  1. Slide 1: Allegheny Energy, Inc. Edison Electric Institute Financial Conference

    Slide 1: Allegheny Energy, Inc. Edison Electric Institute Financial Conference

    October 24-27, 2004 Allegheny Energy, Inc. Edison Electric Institute Financial Conference

  2. Slide 2: Forward-Looking Statements

    Slide 2: Forward-Looking Statements

    Forward-Looking Statements In addition to historical information, this presentation contains a number of "forward-looking statements" as defined in the Private Securities Litigation Reform Act of 1995. Words such as anticipate, expect, project, intend, plan, believe, and words and terms of similar s

  3. Slide 3: Non-GAAP Financial Measures

    Slide 3: Non-GAAP Financial Measures

    Non-GAAP Financial Measures 2 This presentation includes non-GAAP financial measures as defined in the Securities and Exchange Commission’s Regulation G. Where noted, the presentation shows certain financial information on an “as adjusted” basis, to exclude the effect of certain items as described h

  4. Slide 4: Jeffrey Serkes, Senior Vice President and Chief Financial Officer

    Slide 4: Jeffrey Serkes, Senior Vice President and Chief Financial Officer

    Jeffrey Serkes Senior Vice President and Chief Financial Officer 3 Paul Evanson Chairman, President and Chief Executive Officer

  5. Slide 5: Allegheny Energy

    Slide 5: Allegheny Energy

    4 Allegheny Energy Allegheny Energy Generation & Marketing 48.3 billion KWH generated (2003) Delivery & Services 46.5 billion KWH sold (2003) 46.4 billion KWH under long-term contracts

  6. Slide 6: Major Priorities: First Year

    Slide 6: Major Priorities: First Year

    Increase liquidity Decrease risk and volatility of earnings, cash flow Re-establish financial reporting Re-focus on core business Rebuild senior management team 5 Major Priorities: First Year

  7. Slide 7: Rebuilt Senior Management Team

    Slide 7: Rebuilt Senior Management Team

    Board of Directors 6 Rebuilt Senior Management Team Paul J Evanson, Chairman H. Furlong Baldwin Cyrus F. Freidheim, Jr. Julia Johnson Michael H. Sutton Eleanor Baum Ted J. Kleisner Steven H. Rice Gunnar E. Sarsten Since June 2003 Existing Chairman, President and CEO Paul Evanson SVP & Chief Financia

  8. Slide 8: Current Priorities

    Slide 8: Current Priorities

    Current Priorities Restore financial strength Build high performance organization Optimize value of generation 7

  9. Slide 9: Restore Financial Strength

    Slide 9: Restore Financial Strength

    Restore Financial Strength Goal: reduce debt by $1.5 billion* Repaid $900 million of debt On track to further reduce debt by $600 million *December 1, 2003 through year-end 2005 8

  10. Slide 10: High Performance Organization: Balanced Scorecard

    Slide 10: High Performance Organization: Balanced Scorecard

    High Performance Organization: Balanced Scorecard 9 VISION: “To Be a Top Performing Utility by Year-End 2007” Financial Performance Engaged Employees Environmental Stewardship Shareholder Value Operational Excellence Customer Satisfaction

  11. Slide 11: High Performance Organization: 2007 Targets

    Slide 11: High Performance Organization: 2007 Targets

    High Performance Organization: 2007 Targets 10 YEAR END 2007 TARGET Operational: Plant availability 91% (1 st quartile) Service unavailability 172 minutes/year Financial: Credit rating Investment grade O&M expense Reduce by $250-300M

  12. Slide 12: High Performance Organization: 2007 Targets

    Slide 12: High Performance Organization: 2007 Targets

    High Performance Organization: 2007 Targets 11 YEAR END 2007 TARGET Customer satisfaction 1 st quartile Engaged employees: OSHA incident rate 2.10 Engagement survey Continuous improvement Environmental Continued full compliance Shareholder value Higher share price

