Aldridge Minerals — Investor Presentation (December 2014)
21 slides from Aldridge Minerals's investor presentation, December 2014

Slide 1: Corporate Presentation
Corporate Presentation December 2014

Slide 2: Cautionary Statement
Cautionary Statement Certain statements in this presentation constitute forward-looking statements or forward-looking information within the meaning of applicable securities laws (“forward-looking statements”). Any statements that express or involve discussions with respect to predictions, expectati

Slide 3: AGM: Investment Highlights
AGM: Investment Highlights ü Yenipazar: Permitted project with robust financial metrics o Low CAPEX – US$230M o NPV – US$330M (after-tax; 7% discount) o IRR – 32.2% (after-tax) o Payback – 2.4 years o Polymetallic (Au, Ag, Cu, Pb, Zn) = Natural Hedge ü Significant exploration upside immediately to

Slide 4: Yenipazar vs. Advanced Stage Comparables
Yenipazar vs. Advanced Stage Comparables P/NAV 1 Lower Risk 0.8 Aldridge Upside 0.6 0.4 0.2 0 Higher Risk Yenipazar Project Robust Economics Pre-‐Tax A9er-‐Tax IRR 34.5% 32.2% CAPEX $230M NPV (7%) $382M $330M Payback 2.3 yrs 2.4 yrs AGM Base Case Price Deck: Gold: $1,250/oz, Silver: $20.00/oz, Cop

Slide 5: Yenipazar: The Right Address
Yenipazar: The Right Address PROJECT Polymetallic deposit with robust economics; high IRR 32% / low CAPEX US$230M PLACE Excellent infrastructure; Turkey low cost mining PEOPLE Strong management team with Turkish experience; supportive major Turkish shareholder www.aldridgeminerals.ca 5 5

Slide 6: Yenipazar: Ideal for Open Pit
Yenipazar: Ideal for Open Pit EXCELLENT INFRASTRUCTURE þ WATER SECURED þ POWER SECURED -‐LOW COST OF Outcrops C$0.085 PER kWh PLANT EGLENCE PIT VILLAGE TMF TAILINGS CLEAN Waste Rock WRD BEACH WATER Dump (WRD) pit POND UPSIDE POTENTIAL backfill (starts Year 5) TAILINGS 1 km POND EARNING SOCIAL LIC

Slide 7: Yenipazar: Longitudinal Section
Yenipazar: Longitudinal Section www.aldridgeminerals.ca 7 7

Slide 8: Yenipazar: Reserves
Yenipazar: Reserves Reserve Escmate: April 15, 2014 Contained Metal Probable Au Ag Cu Pb Zn NSR Au Ag Cu Pb Zn Tonnage Reserves (g/t) (g/t) (%) (%) (%) ($/t) (M oz) (M oz) (M lbs) (M lbs) (M lbs) Oxide 3,214,000 0.83 23.2 0.24 0.96 0.54 42.24 0.09 2.40 16.67 68.02 38.31 Cu-‐Enriched 2,547,000 0.89

Slide 9: Yenipazar: Outline of Process Flowsheet
Yenipazar: Outline of Process Flowsheet Crushing SIMPLE & PROVEN TECHNOLOGY Grinding and Classification Gravity Circuit Flotation Tail Gold Leaching Cu Flotation (Doré) Pb Flotation Zn Flotation TOTAL RECOVERIES - SULPHIDE ZONE YEARS 1-4: Au: 82% Ag: 72% Cu: 75% Pb: 73% Zn: 62% YEARS 5-11: Au: 79% A

Slide 10: Yenipazar: Production
Yenipazar: Production Life of Average Mine Annual Gold 650,165 54,180 (oz) Silver 19.4M 1.6M (oz) Copper 122.1M 10.2M (lbs) Lead 387.0M 32.3M (lbs) Zinc 589.2M 49.1M (lbs) *AGM Base Case Price Deck: Gold: $1,250/oz, Silver: $20.00/oz, Copper: $3.00/lb, Lead: $0.94/lb, Zinc: $0.90/lb www.aldridgemine

