  1. Slide 1: Project Update

    Slide 1: Project Update

    Project Update  General Manager – Joe Ranford has accepted a role in Finland  Terramin continue to have same development team on BIHGP  Martin Janes to become Project Director  No formal feedback received on draft Mining Lease Proposal  Helpful comment on impact assessment layout  Corresponden

  2. Slide 2: MAR Drilling EPEPR – stage 1

    Slide 2: MAR Drilling EPEPR – stage 1

    MAR Drilling EPEPR – stage 1  Proposal submitted for three reinjection bores with paired monitoring bore – to gain DEWNR ‘drainage permit’  Results from these bores will inform the test work proposal/EPEPR  Objectives for MAR trial  Confirms groundwater model  Mitigates salt intrusion from Dawe

  3. Slide 3: Bird in Hand Gold Project

    Slide 3: Bird in Hand Gold Project

    Bird in Hand Gold Project TERRAMIN AUSTRALIA LIMITED SLIDE No. 3

  4. Slide 4: Structure of Presentation

    Slide 4: Structure of Presentation

    Structure of Presentation  The nature of impact – How do economic impacts occur?  Existing economic environment – understanding the local economy  Experts used and why  What we have heard – and how we are addressing these concerns  Land value  Perceptions TERRAMIN AUSTRALIA LIMITED SLIDE No. 4

  5. Slide 5: What is economic impact?

    Slide 5: What is economic impact?

    What is economic impact?  Negative economic impacts could occur if there is a confirmed  Source – A description of the source of the potential impact event which alone or in combination has the potential to cause harm to an environmental receptor.  Pathway – A description of the potential pathway

  6. Slide 6: Experts - Economic

    Slide 6: Experts - Economic

    Experts - Economic  Barry Burgan – Economic Research Consultants  Professor of Management and MBA Program Director at Bond University  Expertise: financial, economic and social assessments  Member: Initial Accreditation Committee of Assoc. to Advance Collegiate Schools of Business  Jim Hancock

  7. Slide 7: FABAL – Agricultural Experts

    Slide 7: FABAL – Agricultural Experts

    FABAL – Agricultural Experts  Ashley Keegan – B.App Sci (viticulture); MBA (finance)  CEO - Operations, Food and Beverage Australia Limited (FABAL), Adelaide  One of Australia’s largest privately owned vineyard/agricultural management groups  Agribusiness – vineyards, orchards, groves – 1700Ha v

  8. Slide 8: FABAL – Agricultural Experts

    Slide 8: FABAL – Agricultural Experts

    FABAL – Agricultural Experts  Chris Day - MBA (international business), Bachelor of Laws and Economics, Grad. Dip in Financial Services  CEO - Group, Food and Beverage Australia Limited (FABAL), Adelaide  25 years experiences in wine industry  Chairman: SA Business Development Committee  Direct

  9. Slide 9: Currently happening – Terramin’s understanding

    Slide 9: Currently happening – Terramin’s understanding

    Currently happening – Terramin’s understanding  We understand this from  Economic Research Consultants – “Economic Impact Assessment”  South Australian Centre for Economic Studies, University of Adelaide, – “Peer Review of Economic Impact Assessment”  Econsearch – “Economic Contribution of Agric

  10. Slide 10: Current Land uses

    Slide 10: Current Land uses

    Current Land uses  Adelaide Hills is a mixed-economic activity area  Long history of resources development  Agriculture, horticulture, defence, food and wine processing, retail, hospitality, water treatment, conservation and recreation  Currently 36 quarry licences in operation in Adelaide Hills

  11. Slide 11: Current Employment Trends – ABS

    Slide 11: Current Employment Trends – ABS

    Current Employment Trends – ABS  Adelaide Hills has an increasing unemployment trend 8.0 7.0 6.0 Unemployment Rate - % 5.0 4.0 3.0 2.0 1.0 0.0 2010 2011 2012 2013 2014 2015 2016 2017 Adelaide Hills Council Regional SA South Australia TERRAMIN AUSTRALIA LIMITED SLIDE No. 11

  12. Slide 12: What’s happening in other areas in SA?

    Slide 12: What’s happening in other areas in SA?

