Alta Copper — Fortescue Metals Group — Macquarie Australia Conference 2020
20 slides from Alta Copper's conference presentation, May 5, 2020

Slide 1: Macquarie Australia Conference
Macquarie Australia Conference 5 May 2020 Global force Thriving communities 100-TE-DC-0036_13

Slide 2: Forward Looking Statements
Important Notice The purpose of this presentation is to provide general information about Fortescue Metals Group Ltd ("Fortescue"). It is not recommended that any person makes any investment decision in relation to Fortescue based on this presentation. This presentation contains certain statements w

Slide 3: A world class company
A world class company Wholly owned, >1.3 billion tonnes 170 - 175mtpa fully integrated Shipped Shipping rate supply chain Core supplier Industry leading to China cost position 3

Slide 4: COVID-19 response
COVID-19 response Prioritise the health of our people, maintain jobs, sustain our business and protect our communities Temporary extension Additional bus and air of operational roster charter services Temperature and health Non-essential site and testing and rapid office-based teams screening workin

Slide 5: Safety and unique culture
Safety and unique culture 2.5 TRIFR Total Recordable Injury Frequency Rate on a 12 month rolling basis 11% Improvement compared to 30 June 2019 Reducing fatality risk profile 5

Slide 6: 1H20 highlights
1H20 highlights 88.6 million tonnes Iron ore shipped US $4.2 billion Underlying EBIDTA US 65% $2.5 billion Underlying EBITDA margin Net profit after tax A US $0.80 ( A $1.16) Earnings per share $0.76 per share Fully franked interim dividend 6

Slide 7: March quarter 2020 highlights
March quarter 2020 highlights US$73/dmt TRIFR 2.5 11% improvement from 2.8 in FY19 Average price received 82% of 62% Fe Index 42.3mt shipped US$13.27/wmt 10% higher than Q3 FY19 C1 costs 2% lower than Q3 FY19 Growth projects US$0.1billion Key milestones achieved Net cash 7

Slide 8: Integrated mine to market infrastructure
Integrated mine to market infrastructure 8

Slide 9: Robust demand in China
Robust demand in China China’s steel production increased 1.2% YoY in Q1 CY20 China Crude Steel Production (mt) Fortescue is a core supplier of 95 iron ore to China 90 85 China’s steel production 80 increased to 235mt in Q1 CY20 75 70 Steel inventories drawn down 65 as economic activity recovers 60

Slide 10: Iron ore prices resilient
Iron ore prices resilient Sustained demand and supply disruptions support the iron ore market Iron Ore Prices (CFR China), US$/dmt Strong demand for Fortescue’s 140 products 120 100 Realisation of 84% of the Platts 80 62% Index year-to-date FY20 60 Draw down of iron ore stocks at 40 Chinese ports 20

Slide 11: Enhanced product mix delivers value
Enhanced product mix delivers value Realising the benefits of West Pilbara Fines Fortescue’s product mix % 9 months to March 2019 9 months to March 2020 10 4 8 8 33 38 45 7 42 4 West Pilbara Fines Kings Fines Fortescue Blend West Pilbara Fines Kings Fines Fortescue Blend 11 Fortescue Lump Super Spec

Slide 12: Growth and development
w7 i a ait ; \ < Fortescue s Growth and - development | Pa

Slide 13: Eliwana project
Eliwana project US$1.275 billion capital investment, Progressing on schedule and budget Stage 1 earthworks First steel erection on 143km railway completed of 30mtpa dry OPF Aerodrome and village Construction peak completed, first charter June 2020 mid-2020 13

Slide 14: Iron Bridge Magnetite Project
Iron Bridge Magnetite Project US$2.6 billion investment delivering enhanced returns to shareholders and JV partners 22 mpta, 67% Fe product Detailed engineering First ore on ship mid-2022 passed halfway mark First blast at OPF site Site construction Allowing earthworks to commence will commence seco

Slide 15: Energy infrastructure
Energy infrastructure US$8001 million investment providing 25–30 per cent of stationary energy requirements from solar Pilbara Transmission project Pilbara Generation project 275km of high voltage transmission lines 150MW gas, 150MW solar PV Large scale battery storage Chichester Solar Gas Hybrid Di

Slide 16: Investing in growth
Investing in growth Iron Bridge Magnetite (US$m) Pilbara Energy Connect (US$m) Investing in growth Eliwana Mine and Rail (US$m) 1,200–1,300 1,200 - 1,300 Disciplined 550-650 allocation to core business, innovation and growth 350-400 500-600 250-300 400-500 300-400 50 FY20 FY21 FY22 FY20 FY21 FY22 FY

Slide 17: FY20 Guidance
175-177mt FY20 Shipments Guidance US$12.75-$13.25 C1 cost / wmt US$2.0-2.2 billion Capital investment 17

Slide 18: Key strategic focus
Key strategic focus Balance sheet Long term strength sustainability Growth and Enhanced returns development to shareholders 18

Slide 19: Our vision
Our = . Vi S re] n 7 << 4 f Renesas The safest, lowest «. an cost, most profitalale mining company = Ke A —“ EEA

Slide 20
Source: company website
More decks from Alta Copper Corp.
Investor Presentation (September 2025)36 slides · September 2025
Investor Presentation (July 2025)34 slides · July 2025
Investor Presentation (June 2025)35 slides · Jun 20, 2025
Investor Presentation (April 2025)35 slides · April 2025
Investor Presentation (October 2024)34 slides · October 2024
Investor Presentation (May 2023)24 slides · May 26, 2023