Slide 1: Bird in Hand Gold Project - Update
Bird in Hand Gold Project - Update Draft Mining Lease Proposal provided to the Government on 20th December 2017 Checks against Mining Act, and regulatory requirements (Ministerial Determination) Discussions continue on aspects of the project with CCC, landholders, local community and governmen

Slide 2: Bird in Hand Gold Project - Update
Bird in Hand Gold Project - Update Managed Aquifer Recharge trial Discussion with Department of Environment, Water and Natural Resources (DEWNR) and Department of the Premier and Cabinet (Minerals) – awaiting feedback 2 - 4 reinjection wells and paired monitoring piezometers proposed No feed

Slide 3: Bird in Hand Gold Project - Update
Bird in Hand Gold Project - Update EPBC Act Referral – Caladenia rigida Optional – Company chose to refer Project Meeting in Canberra last year advised potentially not necessary based on outline of Project Lodged in October 2017 to ensure managing potential impacts appropriately Can be dow

Slide 4: Bird in Hand Gold Project - Update
Bird in Hand Gold Project - Update Corporate Reorganisation Announced to ASX on 11th January 2018 CEO to transform into executive management of Australian projects and exploration activities Overall responsibility for Terramin’s corporate and finance functions More resources for Bird in Ha

Slide 5: Noise – Examples of Noise Abatement Angas Zinc Mine
Noise – Examples of Noise Abatement Angas Zinc Mine Angas Zinc Mine – Underground and processing – Strathalbyn Landscape bunding / noise shielding Infrastructure placed below ground level Ventilation fan underground Activities limited during night – no road trucking or crushing between 10p

Slide 6: Noise – Examples of Noise Abatement Angas Zinc Mine
Noise – Examples of Noise Abatement Angas Zinc Mine TERRAMIN AUSTRALIA LIMITED SLIDE No. 6

Slide 7: Noise – Examples of Noise Abatement Waihi Gold Mine NZ
Noise – Examples of Noise Abatement Waihi Gold Mine NZ Waihi Gold Mine – New Zealand (open cut, underground + processing) – NZ TERRAMIN AUSTRALIA LIMITED SLIDE No. 7

Slide 8: Noise – Examples of Noise Abatement Waihi Gold Mine NZ
Noise – Examples of Noise Abatement Waihi Gold Mine NZ Waihi Gold Mine Town of approx. 5000 – horticulture and dairy farming region 2004: Underground commenced – 37km of drives, 360m deep Employs 400 Includes ore brought to surface, crushed, 2.7km conveyor, and processing plant Construct

Slide 9: Blasting and Vibration
TERRAMIN AUSTRALIA LIMITED Blasting and Vibration

Slide 10: 2q TERRAMIN AUSTRALIA LIMITED SLIDE No. 10
2q TERRAMIN AUSTRALIA LIMITED SLIDE No. 10

Slide 11: Project Cycle
Project Cycle After grouting cycle Drill Blast/Charge Remove “bog/muck” Insert ground support Map geology Check groundwater Backfill TERRAMIN AUSTRALIA LIMITED SLIDE No. 11

Slide 12: Explosive pattern
Explosive pattern Twin boom drills on articulated carrier – Jumbo ~60 holes per face 2.5m – 3.5m depth 45mm diameter Twice over 24 hours less than 30 seconds/day TERRAMIN AUSTRALIA LIMITED SLIDE No. 12

Slide 13: Explosive pattern
Explosive pattern Twin boom drills on articulated carrier – Jumbo ~60 holes per face 2.5m – 3.5m depth 45mm diameter Twice over 24 hours Total blasting less than 30 seconds/day TERRAMIN AUSTRALIA LIMITED SLIDE No. 13

Slide 14: Vibration and Air overpressure
Vibration and Air overpressure When explosives detonate in rock, most of the energy is used in breaking and displacing the rockmass. However, some of energy is released in the form of ground vibration and air-overpressure. A soundwave from blasting is generated below the threshold of human hearin