    What’s happening in other areas in SA?  Strathalbyn – Mine co-existed with grain farming, hospitality, horses and polo fields and Langhorne Creek wine region.  Barossa Valley – Largest extractive quarry (vineyards, cellardoors, B&Bs)  McLaren Vale – numerous quarries located adjacent (inc. 600m f

  13. Slide 13: Proposed Project – over 8 years

    Slide 13: Proposed Project – over 8 years

    Proposed Project – over 8 years  Impact on SA Economy  $280M  TOTAL: 140 direct jobs and 423 indirect (year 4)  599 direct FTE and 1837 indirect FTEs over 5 years  Impact on Adelaide Hills Economy  93 direct jobs and 240 indirect (year 4)  $152.6M  Impact on Fleurieu Peninsula Region  44 di

  14. Slide 14: Local Spend Policy

    Slide 14: Local Spend Policy

    Local Spend Policy  Terramin have a local spend policy  Always use local services and suppliers where possible  Estimated to be – $7M per year directly into local Woodside and surrounds economy – $152.6M into Adelaide Hills region (over project)  $30M per year operating expenditure (operating ph

  15. Slide 15: TERRAMIN AUSTRALIA LIMITED SLIDE No. 15

    Slide 15: TERRAMIN AUSTRALIA LIMITED SLIDE No. 15

    TERRAMIN AUSTRALIA LIMITED SLIDE No. 15

  16. Slide 16: We have heard

    Slide 16: We have heard

    We have heard  Concern: Visual amenity could impact businesses  Used Oxigen - 2017 South Australian Landscape Architecture Awards – Tonsley, Adelaide Riverbank, Flinders uni, Waterfall gully, Halifax St  Visual amenity plan removes the pathway of seeing mining infrastructure from hospitality/cell

  17. Slide 17: TERRAMIN AUSTRALIA LIMITED SLIDE No. 17

    Slide 17: TERRAMIN AUSTRALIA LIMITED SLIDE No. 17

    TERRAMIN AUSTRALIA LIMITED SLIDE No. 17

  18. Slide 18: Proposed Entrance

    Slide 18: Proposed Entrance

    Proposed Entrance TERRAMIN AUSTRALIA LIMITED SLIDE No. 18

  19. Slide 19: View Once Built from Cellardoors

    Slide 19: View Once Built from Cellardoors

    View Once Built from Cellardoors VIEW BIH CELLARDOOR VIEW ARTWINE CELLARDOOR TERRAMIN AUSTRALIA LIMITED SLIDE No. 19

  20. Slide 20: Current Vegetation Growth

    Slide 20: Current Vegetation Growth

    Current Vegetation Growth TERRAMIN AUSTRALIA LIMITED SLIDE No. 20

  21. Slide 21: We have heard

    Slide 21: We have heard

    We have heard  Concern: Nuisance noise could impact businesses  We have designed our site to be 10 dB(A) lower than the legislative limits and inline with baseline noise measurements taken  Lower limits than adjoining agricultural businesses  Includes acoustic mitigation strategies – enclosing,

  22. Slide 22: We have heard

    Slide 22: We have heard

    We have heard  Concern: Dust could impact businesses  We have designed our site to remove most “normal” mining dust sources  Bitumised roads, ore silo system, vegetation buffers, hydromulching  Agricultural Impact Assessment identifies dust monitoring programme associated with Project likely to

  23. Slide 23: We have heard

    Slide 23: We have heard

    We have heard  Concern: Dust has the potential to inhibit vineyard productivity  Agricultural Impact Assessment discusses  Deposition rates of organic fungicides and current practice of applying white reflective clay on vines (Kaolin) – no statistical difference in photosynthesis rates  Agricult

  24. Slide 24: We have heard

    Slide 24: We have heard

    We have heard  Concern: Vibration could impact businesses  We have designed vibration to be half of the vibration felt if person was walking next to you at all hospitality businesses  Removes or reduces the pathway significantly  No impact to businesses envisaged – either to hospitality business

