Slide 1: Technical File EVO On steel deck
TECHNICAL FILE EVO® On steel deck EN ISO 14122-3 : 2017 NF E85-015 : 2019 newsletter delta plus systems : diffusion interne uniquement

Slide 2: General information: Guardrail on steel deck EVO
General information Distributed by Guardrail on steel deck EVO® PRODUCT PRESENTATION The EVO® guardrail on steel deck is a collective fall protection system designed to protect roof terraces not accessible to the public. It is the perfect solution to secure steel deck roofs without cutting or re-sea

Slide 3: General information: Standards and regulation
General information Distributed by Guardrail on steel deck EVO® STANDARDS - This space shall be reduced to a maximum of 340 mm between the rail and the - A guardrail must be installed as soon as the possible height of fall is higher middlerail and between the middlerail and the toeboard when the gua

Slide 4: General information: Upright and fixing bracket dimensions
General information Distributed by Guardrail on steel deck EVO® UPRIGHTS DIMENSIONS 840 mm (NF) 1000 / 1100 mm (NF) 1100 mm (EN) 1 Straight 2 Inclined 3 Folding FIXING BRACKETS DIMENSIONS (in mm) For steel deck with 250 mm-wave-spans 250 mm wave fixing base for steel deck with railing parallel to th

Slide 5: Use and maintenance instructions
General information Distributed by Guardrail on steel deck EVO® USE & MAINTENANCE INSTRUCTIONS - The use of a EVO® toeboard is madatory if the terrace does not have any - The person performing the installation of EVO® guardrail must be a qualified parapet or if it is less than 100 mm height. person

Slide 6: Fixing: Guardrail on steel deck
Fixing Distributed by Guardrail on steel deck EVO® FIXING PRINCIPLE 1 Before fixing After fixing 1: Self-drilling screw 6x25 2 1 2 2: Waterproof washer 3: Fixing plate 3 4: Waterproof flue washer 3 4 4 Steel deck Steel deck Wave spans Guardrail configurations Quantities Parallel to the deck 8 250 mm

Slide 7: Fixing: Guardrail on steel deck, wave spans 250mm
Fixing Distributed by Guardrail on steel deck - wave spans: 250mm EVO® 21 6 8 5 22 7 8 1 3 2 19 4 18 20 23 25 26 24 GENERAL COMPONENTS 1 2 3 4 Shrunk rail Ø45 mm Shrunk middle-rail Ø35 mm Rail cap Ø45 mm Middle-rail cap Ø35 mm WV830450 WV830350 WV830451 WV830351 Lenght 3000 mm Lenght 3000 mm 5 6 7 8

Slide 8: Nomenclature: General components and support bases
Nomenclature Distributed by Guardrail on steel deck EVO® GENERAL COMPONENTS 9 10 11 12 Wall fixing bracket Wall fixing bracket Wall fixing aluminium bracket Straight upright for rail Ø45 mm - WV830454 for middle-rail Ø35 mm for rail and middle-rail H : 1010 mm WV830354 WV830455 WV8201010 13 14 15 16

Slide 9: Nomenclature: Fixings and examples of layouts
Nomenclature Distributed by Guardrail on steel deck - wave spans: 250mm EVO® NOMENCLATURE: FIXINGS 27 28 29 30 Stainless steel self-drilling Stainless steel self-drilling 6x25 self-drilling screw Chimney washer screw 4.8x16 TH - Z0SYSBVHF48016 screw 4.8x25 TH - Z0SYSBVHF48025 With sealed washers - Z

Slide 10: Implementation
Implementation Distributed by Guardrail on steel deck EVO® Inside angle Outside angle 1332 mm for 333 or 1500 mm for 250 wave spans 1332 mm for 333 or 1500 mm for 250 wave spans 1332 mm for 333 or 1500 mm for 250 wave spans 1332 mm for 333 or 1500 mm for 250 354 mm maxi for 250 wave spans 480 mm max

Slide 11: Installation
Installation Distributed by Guardrail on steel deck EVO® INSTALLATION The installation of EVO® guardrail must be done by a minimum of two people. It is recommended to start installation in an angle 354 mm maxi for 250 wave spans 900 mm for 250 and 333 wave Example for fixing on 250 mm-wave-span stee

Slide 12: Installation
Installation Distributed by Guardrail on steel deck EVO® INSTALLATION Bowl screws 7 - Insert a middlerail through 2 8 - Insert the set into the fixing supports 9 - Screw in the bowl 10 - Put the rail on 11 - Clip EZclip to the top uprights screws of the flat bases the uprights of the upright mm 300

Slide 13: Installation: Wall brackets and toeboard
Installation Distributed by Guardrail on steel deck EVO® INSTALLATION: WALL BRACKETS 300 mm max. 1 - Fix wall brackets using self-drilling 4.8 x 25 2 - Observe the maximum distance of 300 mm between screws the upright and the wall INSTALLATION: TOEBOARD 1 - Place the toeboard support on the 2 - Atta
Source: company website
More decks from Delta Plus Group SA
Investor Presentation (January 2025)17 slides · Jan 29, 2025
Investor Presentation (2025)17 slides · 2025
FY2023 Earnings Presentation60 slides · Apr 3, 2024
FY2022 Earnings Presentation62 slides · Apr 4, 2023
FY2021 Earnings Presentation58 slides · Apr 5, 2022
FY2019 Earnings Presentation57 slides · Apr 28, 2020