    Maintaining the Momentum Noosa Mining Conference 11 November 2020 Presented by: Andre Labuschagne

  2. Slide 2: Important notice and disclaimer

    Important notice and disclaimer This presentation may contain certain statements and projections provided by or on behalf of Aeris Resources Limited (Aeris) with respect to the anticipated future undertakings. These forward-looking statements reflect various assumptions by or on behalf of Aeris. Acc

  3. Slide 3: Compliance statements

    Compliance statements Tritton Copper Operations Production Targets Cautionary Statement The presentation includes references to a Production Plan (Production Targets) for the Company’s Tritton Copper Operations. The Production Targets referred to in this presentation are based on:  Proved Ore Reser

  4. Slide 4: Company snapshot

    Company snapshot ASX Code AIS Market capitalisation Cracow Gold Operations A$138m (fully diluted)1 Ownership 100% Mine type U/G Enterprise Value Processing 570 ktpa CIP (fully diluted)1 A$166m FY21F Production 70 – 75 koz Au FY21F AISC A$1,525/oz-A$1,575/oz Net debt2 A$28m Au Reserves(3) 550kt @ 5.1

  5. Slide 5: Aeris' corporate history

    Aeris’ corporate history Following years of restructuring, Aeris is now primed to deliver high impact growth Phase 3: Growth execution Phase 2: Position for Growth FY13 Q1 FY21 (2018 – 2020)  Acquisition of Cracow  Balance sheet strength restored Phase 1:  Pivot to active growth program: Restruct

  6. Slide 6: Cracow Gold Operations

    Cracow Gold Operations Zap heris

  7. Slide 7: Cracow Gold Operations

    Cracow Gold Operations A highly cash flow generative mine which is transforming the company  A high grade, low cost gold mine in Queensland, Australia with a proven operating history  Acquired from Evolution Mining in July 2020: ─ A$60m cash paid at completion ─ A deferred cash payment of A$15m on

  8. Slide 8: Cracow - first 4 months of ownership - exceeding our expectations

    Cracow - first 4 months of ownership - exceeding our expectations Integration  Well capitalised asset - no asset integrity issues emerged since taking ownership  New management team in place  Skilled and stable workforce – low turnover  Teams well aligned with Aeris strategy  Systems integratio

  9. Slide 9: Immediate priorities for Cracow

    Immediate priorities for Cracow  FY21 Guidance - 70koz to 75koz Au @ AISC A$1,525 – A$1,575/oz Operational  Repay A$30m Acquisition Debt Facility by end FY21 Delivery  Maximising cashflows (~A$280m in available tax losses)  Improve mine and mill productivity – processing plant already demonstrat

  10. Slide 10: Cracow – a prolific goldfield – Aeris re-invigorating exploration

    Cracow – a prolific goldfield – Aeris re-invigorating exploration  Strong history of replenishing reserves and resources - remains a key focus for Aeris  Cracow has produced more than 1.4 Moz of gold over its life since first production in 2004  Depletion consistently replaced with a 3 to 5 year

  11. Slide 11: Rebuilding the Life Of Mine Plan – targeting a horizon of +5 Years

    Rebuilding the Life Of Mine Plan – targeting a horizon of +5 Years Site Team challenged to develop a rolling 4 year plan from UG operations  Explore around current and old workings - 1 U/G drill rig operating and another on the way  Challenge all current paradigms - break all models and rebuild fr

  12. Slide 12: Cracow near mine exploration – looking in new spaces

    Cracow near mine exploration – looking in new spaces Killarney Deeps drill target • High grade mineralisation open along strike and down dip • Structure still present >100m below existing shoot • Previous drill results ― KLU180: 4m @ 7.7 g/t Au Killarney Deeps target ― CBK261: 1m @ 3.6 g/t Au Kennet

  13. Slide 13: Cracow near mine exploration – Roses Pride drilling delivers gold

    Cracow near mine exploration - Roses Pride drilling delivers gold First drilling campaign already completed  +400m strike length  44 of 48 drill holes intersected gold, including: ─ RPS003 19.0m @ 5.5 g/t Au (true width 10.1 m) ─ RPS025 15.0m @ 4.1 g/t Au (true width 6.1m) ─ RPS050 5.0m @ 5.3 g/t

  14. Slide 14: Cracow near mine exploration – Klondyke / Royal

    Cracow near mine exploration – Klondyke / Royal Klondyke and Royal Deposits Klondyke / Royal • Recent shallow drilling indicates potential. Drill results include: ― KDS002 7.0m @ 11.6 g/t Au (true width 3.3m) ― KDS003 3.0m @ 3.1 g/t Au (true width 1.7m) ― KDS017 4.0m @ 2.9 g/t Au (true width 1.4m) ―

  15. Slide 15: Cracow near mine exploration – Golden Plateau

    Cracow near mine exploration – Golden Plateau • ~850koz previously mined from Gold Plateau – both open pit and underground • Large mineralised system which remains open down plunge • Currently validating historical workings and drill hole database • Planned drill program testing shallow extensions t