  25. Slide 25: Year 1 – development, Year 3 – production, Year 5 – production

    Slide 25: Year 1 – development, Year 3 – production, Year 5 – production

     Year 1 – development  Year 3 – production  Year 5 – production TERRAMIN AUSTRALIA LIMITED SLIDE No. 25

  26. Slide 26: Year 1 – development, Year 3 – production, Year 5 – production

    Slide 26: Year 1 – development, Year 3 – production, Year 5 – production

     Year 1 – development  Year 3 – production  Year 5 – production TERRAMIN AUSTRALIA LIMITED SLIDE No. 26

  27. Slide 27: Year 1 – development, Year 3 – production, Year 5 – production

    Slide 27: Year 1 – development, Year 3 – production, Year 5 – production

     Year 1 – development  Year 3 – production  Year 5 – production TERRAMIN AUSTRALIA LIMITED SLIDE No. 27

  28. Slide 28: We have heard

    Slide 28: We have heard

    We have heard  Concern: Groundwater could impact businesses  We respect businesses rely on groundwater  We have designed water management system to not impact any agricultural businesses’ ability to access water  Proposal - Water neutral and licenced trading  This includes – Fracture avoidance

  29. Slide 29: Credible worst case – 70% Effective Grouting with MAR

    Slide 29: Credible worst case – 70% Effective Grouting with MAR

    Credible worst case – 70% Effective Grouting with MAR 6628 6628 6628 6628 6628 6628 6628 6628 6628 6628 6628 6628 8936 8940 10944 9154 23182 9153 8946 20475 18637 9152 10249 8301 Ground level 0.00 20.00 40.00 60.00 metres below surface 80.00 100.00 120.00 140.00 160.00 AIR SWL Range Terramin contrib

  30. Slide 30: Expected Impact – 90% Effective Grouting with MAR

    Slide 30: Expected Impact – 90% Effective Grouting with MAR

    Expected Impact – 90% Effective Grouting with MAR 6628 6628 6628 6628 6628 6628 6628 6628 6628 6628 6628 6628 Ground level 8936 8940 10944 9154 23182 9153 8946 20475 18637 9152 10249 8301 0.00 20.00 40.00 metres below surface 60.00 80.00 100.00 120.00 140.00 AIR SWL Range Terramin contribution 90%+M

  31. Slide 31: Groundwater Modelling Reviews

    Slide 31: Groundwater Modelling Reviews

    Groundwater Modelling Reviews  IGS – Commissioned by Terramin for the Ministerial Determination  Concluded Model is fit for purpose regarding the objectives – Objectives: verification of data, implementation of conceptual model into numerical model, model calibrations, scenario modelling (includin

  32. Slide 32: Agricultural Impact Assessment

    Slide 32: Agricultural Impact Assessment

    Agricultural Impact Assessment  The Agricultural Impact assessment considers spray drift and disease introduction a low risk  We have removed use of Group I, Phenoxy Acid herbicides onsite  We use weed spraying chemicals registered in the Aus. Wine Institute registered pesticide guidelines  Stan

  33. Slide 33: Other issues considered by Ag. Impact Assessment

    Slide 33: Other issues considered by Ag. Impact Assessment

    Other issues considered by Ag. Impact Assessment  Considers additional vegetation (shelter belt) planting to be beneficial for biota habitat (Thompson and Hoffman, 2010; Retallack, 2012) and additional buffering capacity between both sites (dust sources and spraying activities)  Tourism – largely

  34. Slide 34: Conclusion – Agricultural Impact Assessment

    Slide 34: Conclusion – Agricultural Impact Assessment

    Conclusion – Agricultural Impact Assessment  Agricultural Impact Assessment  Considered all impact assessments and information available  Included site walk over  Most credible pathways have been considered  Based on implementation of design and proposed controls, residual risks are low TERRAMI

