Allegheny Energy Inc

Allegheny Energy — Merger or Acquisition (August 2010)

20 slides from Allegheny Energy's merger presentation, Aug 13, 2010

  1. Slide 1: FirstEnergy / Allegheny Energy Merger Update

    FirstEnergy / Allegheny Energy Merger Update August 2010

  2. Slide 2: Forward-Looking Statements

    In addition to historical information, this presentation may contain a number of "forward-looking statements" as defined in the Private Securities Litigation Reform Act of 1995. Words such as anticipate, expect, project, intend, plan, believe, and words and terms of similar substance used in connect

  3. Slide 3: Additional Information and Where to Find It

    Additional Information and Where to Find It In connection with the proposed merger, FirstEnergy filed a Registration Statement on Form S-4 (Registration No. 333- 165640) with the SEC that includes a joint proxy statement of FirstEnergy and Allegheny Energy and that also constitutes a prospectus of F

  4. Slide 4: Natural Geographic Fit

    FirstEnergy Power Plants Allegheny Power Plants Natural Geographic Fit... * Reflects the sale of Allegheny Energy's Virginia distribution assets, which was completed on June 1, 2010, and indicates the transmission service area within Virginia. FirstEnergy (FE) Service Area Allegheny Energy (AYE) Ser

  5. Slide 5: Three Separate Growth Platforms

    Three Separate Growth Platforms... Assets Utilities Transmission Generation / Retail Greater scale Increased geographic reach 7 states 10 utilities 6 million customers Diverse customer base Multiple load centers Nearly 20K miles of transmission Separate transmission entities ATSI1 TrAIL2 PATH3 Utili

  6. Slide 6: Transition Planning Underway

    Transition Planning Underway... Integration / planning teams Teams comprising FirstEnergy and Allegheny Energy employees Began review in mid-April Identifying value-drivers Teamwork has been very positive Leveraging prior integration experience Value of "lessons learned" GPU / FirstEnergy Centerior

  7. Slide 7: Generation and Fuel: Benefits

    Generation and Fuel: Benefits Generation asset reliability improvement Dispatch optimization Expand use of fuel blending techniques Mining assets (increased MW) Centralized, in-sourced maintenance functions Outage best practices Safety / training program best practices Ash sales Retail sales growth

  8. Slide 8: Proven Performance

    Note: Peer benchmarking figures are sourced from a Navigant study commissioned by FE in 2009. Source: Generation Knowledge Service, Copyright 2010 Navigant Consulting, Inc. Supercritical Benchmark 2009 2008 2007 2006 Equivalent Forced Outage Rate (EFOR) FE and AYE (Supercritical and Subcritical) Cap

  9. Slide 9: Value Chain

    Value Chain Retail Suppliers Allegheny Energy Supply FirstEnergy Solutions Retail Margin ? ? Wholesale Margin ? ? Generation Margin ? ? Retail Risk Counterparty Collateral Limited Counterparty Limited Collateral Limited Counterparty Limited Collateral Margin captured across entire value chain, not j

  10. Slide 10: Corporate and Information Services: Benefits

    Corporate and Information Services: Benefits Review of outsourced services Integrate SAP and other systems Information systems consolidation: Enterprise applications Network communications Infrastructure & data centers Utility systems Generation systems Transaction management Credit systems Informat

  11. Slide 11: Utility Operations: Benefits

    Utility Operations: Benefits Benefits Services Materials Processes Vegetation management Substation construction Pole inspections Energy efficiency Underground locating Vehicle leasing Meters Substation transformers Distribution transformers Wire and cable Wood poles Pole line hardware Vehicle fuel

  12. Slide 12: On Plan and On Schedule

    On Plan and On Schedule... Shareholder Approvals S-4 Registration Statement declared effective July 16, 2010 Separate shareholder meetings scheduled for September 14, 2010 State Regulatory Filings Maryland Public Service Commission - Filed May 27, 2010 Pennsylvania Public Utility Commission - Filed

  13. Slide 13: Proposals: Jobs / Economic Development / Service

    Proposals: Jobs / Economic Development / Service No net utility job reductions for two years due to involuntary attrition as a result of the merger integration process (MD, PA, WV) Establish FE regional management approach (MD, PA, WV) Establish new Power Systems Institute program (PA, WV) Maryland

  14. Slide 14: Compelling Transaction

    Compelling Transaction... Benefits - real and achievable Margin - across entire value chain Assets - three growth platforms Approvals - on plan and on schedule Experienced management with proven ability to integrate companies

  15. Slide 15: Appendix

    Appendix tae 212% Building a Better, Stronger Company —FisténerqyiAlegheny Energy Merger Update August 17, 2010

  16. Slide 16: Diverse Competitive Generation Portfolio

    Diverse Competitive Generation Portfolio Combined Competitive Capacity 1 Capacity Combined Subcritical Coal 20 Supercritical Coal 42 Nuclear 19 Gas / Oil 12 Hydro/Wind 7 Wind Combined Competitive Production 2 Nuclear Gas / Oil Output Combined Subcritical Coal 18 Supercritical Coal 52 Nuclear 27.5 Ga

  17. Slide 17: Utility Operations at a Glance

    Utility Operations at a Glance* Ownership Company Customers (millions) Service Area Square Miles (thousands) Distribution Overhead Wire Miles (thousands) Number of Substations Total Line Staffing FE Ohio Edison/Penn Power 1.2 8.1 41.2 447 625 FE Cleveland Electric Illuminating 0.8 1.6 21.2 207 364 F

  18. Slide 18: Rate Base

    Rate Base Ownership Company Rates Effective Rate Base ($ millions) Allowed ROE FE Ohio Edison January 2009 $1,251 10.5% FE Penn Power May 1998 $654 12.9% FE Cleveland Electric Illuminating May 2009 $984 10.5% FE Toledo Edison January 2009 $414 10.5% FE Jersey Central Power & Light June 2005 $2,080 9

  19. Slide 19: State Procedural Schedules: Pennsylvania and Maryland

    State Procedural Schedules Pennsylvania June 22, 2010 - Prehearing Conference July 15, 2010 - Supplemental Testimony Filed July 30, 2010 - Deadline to Identify Proposed Witnesses Week of August 3, 2010 - Public Input Hearing August 17, 2010 - Direct Testimony (Intervenors) Due September 13, 2010 - R

  20. Slide 20: State Procedural Schedules: West Virginia and Virginia

    State Procedural Schedules West Virginia August 2, 2010 - Intervention Deadline October 14, 2010 - Non-Company Direct and Rebuttal Testimony Due November 1, 2010 - Company Rebuttal Testimony Due November 8, 2010 - Evidentiary Hearings Commence December 6, 2010* - Initial Briefs Due December 16, 2010

Allegheny Energy — Merger or Acquisition (August 2010) on 6ix