Slide 15: Proposed Project Outcome
Proposed Project Outcome No public nuisance impacts from air- overpressure and vibration caused by blasting Proposal addition: “from the mining operation”. TERRAMIN AUSTRALIA LIMITED SLIDE No. 15

Slide 16: Blasting Mitigation
Blasting Mitigation Ground Vibration Air Overpressure Process of charging • Explosive quantity • Explosive quantity • Explosive type • Explosive type • Initiation timing • Degree of Confinement • Burden to free face – Rock and space between – Uncharged drillhole length explosive drillholes • Number

Slide 17: Vibration - Context
Vibration - Context Terramin commitment AS 2670.2–1990 TERRAMIN AUSTRALIA LIMITED SLIDE No. 17

Slide 18: Air Overpressure
Air Overpressure Background air-overpressure is currently peaking over 110-120 dBL Data collected remotely by Saros (independent expert consultants in 140.00 blasting) 731 instances above 115 dBL = 0.58% 130.00 212 instances above 120 dBL = 0.17% 120.00 dBL 110.00 100.00 90.00 80.00 22/09/2017 2

Slide 19: Compliance Requirements
Compliance Requirements Australian blasting compliance limits AS 2670.2–1990 are amongst the most stringent in the world. Both ground vibration and air overpressure limits are based on human comfort criteria Terramin commits to: Ground Vibration – Not to exceed 5mm/second for 95% of occasions, wit

Slide 20: Underground Development
Underground Development 0.5 1 2 10 5 TERRAMIN AUSTRALIA LIMITED SLIDE No. 20

Slide 21: TERRAMIN AUSTRALIA LIMITED SLIDE No. 21
0.5 2 1 TERRAMIN AUSTRALIA LIMITED SLIDE No. 21

Slide 22: TERRAMIN AUSTRALIA LIMITED SLIDE No. 22
0.5 1 TERRAMIN AUSTRALIA LIMITED SLIDE No. 22

Slide 23: TERRAMIN AUSTRALIA LIMITED SLIDE No. 23
0.5 TERRAMIN AUSTRALIA LIMITED SLIDE No. 23

Slide 24: TERRAMIN AUSTRALIA LIMITED SLIDE No. 24
0.5 TERRAMIN AUSTRALIA LIMITED SLIDE No. 24

Slide 25: TERRAMIN AUSTRALIA LIMITED SLIDE No. 25
0.5 TERRAMIN AUSTRALIA LIMITED SLIDE No. 25

Slide 26: Managed Aquifer Recharge - Update
Managed Aquifer Recharge - Update Met with DEWNR (Water Dept.) and DPC (Mining Dept.) in December Waiting on feedback as to what testwork would be suitable to meet expectations Trial will inform final design of Managed Aquifer Recharge network for operations Trial will be between 2 and 4 rei

Slide 27: Reinjection and Water Treatment Process
Reinjection and Water Treatment Process TERRAMIN AUSTRALIA LIMITED SLIDE No. 27

Slide 28: Reinjection and Water Treatment Process
Reinjection and Water Treatment Process TERRAMIN AUSTRALIA LIMITED SLIDE No. 28

Slide 29: Credible Worst Case Scenario Inflows
Credible Worst Case Scenario Inflows How was it built? Using the credible worst case scenario of a 70% effective grouting regime A maximum peak inflow of 24l/s The underground dewatering system has been designed on this plus an additional 14l/s. The additional 14l/s came from doubling of aqu
Source: Internet Archive copy of terramin.com.au
More decks from Terramin Australia Limited
Shareholder Meeting (May 2026)15 slides · May 2026
Shareholder Meeting (May 2025)12 slides · May 2025
Shareholder Meeting (May 2022)12 slides · May 26, 2022
Investor Presentation (October 2019)23 slides · Oct 31, 2019
Investor Presentation (October 2019)22 slides · Oct 30, 2019
Technical Presentation (June 2019)20 slides · June 2019