  16. Slide 16: Exploring in new spaces – looking for the next big discovery

    Exploring in new spaces – looking for the next big discovery  Ballymore ─ Recently identified structure along southern margin of the current mining footprint ─ Limited drilling returned encouraging results: ─ Evidence of epithermal vein textures ─ Anomalous pathfinder elements including gold  Nort

  17. Slide 17: Tritton Copper Operations

    Tritton Copper Operations Tay heris

  18. Slide 18: Tritton Copper Operations

    Tritton Copper Operations A consistent producer with upside  Established underground copper mine and 1.8 Mtpa processing plant in Western NSW, Australia ─ Operating since 2005 with >320 kt Cu produced  Highly endowed region and tenement package ─ Nearby mines include CSA (Glencore plc), Peak and H

  19. Slide 19: Tritton Life of Mine Plan (LOM)

    Tritton Life of Mine Plan (LOM) 4 year LOM with multiple options to extend Aggressive focus on extending mine plan from:  Tritton and Murrawombie extensions  Developing Budgerygar via access from Tritton  Prioritizing higher grade Avoca Tank U/G into production  Potential Open Pits: ― Murrawombi

  20. Slide 20: Tritton – brownfields exploration (Tritton and Budgerygar)

    Tritton – brownfields exploration (Tritton and Budgerygar) Life of Mine extension opportunities Tritton Deposit: ― Mineralisation open at depth • Commenced drill program testing down plunge potential ― South Wing – adjacent to Tritton orebody – further drilling planned Corridor between Tritton and B

  21. Slide 21: Murrawombie – brownfields exploration

    Murrawombie – brownfields exploration  Geologically performing better than expected  Minerailsation open at depth and to the north  Recent drilling continues to intersect high grade mineralisation, including: ─ 14.60m @ 2.43% copper (true thickness approx. 7.8m) MWGC514; and ─ 9.55m @ 2.54% coppe

  22. Slide 22: Greenfields Exploration Activities in FY21

    Greenfields Exploration Activities in FY21 Anomaly K • Bedrock conductor identified initially from an airborne EM survey • Anomaly extended beyond tenement boundary – additional tenement granted in June quarter • Ground based EM recently completed and confirmed anomaly (approx. 150m below surface) •

  23. Slide 23: Torrens JV

    Torrens JV  Aeris holds a 70% interest and is manager of the Torrens Project through a JV with Argonaut Resources NL  Torrens located on Eastern Gawler Craton IOCG corridor in South Australia, which hosts several large scale deposits and world class copper-gold operations: ─ Olympic Dam ─ Carrapat

  24. Slide 24: An exciting path forward with multiple value catalysts in FY21

    An exciting path forward with multiple value catalysts in FY21  Exploration activities at Tritton and Cracow – looking for LOM extensions  Mineral Resources for Roses Pride and Klondyke / Royal at Cracow  Budgerygar exploration drive and drilling program  Tritton and Cracow LOM Plan reviews  Me

  25. Slide 25: Summary

    Summary FAH Aeris

  26. Slide 26: What makes Aeris different?

    What makes Aeris different? Proven team with a consistent Financially robust, rapidly track record deleveraging A unique platform to Diversified, strong free cash consolidate the landscape generation where others cannot 29 79 Favourable gold / copper Primed to unlock value Cu Au price exposure 26

  27. Slide 27: Thank You

    Thank You

  28. Slide 28: Appendix

    Appendix

  29. Slide 29: Tritton – reported Mineral Resource

    Tritton – reported Mineral Resource Tritton tenement package (30 June 2020)(1)(2) Measured Indicated Inferred Total Resource Cut-off Project (%Cu) Tonnes Cu grade Cu metal Tonnes Cu grade Cu metal Tonnes Cu grade Cu metal Tonnes Cu grade Cu metal (kt) (%) (kt) (kt) (%) (kt) (kt) (%) (kt) (kt) (%) (k

  30. Slide 30: Tritton – reported Ore Reserve

    Tritton – reported Ore Reserve Tritton tenement package (30 June 2020)(1)(2)(3)(4) Proven Probable Total Ore Reserves Cut-off Project Type (%Cu) Tonnes Cu grade Cu metal Tonnes Cu grade Cu metal Tonnes Cu grade Cu metal (kt) (%) (kt) (kt) (%) (kt) (kt) (%) (kt) Tritton Underground 1.2 1,200 1.5 17 1

  31. Slide 31: Cracow – Mineral Resource and Ore Reserve

    Cracow – Mineral Resource and Ore Reserve Cracow (30 June 2020)(1) Gold grade Tonnes (Mt) Gold metal (koz) (g/t) Ore Reserve Proven 0.28 5.2 46 Probable 0.27 4.9 43 Total 0.55 5.1 89 Mineral Resource Measured 0.20 7.8 53 Indicated 0.69 5.9 130 Inferred 1.40 2.6 120 Total 2.30 4.0 300 (1) Full detail

  32. Slide 32: Competent Persons statement

    Competent Persons statement Competent Persons statement Mr Cox confirms that he is the Competent Person for all the Mineral Resource and Exploration Target estimates summarised in this Report and he has read and understood the requirements of the 2012 Edition of the Australasian Code for Reporting o