Alta Copper — Fortescue Metals Group — Corporate Update (November 2019)
20 slides from Alta Copper's corporate update, Nov 28, 2019

Slide 1: Building world-class mines: An integrated approach to marketing, operations and infrastructure
Building world-class mines: An integrated approach to marketing, operations and infrastructure Greg Lilleyman, COO 28 November 2019

Slide 2: Important Notice
Important Notice The purpose of this presentation is to provide general information about Fortescue Metals Group Limited ("Fortescue"). It is not recommended that any person makes any investment decision in relation to Fortescue based on this presentation. This presentation contains certain statemen

Slide 3: A world class company
A world class company >1.3 billion ~170mtpa Shipped Wholly owned, fully integrated supply chain Core supplier Low cost to China producer 3

Slide 4: Track record of embracing innovation
Track record of embracing innovation Approach to Financing and exploration marketing Remote Autonomous operations haulage 4

Slide 5: Culture of innovation
Culture of innovation People and process Data analytics Assets 5

Slide 6: Automated mining
Automated mining Innovation delivering safety and productivity improvements AHS operation Autonomous drills >37 million km safely travelled 8 drills in operation AHS conversion Relocatable conveyor 147 trucks in operation Operating at full capacity 6

Slide 7: Clear strategic focus
Clear strategic focus Core Leadership Product Team strategy Appointed in February 2018 Majority over 60% Fe Deliberate strategy for dynamic Structure of Fully future growth business integrated Operations and marketing Supply chain 7

Slide 8: Fully integrated supply chain
Fully integrated supply chain Supported by a culture of innovation 8

Slide 9: Integrated operations and marketing
Integrated operations and marketing Direct customer engagement Co-location of key decision driving deep market insights makers enabling rapid response to market trends Collaborative operations Agile product mix adjustments and marketing to optimise to meet customers’ needs market opportunities 9

Slide 10: Shipping and towage fleet
Shipping and towage fleet Designed to optimise efficient port infrastructure Eight ore carriers Towage fleet Completed over 180 journeys Maximise efficiencies of operations 14% of Fortescue’s annual volume Additional towage capacity 10

Slide 11: China port sales
China port sales Enhanced sales channel offering, supporting marketing strategy of direct customer engagement More flexibility Greater choice Established in April 2019 Purchase smaller lot sizes Trading in RMB Sales volume Expedited delivery ~5% of Fortescue China sales 11

Slide 12: Investment in growth
Investment in growth Unparalleled track record and capability in safely developing and operating major iron ore projects in the Pilbara 12

Slide 13: Eliwana project
Eliwana project US$1.275 billion capital investment Progressing on schedule and budget Infrastructure Latest technology 143km rail; 30mtpa dry OPF Driving low cost operation First ore on train West Pilbara Fines December 2020 Increasing production and mine life 13

Slide 14: Ore processing facility overview
Ore processing facility overview Significantly smaller footprint compared to Firetail Fortescue integrated design team Firetail 30mtpa dry processing Low height structure designed to support onsite construction Eliwana Optimised, highly efficient design Low capital intensity Modular plant design 14

Slide 15: Iron Bridge Magnetite Project
Iron Bridge Magnetite Project Integrated mine to port solution US$2.6 billion 22 mtpa Investment delivering value First ore scheduled mid-2022 67% Fe Low capital Low impurity premium product intensity and operating cost 15

Slide 16: Innovative process and design
Innovative process and design US$0.5 billion invested in Stage 1 to reduce process technical risk Stage 1 pilot plant OPF process flow Rigorous process validation Dry grinding and crushing circuit Magnetite recovery Energy efficient Efficiently handle by-product Industry leading, proven design 16

Slide 17: Diverse product offering
Diverse product offering Aligned with customer requirements Competitively positioned across all key segments Flexibility to optimise product mix to meet customer requirements Highest grade Australian product with global scale in magnetite 17

Slide 18: Delivering on our strategy
Delivering on our strategy Driven by innovation, our culture and values Supply chain Fully integrated from pit to port Optimise value Integrated operations and marketing Product strategy Majority over 60% Fe 18

Slide 19: Our = |
Our = | Vi S re] n 7 << 4 f Renesas The safest, lowest «. an cost, most profitalale mining company = Ke A —“ EEA

Slide 20: Fortescue
as Fortescue
Source: company website
More decks from Alta Copper Corp.
Investor Presentation (September 2025)36 slides · September 2025
Investor Presentation (July 2025)34 slides · July 2025
Investor Presentation (June 2025)35 slides · Jun 20, 2025
Investor Presentation (April 2025)35 slides · April 2025
Investor Presentation (October 2024)34 slides · October 2024
Investor Presentation (May 2023)24 slides · May 26, 2023