Investor Presentation May 2017 Unearthing the minerals powering our future

Slide 2: Why Cape Lambert Resources?
Why Cape Lambert Resources? Cape Lambert is a diversified mineral development and investment company well positioned to deliver shareholder value though our Acquire, Add Value and Realise strategy. Our activities aim to meet global demand for minerals that drive progress and power our future. Strate

Slide 3: Company Strategy
Company Strategy In line with our strategy to acquire and invest in undervalued and undeveloped mineral projects we seek to capitalise on an undervalued and emerging cobalt market by acquiring the rights to: ▪ a readily available cobalt rich tailings dam in the DRC copper belt; ▪ a nearby processing

Slide 4: DRC Cobalt Project – Summary
DRC Cobalt Project – Summary Paragon’s holdings/interests that ▪ a 70% interest in the Kipushi tailings dam and will increase that interest to 85%; are part of the proposed JV Agreement include: ▪ 100% ownership of the Kipushi Processing Plant; and ▪ The rights to acquire 100% interest in 3 cobalt r

Slide 5: DRC Cobalt Project – JVCo Objectives
DRC Cobalt Project – JVCo Objectives The objectives of the JVCo will be to: ▪ commence mining activities at Kipushi Tailings as soon as practical; ▪ commence exploration activities on Kasombo; ▪ complete a Feasibility Study on Kasombo within 18 months; ▪ commence mining activities at Kasombo as soon

Slide 6: Cobalt Sources
Cobalt Sources Most cobalt is produced as a by product of either copper or nickel production 38% nickel 60% copper production by production by product product 2% primary cobalt production Page 6 | May 2017

Slide 7: Cobalt – Qualities & Applications
Cobalt – Qualities & Applications Cobalt - one of the worlds essential minerals ▪ Lustrous, silvery-blue, magnetic metal; ▪ High melting point (1,495 degrees Celsius); ▪ Maintains strength even at high temperatures; ▪ Maintains its magnetism at temperatures up to 1,121 degrees Celsius; ▪ Used in: pi

Slide 8: Global Cobalt Production
Global Cobalt Production Page 8 | May 2017

Slide 9: Global Cobalt Supply/Demand Balance
Global Cobalt Supply/Demand Balance Page 9 | May 2017

Slide 10: Why the DRC?
Why the DRC? The DRC holds approximately 47% of the global cobalt reserve base. It is the world's single largest supply source with roughly 63% of global cobalt supply originating in the DRC. Page 10 | May 2017

Slide 11: Kipushi Project Location
Kipushi Project Location The Kipushi Project is located only 25 minutes from the well established mining town of Lubumbashi and is accessed mostly by sealed road. Page 11 | May 2017

Slide 12: DRC Cobalt Project Layout
DRC Cobalt Project Layout Page 12 | May 2017

Slide 13: Kipushi Cobalt Project – Tailings Dam
Kipushi Cobalt Project – Tailings Dam View over Kipushi tailings dam The Kipushi tailings dam extends over 1km in length, over 400m in width, with an average depth of 8m. It is located approximately 8km from the Kipushi Processing Plant. Page 13 | May 2017

Slide 14: Kipushi Tailings Dam – Sampling Locations
Kipushi Tailings Dam – Sampling Locations Refer ASX announcement dated 29 March 2017 for full details Page 14 | May 2017

Slide 15: Kipushi Processing Plant
Kipushi Processing Plant The Kipushi Processing Plant comprises a conventional flotation plant with a design throughput of 150tph. The process plant is connected to State power via a 12Mw substation. Construction of the process plant is all but complete and requires upgrades and commissioning. Page

Slide 16: Kipushi Processing Plant
Kipushi Processing Plant View over milling circuit Administration Building View over flotation circuit Conveyors for dry tailings disposal Page 16 | May 2017

Slide 17: Kasombo Copper-Cobalt Project
Kasombo Copper-Cobalt Project The Kasombo Copper-Cobalt Project (Kasombo) is part of the Kasombo Complex, a series of copper- cobalt rich deposits that have been extensively explored by Gecamines and developed and mined by various international companies in joint venture with Gecamines. Kasombo is a