  13. Slide 13: Optimize Value of Generation: Low-Cost Fleet

    Slide 13: Optimize Value of Generation: Low-Cost Fleet

    $0 $20 $40 $60 $80 $100 $120 0 20,000 40,000 60,000 80,000 100,000 120,000 140,000 160,000 180,000 Optimize Value of Generation: Low-Cost Fleet Capacity in MW Dispatch Cost Allegheny Units Allegheny 58 MW Allegheny 7,617 MW Allegheny 951 MW Allegheny has an advantaged dispatch in PJM PJM Dispatch Co

  14. Slide 14: Optimize Value of Generation: Transition to Market

    Slide 14: Optimize Value of Generation: Transition to Market

    13 * 2004 through 2007: spot and forward markets. 2008: independent market forecast. Optimize Value of Generation: Transition to Market Independent Market Forecast* POLR Contract Prices

  15. Slide 15: Optimize Value of Generation: Transition to Market

    Slide 15: Optimize Value of Generation: Transition to Market

    Maryland – Additional Industrial 2003 2004 2005 2006 2007 2008 Ohio – Com & Ind POLR Agreements Expiring Transitioning to Market MWH millions 2004 2005 2006 2007 2008 2009 0 5 10 15 25 35 20 30 Ohio Maryland Pennsylvania 14 Maryland - Res Maryland – Com & Ind Ohio – Additional Industrial Pennsylvani

  16. Slide 16: Pennsylvania Rate Petition

    Slide 16: Pennsylvania Rate Petition

    $20 $25 $30 $35 $40 $45 $50 $55 2005 2006 2007 2008 2009 2010 $0 $50 $100 $150 $200 $250 $300 $350 $400 $450 2006 2007 2008 2009 2010 Current Proposed Generation Rate, Pennsylvania $ per MWH Cumulative Increase in Pre-Tax Operating Income* $ millions 15 *Based on 2003 MWH Pennsylvania Rate Petition

  17. Slide 17: Challenge: Coal Costs

    Slide 17: Challenge: Coal Costs

    16 100% 90% 50% 2004 2005 2006 Contracted Coal $31 $34 $35* 2004 2005 2006 Average Cost Per Ton * Existing contracts only Challenge: Coal Costs

  18. Slide 18: Challenge: SO2 Allowance Costs

    Slide 18: Challenge: SO2 Allowance Costs

    Challenge: SO 2 Allowance Costs Emit 370,000 - 380,000 tons of SO 2 /year Receive allowances for 220,000 tons/year Additional allowance inventory of 450,000 tons phases in over five years Exposure to allowance market: < 50,000 tons in 2005 ~100,000 tons/year in 2006-2008 17

  19. Slide 19: Potential for Coal and SO2 Cost Recovery

    Slide 19: Potential for Coal and SO2 Cost Recovery

    Potential for Coal and SO 2 Cost Recovery Market- Based 19% Fixed Price 61% Regulated 20% 18 Generation Sales in 2006 (MWH; estimates) 39%

  20. Slide 20: Challenge: Environmental Issues

    Slide 20: Challenge: Environmental Issues

    Challenge: Environmental Issues 19 In compliance with all environmental laws Evaluating options for the future If install scrubbers/SCRs at 5 remaining major units, estimated cost = $1.3 billion In discussions with state/federal authorities

  21. Slide 21: The Road to Recovery

    Slide 21: The Road to Recovery

    The Road to Recovery $80 $100 $120 $140 $160 $180 $200 $220 AYE Dow Electric Utilities S&P 500 Stock Performance ($100 Invested on July 1, 2003) 20 Refinanced bank debt Exited energy trading Brought reporting up to date Announced OVEC, Mountaineer, Lincoln sales Filed PA rate proposal Completed equi

  22. Slide 22: The Road to Recovery

    Slide 22: The Road to Recovery

    21 The Road to Recovery FINANCIAL Reduce interest expense STRENGTH Issued equity; conversion of trust preferred HIGH Increase plant availability PERFORMANCE Reduce O&M expense OPTIMIZE Approved rate increase, PA (2006 & 2008) GENERATION Market-based rates/PA settlement CHALLENGES Coal and SO 2 costs

