invested $3M in the Company to date. Board Management Paul Chapman Chris Davidson - Chief Development Officer Non-Executive Chairman MINING ENGINEER ACCOUNTANT Mine manager for Silver Lake Resources responsible for developing their newest Chartered accountant with >30 years in the re

  6. Slide 6: Murchison Gold Project – Production Ready

    Murchison Gold Project – Production Ready 100% MEK ownership in: Upgrade underway based on increased processing • 1.2Moz @ 3.0g/t Au Mineral Resource capacity and additional • 305koz @ 3.8g/t Au Ore Reserve drilling. Oxide open pits (St Anne’s / Turnberry) and existing underground (Andy Well) operat

  7. Slide 7: DFS Outlines Strong Cash Flows

    DFS Outlines Strong Cash Flows Expected to get better with increased production in Dec ’24 DFS update. 650 650 May 2024 DFS cash flows @ $3,500/oz: $577M 550 550 • Undiscounted free cash flow of $577M pre- tax and $413M post-tax. 450 450 Recommissioning • NPV8% of $344M pre-tax and $244M post- phase

  8. Slide 8: Bigger Mill = Improved Outcome in updated DFS in Dec ’24

    Bigger Mill = Improved Outcome in updated DFS in Dec ’24 • 30% increase in processing capacity from original DFS with purchase of larger 750kW / 640ktpa ball mill, motor, gearbox (+spare) and ancillary equipment for $318k in July 2024. • Other equipment including accommodation village, change house,

  9. Slide 9: DFS Economics Likely to Improve with Updated Dec ’24 DFS

    DFS Economics Likely to Improve with Updated Dec ’24 DFS Project Economics from DFS Gold Price $/oz 3,000 3,250 3,500 Revenue $M 1,169 1,267 1,364 EBITDA $M 624 717 809 Free Cash Flow (Pre-tax) $M 392 485 577 Free Cash Flow (Post-tax) $M 284 348 413 NPV8% (Pre-tax) $M 225 284 344 NPV8% (Post-tax) $M

  10. Slide 10: Production Increase Anticipated in Updated Dec ’24 DFS

    Production Increase Anticipated in Updated Dec ’24 DFS 700 700 Additional production sources available to fill increased 640ktpa processing capacity: 600 600 • 52,000oz @ 1.3g/t Au – expanded open pit mining within a $3,500/oz optimised pit shell. 500 500 • 61,000oz @ 3.3g/t Au – 2023 underground Or

  11. Slide 11: Low-risk Re-start of Existing Processing Plant

    Low-risk Re-start of Existing Processing Plant Minimal work required to re-commission 640ktpa CIL processing capacity. 11

  12. Slide 12: Permitted Infrastructure, Rapid Restart

    Permitted Infrastructure, Rapid Restart Existing infrastructure: • 640ktpa CIL processing plant • Mill workshop, stores building • Powerhouse • Water source, storage, reticulation infrastructure Andy Well process plant commissioned in July 2013, Mill Workshop / Stores kept in excellent condition. Po

  13. Slide 13: Development activities are well advanced

    Open Pit Mining Area – 19km Underground Mine Processing plant and administration complex Development infrastructure arriving Installation of 116-person accommodation village well underway Development activities are well advanced 13

  14. Slide 14: Site Layout and Access

    Site Layout and Access 9 year initial plan: • New open pits at Turnberry and St Anne’s. • Restart high-grade Andy Well underground mine. Road access via the Great Northern Highway. Processing plant at Andy Well. 20km haul road between Andy Well and Turnberry on a granted Miscellaneous Licence. Minin

  15. Slide 15: Low Risk, Low-Cost Oxide Open Pits in First 12 Months

    Low Risk, Low-Cost Oxide Open Pits in First 12 Months DFS = 55koz @ 2.6g/t Au ▪ Recent drilling focused on near-surface open pit $2,300/oz pit shells resource = 10,882m (121 holes) of infill drilling. ▪ 360koz @ 1.4g/t Au open pit Mineral Resource (86% M&I). ▪ Only oxide ore considered in DFS mine p

  16. Slide 16: Further Drilling Below Turnberry Open Pits is Expected to Deliver Underground Growth

    Further Drilling Below Turnberry Open Pits is Expected to Deliver Underground Growth ~8km underground growth drilling commencing in October 2024 average 1,600 OVM’s to a depth of 200m (where density of drilling reduces) Lack of drilling below 200m growth drilling growth drilling target area growth d

  17. Slide 17: Andy Well Underground

    Andy Well Underground High-grade, low capital re-start from existing decline development. • High-grade 505koz @ 8.6g/t Au Mineral Resource (73% M&I). • Initial 7 years of production planned. • Andy Well closed in 2017 at ~A$1,550/oz gold price. • Re-access underground mine in Jan-25. • All lodes rem

  18. Slide 18: Andy Well Underground

    Andy Well Underground Rapid, low risk re-start in CY25. • Accelerated production schedule following expansion in available processing capacity. • Mining to commence in first half of CY25. First +12 months of mining – all from existing capital development. Oblique view • Low capital re-start with exi

  19. Slide 19: Andy Well Growth

    Andy Well Growth Drilling to deliver resource growth in CY25. Stage 1 Drilling: up-dip extension of high- grade shoot Au ppm 11.4m @ 14.2g/t Au up to 1,500 OVM’s in top 400m 3.5m @ 34.4g/t Au Stage 2: growth drilling down Stage 3: infill plunge high- and extend grade shoot 3.9m @ 9.4g/t Au high-grad

  20. Slide 20: Looking Forward

    Looking Forward Planned work through FY26. FY25 FY26 Q1 Q2 Q3 Q4 Q1 Q2 Studies DFS Update - expanded processing capacity Turnberry growth drilling targeting UG extensions Drilling Open pit grade control drilling Andy Well growth drilling from UG drill platforms Camp / support infrastructure installa

  21. Slide 21: Moon

    Moon ASX:MEK (08) 6388 2700 info@meekametals.com.au meekametals.com.au DISCOVER GROW DEVELOP

Meeka Metals — Australian Gold Conference (August 2024) on 6ix