Terramin Australia Limited · ASX:TZN
Terramin Australia — Corporate Update (March 2018)
47 slides from Terramin Australia's corporate update, March 2018

Slide 1: Project Update
Project Update General Manager – Joe Ranford has accepted a role in Finland Terramin continue to have same development team on BIHGP Martin Janes to become Project Director No formal feedback received on draft Mining Lease Proposal Helpful comment on impact assessment layout Corresponden

Slide 2: MAR Drilling EPEPR – stage 1
MAR Drilling EPEPR – stage 1 Proposal submitted for three reinjection bores with paired monitoring bore – to gain DEWNR ‘drainage permit’ Results from these bores will inform the test work proposal/EPEPR Objectives for MAR trial Confirms groundwater model Mitigates salt intrusion from Dawe

Slide 3: Bird in Hand Gold Project
Bird in Hand Gold Project TERRAMIN AUSTRALIA LIMITED SLIDE No. 3

Slide 4: Structure of Presentation
Structure of Presentation The nature of impact – How do economic impacts occur? Existing economic environment – understanding the local economy Experts used and why What we have heard – and how we are addressing these concerns Land value Perceptions TERRAMIN AUSTRALIA LIMITED SLIDE No. 4

Slide 5: What is economic impact?
What is economic impact? Negative economic impacts could occur if there is a confirmed Source – A description of the source of the potential impact event which alone or in combination has the potential to cause harm to an environmental receptor. Pathway – A description of the potential pathway

Slide 6: Experts - Economic
Experts - Economic Barry Burgan – Economic Research Consultants Professor of Management and MBA Program Director at Bond University Expertise: financial, economic and social assessments Member: Initial Accreditation Committee of Assoc. to Advance Collegiate Schools of Business Jim Hancock

Slide 7: FABAL – Agricultural Experts
FABAL – Agricultural Experts Ashley Keegan – B.App Sci (viticulture); MBA (finance) CEO - Operations, Food and Beverage Australia Limited (FABAL), Adelaide One of Australia’s largest privately owned vineyard/agricultural management groups Agribusiness – vineyards, orchards, groves – 1700Ha v

Slide 8: FABAL – Agricultural Experts
FABAL – Agricultural Experts Chris Day - MBA (international business), Bachelor of Laws and Economics, Grad. Dip in Financial Services CEO - Group, Food and Beverage Australia Limited (FABAL), Adelaide 25 years experiences in wine industry Chairman: SA Business Development Committee Direct

Slide 9: Currently happening – Terramin’s understanding
Currently happening – Terramin’s understanding We understand this from Economic Research Consultants – “Economic Impact Assessment” South Australian Centre for Economic Studies, University of Adelaide, – “Peer Review of Economic Impact Assessment” Econsearch – “Economic Contribution of Agric

Slide 10: Current Land uses
Current Land uses Adelaide Hills is a mixed-economic activity area Long history of resources development Agriculture, horticulture, defence, food and wine processing, retail, hospitality, water treatment, conservation and recreation Currently 36 quarry licences in operation in Adelaide Hills

Slide 11: Current Employment Trends – ABS
Current Employment Trends – ABS Adelaide Hills has an increasing unemployment trend 8.0 7.0 6.0 Unemployment Rate - % 5.0 4.0 3.0 2.0 1.0 0.0 2010 2011 2012 2013 2014 2015 2016 2017 Adelaide Hills Council Regional SA South Australia TERRAMIN AUSTRALIA LIMITED SLIDE No. 11

Slide 12: What’s happening in other areas in SA?
What’s happening in other areas in SA? Strathalbyn – Mine co-existed with grain farming, hospitality, horses and polo fields and Langhorne Creek wine region. Barossa Valley – Largest extractive quarry (vineyards, cellardoors, B&Bs) McLaren Vale – numerous quarries located adjacent (inc. 600m f

Slide 13: Proposed Project – over 8 years
Proposed Project – over 8 years Impact on SA Economy $280M TOTAL: 140 direct jobs and 423 indirect (year 4) 599 direct FTE and 1837 indirect FTEs over 5 years Impact on Adelaide Hills Economy 93 direct jobs and 240 indirect (year 4) $152.6M Impact on Fleurieu Peninsula Region 44 di

Slide 14: Local Spend Policy
Local Spend Policy Terramin have a local spend policy Always use local services and suppliers where possible Estimated to be – $7M per year directly into local Woodside and surrounds economy – $152.6M into Adelaide Hills region (over project) $30M per year operating expenditure (operating ph