Slide 11: Yenipazar: Capital & Operating Costs
Yenipazar: Capital & Operating Costs Pre-‐Produccon Capital Costs (CAPEX) in millions HIGH MARGIN: DIRECT Pre-‐producFon development $20 NSR PER TONNE: $83.24 Mine equipment $0 Life of Mine Operacng Costs1 Process plant and equipment $63 $ Total $/tonne Tailings & waste rock dump $12 (millions) of

Slide 12: Yenipazar: Development Timeline
Yenipazar: Development Timeline 2013 2014 2015 2016 2017 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 H1 H2 H1 H2 Feasibility Study þ COMPLETED EIA þ COMPLETED OpFmizaFon Study þ COMPLETED Land AcquisiFon Project Finance Engineering & Procurement ConstrucFon Commissioning & ProducFon Stakeholder Engmt. 12

Slide 13: Experienced Team: Diverse Skill Set
Experienced Team: Diverse Skill Set BOARD MANAGEMENT Barry Hildred, Chairman Han Ilhan, President & CEO CEO & Director of Aquila Resources; founder of The Equicom Group. Professional engineer; 26 years at URS leading global mining practice. Baran Baycan Robbert Borst, VP Project Development Founder

Slide 14: Capital Structure
Capital Structure Shares Outstanding: 107.0 million SEPTEMBER 2014 Fully diluted: 124.1 million EQUITY FINANCING: Director/Management ownership: ~33% (including ANT Holding) 52 week range: C$0.15 -‐ C$0.40 Recent price: C$0.22 US$10 MILLION @ Market Cap: C$23.5 million US$0.45 PER SHARE Top insFtuF

Slide 15: Why Aldridge
Why Aldridge ü Right Project - Right Place o Exceptional financial metrics o Natural hedge against commodity fluctuations o Significant exploration upside o Fully financed to construction ü Strong Support in Turkey o Key permits secured o Favourable infrastructure (water, power, roads, rail, and p

Slide 16: Appendix: Developing Value, Sustaining Growth
Appendix David Carew Director Corporate Development & IR T: +1 (416) 477-6984 E: dcarew@aldridgeminerals.ca DEVELOPING VALUE ⏐ SUSTAINING GROWTH 16

Slide 17: Aldridge Background
Aldridge Background Owner: Aldridge Minerals Inc. (TSX-‐V:AGM) – 100% (Alacer Gold Corp. maintains a NPI) Market Capitalizacon: C$21.4 million (as at November 4, 2014) Project Locacon: Tethyan mineral belt, Central Turkey Geology: Metamorphosed volcanogenic massive sulphide Mining Operacon: ConvenF

Slide 18: Aldridge: Significant Events
Aldridge: Significant Events Apr 3 – Feasibility Study results announced Apr 15– Yenipazar Opcmizacon Study Posicve Results announced Mar 25 – Han Ilhan appointed President & CEO Sep 2 – Announce US$45 M Financing Jun 17 – Earns 100% interest in with Orion Mine Finance Yenipazar Project Aug 28 – AGM

Slide 19: Yenipazar: Project Sensitivities
Yenipazar: Project Sensitivities STRONG ECONOMICS WITH DOWNSIDE PROTECTION www.aldridgeminerals.ca 19

Slide 20: Yenipazar: Recoveries by Ore Type
Yenipazar: Recoveries by Ore Type Total Copper Lead Zinc Metal Doré Recoveries Concentrate Concentrate Concentrate Gold 82% 71.5% 9% 0% 1.5% Silver 72% 2.5% 9.5% 50% 10% Sulphide Yrs 1 – 4 Copper 75% 75% Lead 73% 73% Zinc 62% 62% Gold 79% 65% 10% 0% 4% Sulphide Silver 76% 4% 10% 51% 11% Yrs 5 – 11 C

Slide 21: Yenipazar: Resource & Reserve Estimate
Yenipazar: Resource & Reserve Estimate Resource Escmate: November 26, 2012* Contained Metal Au Ag Cu Pb Zn Au Eq Au Ag Cu Pb Zn AuEq Category Tonnage (g/t) (g/t) (%) (%) (%) (g/t) (M oz) (M oz) (M lbs) (M lbs) (M lbs) (M oz) Indicated 29,669,000 0.95 31.3 0.31 1.01 1.47 2.42 0.90 29.85 204.8 660.2 9