  35. Slide 35: Conclusion – Economic Impact Assessment

    Slide 35: Conclusion – Economic Impact Assessment

    Conclusion – Economic Impact Assessment  Economic Impact Assessment – if no management strategies used  Overall conclusion is that the risk to other economic activities in the area is low  Economic Model: If all management and/or mitigation were not implemented – i.e. no water, dust, noise, visua

  36. Slide 36: TERRAMIN AUSTRALIA LIMITED SLIDE No. 36

    Slide 36: TERRAMIN AUSTRALIA LIMITED SLIDE No. 36

    TERRAMIN AUSTRALIA LIMITED SLIDE No. 36

  37. Slide 37: Land Value

    Slide 37: Land Value

    Land Value  Strathalbyn has seen continued growth even with operating mine since 2007 (Care and Maintenance Q4: 2013) **Average sale price 2009 2010 TERRAMIN AUSTRALIA LIMITED SLIDE No. 37 Realestate.com.au, retrieved 7th March 2018

  38. Slide 38: Woodside

    Slide 38: Woodside

    Woodside  Mineral Claim registered in 2007 **Average sale price 2009 2010 TERRAMIN AUSTRALIA LIMITED SLIDE No. 38 Realestate.com.au, retrieved 7th March 2018

  39. Slide 39: Woodside

    Slide 39: Woodside

    Woodside  No current indication of real estate impact with proposed project over last 12 months **Average sale price Mar-17 Apr-17 TERRAMIN AUSTRALIA LIMITED SLIDE No. 39 Realestate.com.au, retrieved 7th March 2018

  40. Slide 40: Within and Surrounding Mineral Claim

    Slide 40: Within and Surrounding Mineral Claim

    Within and Surrounding Mineral Claim  Even with Mineral Claim since 2007 and proposed mining project  8 adjoining properties have sold  5 in previous 5 years  4 in previous 18 months TERRAMIN AUSTRALIA LIMITED SLIDE No. 40

  41. Slide 41: TERRAMIN AUSTRALIA LIMITED SLIDE No. 41

    Slide 41: TERRAMIN AUSTRALIA LIMITED SLIDE No. 41

    TERRAMIN AUSTRALIA LIMITED SLIDE No. 41

  42. Slide 42: Land Value

    Slide 42: Land Value

    Land Value  If you feel your property will be impacted, there is a process  Terramin will continue to monitor and compensation may be available to proven land value reductions  Prescribed process - Mining Act 1971 (SA)  Potential for independent value assessments  Process to assess: prior to PE

  43. Slide 43: Perception - Tourism

    Slide 43: Perception - Tourism

    Perception - Tourism  Anchor survey results from CSIRO  Local people are not sure that Project will discourage tourists from visiting  This group of people have limited information about the Project TERRAMIN AUSTRALIA LIMITED SLIDE No. 43 Strongly disagree Strongly agree

  44. Slide 44: CSIRO Anchor Survey

    Slide 44: CSIRO Anchor Survey

    CSIRO Anchor Survey  Local shops and  Mine will provide  The mine will provide businesses will benefit valuable taxes and opportunities for local other income for the suppliers and contractors from mine employees state government Strongly disagree Strongly agree Strongly disagree Strongly agree S

  45. Slide 45: Community Grant Scheme – Opportunity for WCCC

    Slide 45: Community Grant Scheme – Opportunity for WCCC

    Community Grant Scheme – Opportunity for WCCC  The aim of these grants is to support projects that provide specific sustainable outcomes which have long lasting benefit/s to the wider community  Not for profit, sporting and recreation, environmental and community organisations  Projects must prov

  46. Slide 46: What if?

    Slide 46: What if?

    What if?  My business has been negatively impacted by the mining project?  Some mining activities will be compensated for prior to construction  Defined by Mining Act 1971 (SA)  Negotiated by Terramin and landowner, if no agreement, ERD Court utilised  Evaluated prior construction  Communicate

  47. Slide 47: TERRAMIN AUSTRALIA LIMITED SLIDE No. 47

    Slide 47: TERRAMIN AUSTRALIA LIMITED SLIDE No. 47

    TERRAMIN AUSTRALIA LIMITED SLIDE No. 47