Slide 15: TERRAMIN AUSTRALIA LIMITED SLIDE No. 15
TERRAMIN AUSTRALIA LIMITED SLIDE No. 15

Slide 16: We have heard
We have heard Concern: Visual amenity could impact businesses Used Oxigen - 2017 South Australian Landscape Architecture Awards – Tonsley, Adelaide Riverbank, Flinders uni, Waterfall gully, Halifax St Visual amenity plan removes the pathway of seeing mining infrastructure from hospitality/cell

Slide 17: TERRAMIN AUSTRALIA LIMITED SLIDE No. 17
TERRAMIN AUSTRALIA LIMITED SLIDE No. 17

Slide 18: Proposed Entrance
Proposed Entrance TERRAMIN AUSTRALIA LIMITED SLIDE No. 18

Slide 19: View Once Built from Cellardoors
View Once Built from Cellardoors VIEW BIH CELLARDOOR VIEW ARTWINE CELLARDOOR TERRAMIN AUSTRALIA LIMITED SLIDE No. 19

Slide 20: Current Vegetation Growth
Current Vegetation Growth TERRAMIN AUSTRALIA LIMITED SLIDE No. 20

Slide 21: We have heard
We have heard Concern: Nuisance noise could impact businesses We have designed our site to be 10 dB(A) lower than the legislative limits and inline with baseline noise measurements taken Lower limits than adjoining agricultural businesses Includes acoustic mitigation strategies – enclosing,

Slide 22: We have heard
We have heard Concern: Dust could impact businesses We have designed our site to remove most “normal” mining dust sources Bitumised roads, ore silo system, vegetation buffers, hydromulching Agricultural Impact Assessment identifies dust monitoring programme associated with Project likely to

Slide 23: We have heard
We have heard Concern: Dust has the potential to inhibit vineyard productivity Agricultural Impact Assessment discusses Deposition rates of organic fungicides and current practice of applying white reflective clay on vines (Kaolin) – no statistical difference in photosynthesis rates Agricult

Slide 24: We have heard
We have heard Concern: Vibration could impact businesses We have designed vibration to be half of the vibration felt if person was walking next to you at all hospitality businesses Removes or reduces the pathway significantly No impact to businesses envisaged – either to hospitality business

Slide 25: Year 1 – development, Year 3 – production, Year 5 – production
Year 1 – development Year 3 – production Year 5 – production TERRAMIN AUSTRALIA LIMITED SLIDE No. 25

Slide 26: Year 1 – development, Year 3 – production, Year 5 – production
Year 1 – development Year 3 – production Year 5 – production TERRAMIN AUSTRALIA LIMITED SLIDE No. 26

Slide 27: Year 1 – development, Year 3 – production, Year 5 – production
Year 1 – development Year 3 – production Year 5 – production TERRAMIN AUSTRALIA LIMITED SLIDE No. 27

Slide 28: We have heard
We have heard Concern: Groundwater could impact businesses We respect businesses rely on groundwater We have designed water management system to not impact any agricultural businesses’ ability to access water Proposal - Water neutral and licenced trading This includes – Fracture avoidance

Slide 29: Credible worst case – 70% Effective Grouting with MAR
Credible worst case – 70% Effective Grouting with MAR 6628 6628 6628 6628 6628 6628 6628 6628 6628 6628 6628 6628 8936 8940 10944 9154 23182 9153 8946 20475 18637 9152 10249 8301 Ground level 0.00 20.00 40.00 60.00 metres below surface 80.00 100.00 120.00 140.00 160.00 AIR SWL Range Terramin contrib

Slide 30: Expected Impact – 90% Effective Grouting with MAR
Expected Impact – 90% Effective Grouting with MAR 6628 6628 6628 6628 6628 6628 6628 6628 6628 6628 6628 6628 Ground level 8936 8940 10944 9154 23182 9153 8946 20475 18637 9152 10249 8301 0.00 20.00 40.00 metres below surface 60.00 80.00 100.00 120.00 140.00 AIR SWL Range Terramin contribution 90%+M

Slide 31: Groundwater Modelling Reviews
Groundwater Modelling Reviews IGS – Commissioned by Terramin for the Ministerial Determination Concluded Model is fit for purpose regarding the objectives – Objectives: verification of data, implementation of conceptual model into numerical model, model calibrations, scenario modelling (includin

Slide 32: Agricultural Impact Assessment
Agricultural Impact Assessment The Agricultural Impact assessment considers spray drift and disease introduction a low risk We have removed use of Group I, Phenoxy Acid herbicides onsite We use weed spraying chemicals registered in the Aus. Wine Institute registered pesticide guidelines Stan