  23. Slide 23: Paul Evanson, Chairman, President and Chief Executive Officer

    Slide 23: Paul Evanson, Chairman, President and Chief Executive Officer

    Paul Evanson Chairman, President and Chief Executive Officer 22 Jeffrey Serkes Senior Vice President and Chief Financial Officer

  24. Slide 24: Financial Review

    Slide 24: Financial Review

    Financial Review Reducing debt, interest expense O&M expense targets Financial results Outlook 23

  25. Slide 25: Restore Financial Strength: Reducing Debt by $1.5 Billion

    Slide 25: Restore Financial Strength: Reducing Debt by $1.5 Billion

    Restore Financial Strength: Reducing Debt by $1.5 Billion * Allegheny expects free cash flow of more than $250 million for 2004 and 2005 combined 497 Announced asset sales > 103 Free cash flow* $ 1,500 TOTAL EXPECTED DEBT REDUCTION $ 900 Achieved to date (includes October 2004 equity proceeds) $ MIL

  26. Slide 26: Reducing Debt: Announced Asset Sales

    Slide 26: Reducing Debt: Announced Asset Sales

    Reducing Debt: Announced Asset Sales 25 PROCEEDS TOTAL EXPECTED ANNOUNCED ($ millions): AT CLOSING PROCEEDS CLOSING Lincoln generating facility $173 $173 Q4 2004 OVEC (9% equity interest) 96 102 Q4 2004/ Q1 2005 Mountaineer Gas 228 244 mid-2005 Total cash and assumed debt $497 $519 IN PROGRESS: Whea

  27. Slide 27: Reducing Interest Expense

    Slide 27: Reducing Interest Expense

    Reducing Interest Expense 26 ANNUALIZED INTEREST SAVINGS FROM: $ MILLIONS (PRE-TAX) Reducing debt $1.5 billion by Dec. 2005 (1) $ 90 Refinanced bank debt (March 2004) 50 Repricing bank debt (October 2004) (2) 10 TOTAL ~ $150 4Q 2003 annualized interest expense vs. estimated 4Q 2005 annualized intere

  28. Slide 28: O&M Expense: 2000 - 2003

    Slide 28: O&M Expense: 2000 - 2003

    $ millions $641 $830 $1,144 $1,010 $0 $200 $400 $600 $800 $1,000 $1,200 2000 2001 2002 2003 27 O&M Expense: 2000 - 2003 Up $369 since 2000

  29. Slide 29: Sources of Higher O&M Expense

    Slide 29: Sources of Higher O&M Expense

    Salaries, Wages & Benefits $98 Contract Work $52 Insurance, Rent & Other $33 Outside Services $78 Cancelled Projects $31 Midwest Assets & Mountaineer Gas $77 Sources of Higher O&M Expense 28 Total Increase, 2000 – 2003: $369 million

  30. Slide 30: O&M Expense: 2007 Target

    Slide 30: O&M Expense: 2007 Target

    $830 $1,144 $1,010 $700 - 750 $641 $0 $200 $400 $600 $800 $1,000 $1,200 2000 2001 2002 2003 2007 29 O&M Expense: 2007 Target ($ millions) Target

  31. Slide 31: Reduce O&M Expense by $250-$300 Million

    Slide 31: Reduce O&M Expense by $250-$300 Million

    Reduce O&M Expense by $250-$300 Million 75 Planned asset sales $250 - 300 TOTAL 125 - 175 Headquarters costs and non-recurring items (net) $ 50 T&D and coal plant costs (excludes fuel and SO 2 allowances) Targeted Decrease, 2003 – 2007 ($ millions) 30

  32. Slide 32: Improving Financial Results in 2004

    Slide 32: Improving Financial Results in 2004

    31 Improving Financial Results in 2004 Reported net loss for first half Outages at Pleasants, Hatfield plants Special maintenance expense Expect net profit on core operations in Q3, Q4 Pleasants, Hatfield in service Less special maintenance Expect losses on asset sales, impairment charges (~$430 mil