Slide 18: Kasombo Copper-Cobalt Project
Kasombo Copper-Cobalt Project Results from random hand held XRF sampling were consistent with and confirmed the previously reported mined copper and cobalt grades by Gecamines and Forrest International Group of between 2.7% to 3.7% copper and 3.5% to 5.3% cobalt. An extreme high grade rock sample fr

Slide 19: Kitwe Cobalt-Copper Tailings Project – Summary
Kitwe Cobalt-Copper Tailings Project – Summary Acquisition details: ▪ Binding terms sheet to conditionally acquire a 70% interest in the Kitwe Cobalt-Copper Tailings Project; (Kitwe Tailings Project) located in Zambia close to the border of the DRC. ▪ Commitment to expend US$500,000 within 6 months

Slide 20: Kitwe Tailings Project Location
Kitwe Tailings Project Location The Kitwe Tailings Project is located approx. 3km from the outskirts of Zambia’s second largest city, Kitwe. Kitwe is an established commercial and industrial area along side Ndola and Lusaka. Page 20 | May 2017

Slide 21: Kitwe Tailings Project – Tailings Dam
Kitwe Tailings Project – Tailings Dam The Kitwe Tailings Project is located in the Zambian Copper belt, one of the world’s largest producing regions of high grade cobalt and copper concentrates and LME grade copper metal with several of the world’s largest copper producing companies operating in the

Slide 22: Kitwe Tailings Dam – Sampling Locations
Kitwe Tailings Dam – Sampling Locations Kitwe Cobalt Project tailings dam Refer ASX announcement dated 22 May 2017 for full details Page 22 | May 2017

Slide 23: Project Operational Objectives
Project Operational Objectives Transaction and Testing and Construction Production Due Diligence Processing Complete due diligence, Further sampling and Finalise and optimise Targeting the exercise of option (project metallurgical testing Kitwe Tailings operational commencement of spend commitment)

Slide 24: Appendices
Cape Lambert [~<\ esources Ltd ey APPENDICES

Slide 25: Corporate Snapshot
Corporate Snapshot Board of Directors 721M $20.9M issued shares market cap @ $0.029 Tony Sage - Executive Chairman Over 30 years’ experience in corporate advisory, funds management, capital raisings and 23.5M $1.2M management of exploration companies. options outstanding1 cash @ 31 Mar 2017 Tim Turn

Slide 26: Business Model & Strategy
Business Model & Strategy Our project team has the technical and commercial Acquire Add Value expertise and experience to > Leverage off strong maximise project development > “Hands on” balance sheet & approach relationships > Explore and > Early stage projects & evaluate project companies considere

Slide 27: Attributes
Attributes Competent Persons Statement The information in this report that relates to Exploration Results is based on information compiled by Mr Olaf Frederickson. Mr Frederickson is a Member of The Australasian Institute of Mining and Metallurgy (AusIMM) and has sufficient experience relevant to th

Slide 28: Disclaimer
Disclaimer This presentation has been prepared by Cape Lambert Resources Limited (“Cape Lambert” or the “Company”). It is not a disclosure document and should not be considered as an offer or invitation to subscribe for, or purchase any securities in the Company or as an inducement to make an offer

Slide 29: www.capelam.com.au
WWW.CAPELAM.COM.AU Cape Lambert Resources Limited Australian PR Investor Relations Professional Public Relations phone: +61 8 9380 9555 David Tasker email: info@capelam.com.au + 61 8 9388 0944 / + 61 (0)433 112 936
Source: Internet Archive copy of capelam.com.au
More decks from Iron Bear Resources Ltd
Shareholder Meeting (November 2026)25 slides · Nov 23, 2026
Investor Presentation (June 2026)23 slides · Jun 17, 2026
Investor Presentation (May 2026)24 slides · May 6, 2026
Cape Lambert Resources — Mining Indaba 201833 slides · February 2018
Cape Lambert Resources — Mines and Money London 201730 slides · November 2017
Cape Lambert Resources — PDAC Convention 201726 slides · March 2017