Slide 33: Other issues considered by Ag. Impact Assessment
Other issues considered by Ag. Impact Assessment Considers additional vegetation (shelter belt) planting to be beneficial for biota habitat (Thompson and Hoffman, 2010; Retallack, 2012) and additional buffering capacity between both sites (dust sources and spraying activities) Tourism – largely

Slide 34: Conclusion – Agricultural Impact Assessment
Conclusion – Agricultural Impact Assessment Agricultural Impact Assessment Considered all impact assessments and information available Included site walk over Most credible pathways have been considered Based on implementation of design and proposed controls, residual risks are low TERRAMI

Slide 35: Conclusion – Economic Impact Assessment
Conclusion – Economic Impact Assessment Economic Impact Assessment – if no management strategies used Overall conclusion is that the risk to other economic activities in the area is low Economic Model: If all management and/or mitigation were not implemented – i.e. no water, dust, noise, visua

Slide 36: TERRAMIN AUSTRALIA LIMITED SLIDE No. 36
TERRAMIN AUSTRALIA LIMITED SLIDE No. 36

Slide 37: Land Value
Land Value Strathalbyn has seen continued growth even with operating mine since 2007 (Care and Maintenance Q4: 2013) **Average sale price 2009 2010 TERRAMIN AUSTRALIA LIMITED SLIDE No. 37 Realestate.com.au, retrieved 7th March 2018

Slide 38: Woodside
Woodside Mineral Claim registered in 2007 **Average sale price 2009 2010 TERRAMIN AUSTRALIA LIMITED SLIDE No. 38 Realestate.com.au, retrieved 7th March 2018

Slide 39: Woodside
Woodside No current indication of real estate impact with proposed project over last 12 months **Average sale price Mar-17 Apr-17 TERRAMIN AUSTRALIA LIMITED SLIDE No. 39 Realestate.com.au, retrieved 7th March 2018

Slide 40: Within and Surrounding Mineral Claim
Within and Surrounding Mineral Claim Even with Mineral Claim since 2007 and proposed mining project 8 adjoining properties have sold 5 in previous 5 years 4 in previous 18 months TERRAMIN AUSTRALIA LIMITED SLIDE No. 40

Slide 41: TERRAMIN AUSTRALIA LIMITED SLIDE No. 41
TERRAMIN AUSTRALIA LIMITED SLIDE No. 41

Slide 42: Land Value
Land Value If you feel your property will be impacted, there is a process Terramin will continue to monitor and compensation may be available to proven land value reductions Prescribed process - Mining Act 1971 (SA) Potential for independent value assessments Process to assess: prior to PE

Slide 43: Perception - Tourism
Perception - Tourism Anchor survey results from CSIRO Local people are not sure that Project will discourage tourists from visiting This group of people have limited information about the Project TERRAMIN AUSTRALIA LIMITED SLIDE No. 43 Strongly disagree Strongly agree

Slide 44: CSIRO Anchor Survey
CSIRO Anchor Survey Local shops and Mine will provide The mine will provide businesses will benefit valuable taxes and opportunities for local other income for the suppliers and contractors from mine employees state government Strongly disagree Strongly agree Strongly disagree Strongly agree S

Slide 45: Community Grant Scheme – Opportunity for WCCC
Community Grant Scheme – Opportunity for WCCC The aim of these grants is to support projects that provide specific sustainable outcomes which have long lasting benefit/s to the wider community Not for profit, sporting and recreation, environmental and community organisations Projects must prov

Slide 46: What if?
What if? My business has been negatively impacted by the mining project? Some mining activities will be compensated for prior to construction Defined by Mining Act 1971 (SA) Negotiated by Terramin and landowner, if no agreement, ERD Court utilised Evaluated prior construction Communicate

Slide 47: TERRAMIN AUSTRALIA LIMITED SLIDE No. 47
TERRAMIN AUSTRALIA LIMITED SLIDE No. 47
Source: Internet Archive copy of terramin.com.au
More decks from Terramin Australia Limited
Shareholder Meeting (May 2026)15 slides · May 2026
Shareholder Meeting (May 2025)12 slides · May 2025
Shareholder Meeting (May 2022)12 slides · May 26, 2022
Investor Presentation (October 2019)23 slides · Oct 31, 2019
Investor Presentation (October 2019)22 slides · Oct 30, 2019
Technical Presentation (June 2019)20 slides · June 2019