  33. Slide 33: Outlook: Beyond 2004

    Slide 33: Outlook: Beyond 2004

    Outlook: Beyond 2004 Achieve predictable earnings, cash flow Restore long-term earnings growth Reduce debt, interest, O&M expense Improve plant availability Transition to market-based pricing Return to investment grade credit rating 32

  34. Slide 34: Allegheny Energy

    Slide 34: Allegheny Energy

    Allegheny Energy Solid regulated business with stable cash flows Low-cost coal generation in PJM Improving financial performance Earnings growth potential 33

  35. Slide 35: Supplemental Information

    Slide 35: Supplemental Information

    Supplemental Information 34

  36. Slide 36: Net Income (Loss)

    Slide 36: Net Income (Loss)

    Net Income (Loss) 35 $ millions As Reported As Adjusted 2003: Q1 $ (58.8) $ (41.0) Q2 (231.5) (28.5) Q3 (51.0) TBA Q4 (13.7) TBA 2004: Q1 $ 33.3 $ (0.3) Q2 (39.5) (32.8) TBA: to be announced

  37. Slide 37: EBITDA

    Slide 37: EBITDA

    EBITDA 36 $ millions As Reported As Adjusted 2003: Q1 $ 77.6 $ 92.9 Q2 (203.5) 150.1 Q3 134.5 TBA Q4 212.6 TBA 2004: Q1 $ 274.3 $ 202.0 Q2 116.6 128.3 TBA: to be announced

  38. Slide 38: Delivery and Services: Overview

    Slide 38: Delivery and Services: Overview

    Delivery and Services: Overview In 5 states (PA, WV, MD, VA, OH) 1.5 million electric customers Load growth: 2.2% (1993-2003) WEST VIRGINIA WEST VIRGINIA West Penn Power Monongahela Power Potomac Edison 37 Allegheny Power VIRGINIA CHARLESTON HARRISBURG PENNSYLVANIA OHIO CLEVELAND WASHINGTON, DC MARY

  39. Slide 39: Delivery and Services: Competitive Rates

    Slide 39: Delivery and Services: Competitive Rates

    Delivery and Services: Competitive Rates Residential Rates as of January 1, 2004 #2 in customer satisfaction in East region for past six years 9.65 6.47 8.98 7.34 9.39 0 2 4 6 8 10 12 Pennsylvania West Virginia Maryland Virginia Ohio 6.76 7.01 6.94 6.81 6.82 ¢/kWh National Average = 9.12 ¢/kWh Alleg

  40. Slide 40: Regulatory Timeline

    Slide 40: Regulatory Timeline

    Regulatory Timeline 39 * One-time T&D increase can be requested through 2007. Fuel cost pass-through and one-time T&D and generation increases can be requested between 2007 and 2010. 2004 2005 2006 2007 2008 Through 2005 Through 2005 Increases through 2008 Through 2005 Increases through 2008 Through

  41. Slide 41: Generation and Marketing: Generation Assets

    Slide 41: Generation and Marketing: Generation Assets

    Generation and Marketing: Generation Assets Capacity MWH Output Capacity by Region Coal 68% Gas 22% Hydro & Oil 10% Coal 95% Gas 1% Hydro & Oil 4% PJM 85% Midwest 15% Note: Data for year ended December 31, 2003 for AE Supply and Monongahela Power generation. 11,500 MW of primarily base load coal-fir

  42. Slide 42: Generation and Marketing: PJM -- An Attractive Market

    Slide 42: Generation and Marketing: PJM -- An Attractive Market

    World’s largest competitive power market 51 million people 700 million MWH of energy annually 160,000 MW of capacity Nation’s most liquid spot power market Model for FERC’s proposed Standard Market Design Provides transactional flexibility: contracts not required Generation and Marketing: PJM -- An

  43. Slide 43: Generation and Marketing: Maintenance Spending

    Slide 43: Generation and Marketing: Maintenance Spending

    Generation and Marketing: Maintenance Spending Legacy Assets Maintenance Spending* and Operating Performance $120 $140 $160 $180 $200 $220 $240 $260 $280 $300 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 0 2 4 6 8 10 12 14 Total Maintenance Spending Equivalent Forced Outage