Argosy Minerals Limited · ASX:AGY

Argosy Minerals — Investor Presentation (July 2025)

19 slides from Argosy Minerals's investor presentation, Jul 10, 2025

  1. Slide 1: Company Presentation

    Company Presentation July 2025 ASX:AGY www.argosyminerals.com.au

  2. Slide 2: Corporate Snapshot

    Corporate Snapshot Capital Structure Argosy Share Price Shares on issue 1 1,535,920,934 0.06 0.05 Share price 2 A$0.034 0.04 Market capitalisation 2 A$52.2 million Share Price (A$) 0.03 3 Cash A$6.1 million* 0.02 Debt Nil 0.01 ASX code AGY 0 Argosy Board AGY Share Price Mal Randall Non-Executive Cha

  3. Slide 3: Building a Tier-1 Lithium Producer

    Building a Tier-1 Lithium Producer  Experienced team of technical operators in Argentina  Supported by strong technical and corporate team in Perth Our Team  Pablo Alurralde with over 30 years of industry experience, formerly with FMC (Livent), holds patents in lithium carbonate production  Pilo

  4. Slide 4: Rincon Lithium Project - Key Highlights

    Rincon Lithium Project - Key Highlights  Rincon Lithium Project located in the world-class “Lithium Triangle” in Salta Province, Argentina BOLIVIA  Argosy currently owns 77.5% of Puna Mining S.A., moving to 90% ownership interest upon development of 12,000tpa operation https://pixlr.com/expr CHILE

  5. Slide 5: Pathway to Sustainable Lithium Production

    Rincon Lithium Project Pathway to Sustainable Lithium Production 5

  6. Slide 6: 12,000tpa Project Status

    12,000tpa Project Status ► EIA regulatory approval granted for a total production capacity of 12,000tpa ► Key engineering and feasibility activities underway include: Chemical flowsheet optimization Process development works have reconfigured the filtration methodology and processing sequence Value

  7. Slide 7: Development Pathway to 12ktpa production

    Development Pathway to 12ktpa production ► 12ktpa Project Development Engineering and feasibility works underway to commercialize the Rincon Lithium Project ► Proven Process Demonstration facility produced >99.5% battery-quality lithium carbonate ► Expert Collaboration Design and execution enhanced

  8. Slide 8: Proven >99.5% Lithium Carbonate Production

    Proven >99.5% Lithium Carbonate Production 8

  9. Slide 9: Significant Infrastructure Access

    Significant Infrastructure Access ► Prime Location Ready access to industrial water, power, Existing ~58ha operational evaporation and transport infrastructure ponds 8,606ha of mining tenements ► Scalable Facilities Demonstration facility location 12,000tpa production facility and evaporation ponds

  10. Slide 10: Mineral Resource Estimate & Exploration Target

    Mineral Resource Estimate & Exploration Target1 Li2CO3 Weighted mean average lithium (tonnes) concentration Total JORC Mineral Resource Estimate (MRE) 731,801 329mg/L (from 412Mm3 of potentially recoverable brine) Indicated MRE 640,330 327mg/L Inferred MRE 91,471 352mg/L JORC Exploration Target1 186

  11. Slide 11: Planned 12,000tpa Project Development

    Planned 12,000tpa Project Development* FID Feasibility & FEED EPCC Ramp-up 2024 H2 2025 H1 2025 H2 2026 H1 2026 H2 2027 H1 2027 H2 2028 H1 Permits and government approvals FID  2ktpa + 10ktpa EIA approved   Final Investment Decision  Award Engineering, Procurement, Construction & Management Feas

  12. Slide 12: Commitment to ESG

    Commitment to ESG Argosy has developed a chemical process technology with a minimal environmental footprint A Commitment to Sustainability Minimal Environmental Footprint Reducing Environmental Impact Low Energy Use – Emission Reduction – Emission Reduction – Waste Management – Waste Management – Wa

  13. Slide 13: Argentina – Sustainable Reforms and Growth

    Argentina – Sustainable Reforms and Growth The bases law (Ley de Bases) enacted in July 2024, and the May’s National Agreement between major political forces (governors and legislative chambers), sets a significant pro-market setting for future investment in Argentina Key features of the Bases Law M

  14. Slide 14: Argentina MOU with USA to Boost Metals Investment

    Argentina MOU with USA to Boost Metals Investment Strengthening Mining Investments in Argentina  On 23 August 2024, an MOU was signed with Argentine Foreign Minister and the United States Under Secretary of State for Economic Growth, Energy and Environment  The MOU seeks to strengthen cooperation

  15. Slide 15: Tonopah Lithium Project

    Tonopah Lithium Project 15

  16. Slide 16: Tonopah Lithium Project – Nevada, USA

    Tonopah Lithium Project – Nevada, USA TONOPAH IS STRATEGICALLY LOCATED IN THE EMERGING USA LITHIUM HEARTLAND Located ~4km from Albemarle’s longstanding Silver Peak operation - the only lithium carbonate operation in USA Geophysical data identifies lithium brine target areas Gravity-derived 3D depth

  17. Slide 17: Contact

    Argosy Minerals Limited (ASX: AGY) Contact admin@argosyminerals.com.au T: +61 8 6188 8181 E: admin@argosyminerals.com.au Level 2, 22 Mount Street Perth WA 6000 Australia 17

  18. Slide 18: Disclaimer & Important Statement

    Disclaimer & Important Statement This presentation is for information purposes only. Neither this presentation nor the information contained in it constitutes an offer, invitation, solicitation or recommendation in relation to the purchase or sale of shares in any jurisdiction. This presentation may

  19. Slide 19: Disclaimer & Important Statement

    Disclaimer & Important Statement Cautionary Note: A Production Target is a projected estimate of potentially mineable mineralised material based on the application of modifying factors. The process and assumptions used to establish the Production Targets for Argosy’s operations and development proje