Slide 2: Key Facts and Strategy
Key Facts and Strategy KEY FACTS Listed on the London’s AIM Market, focussed on the Rukwa Coal to Power project in Western Tanzania Rukwa coal mine operational – ramp up production in Q4 2017 supplying coal to East Africa industries Pre-development stage on the Rukwa Coal to Power Project – oppor
Slide 3: Corporate Information
Corporate Information Edenville Energy: Thermal coal developer in Tanzania Developer of Tanzania’s brownfield Rukwa Coalfields with a measured & indicated resource of 170Mt Company Capitalisation Share Price Performance Shares on Issue 1,336,317,798 Warrants and Options 293,678,147 Fully Diluted 1,6
Slide 4: Board and Management Team
Board and Management Team Jeffrey Malaihollo, Non Executive Chairman – 23+ experience in varied roles within resources and finance. A PhD in Geology having worked for Newcrest Mining and Rio Tinto. A mining analyst with Loeb Aron, a corporate finance firm in London, followed by several years of CEO/
Slide 5: Rukwa Coal to Power Project, Rukwa Region - Tanzania
Rukwa Coal to Power Project Rukwa Region - Tanzania Tanzania – Part of the East Africa Power Pool (EAPP) Project located in Western Tanzania - opportunity for Coal and Power Coal Mine and Wash Plant Construction Completed Long Term Opportunity to Develop up to 300MW of Power Supply 5 www.edenvil
Slide 6: Key Points - Mining
Key Points - Mining MINING PROJECT AT ADVANCED STAGE Construction Completed with Mining and Washing Operations Started Asset quality and scale – 173 million tonnes JORC resource + exploration upside – Thermal power plant quality coal – Typical washed values 5,000kcal, Ash 20%, Moisture 5% Mini
Slide 7: Project Development
Project Development Top: New Edenville Volvo EC300 Excavator Top: New Road to Mine Top: Plant Site; Centre: Road Construction Drainage; Bottom: Mkomolo Coal Bottom: Wash Plant arriving in Tanzania Bottom: Crushed Coal Stockpile 7 www.edenville-energy.com
Slide 8: Project Production
Project Production Top: New Road to Mine Top: Washed Coal Stockpiles Above: Wash Plant Drum Assembly Bottom: Mining Upper Seam Coal Bottom: Uniform coal quality 8 www.edenville-energy.com
Slide 9: Mining Project Metrics
Mining Project Metrics MINING PROJECT IN PRODUCTION Construction Completed with Mining and Washing Operations Started Capital expenditure of approximately USD2.1m Monthly production target of 10,000 to 15,000 tonnes of product by early 2018 Payback estimated between 14 and 18 months Projec
Slide 10: Transport and Logistics Infrastructure
Transport and Logistics Infrastructure The mine is located in a strong position in western Tanzania for transportation and logistics ______ Excellent road network north and south of the project Multiple road access to Zambia going south ______ Lake Tanganyika provides barging options to take coal no
Slide 11: Sumbawanga and Site Area
Sumbawanga and Site Area Top: Airstrip in Sumbawanga Centre: New +200km Road Connection near Top: Community assistance to local site schools Bottom: Old Namwele Pit Workings Bottom: Sumbawanga – Regional Centre 11 www.edenville-energy.com
Slide 12: Key Points – Power Development
Key Points – Power Development POWER DEVELOPMENT KEY POINTS Edenville Energy plc have formally been asked to move forward plans on a coal fired thermal power project at Sumbawanga by the Ministry of Energy and Minerals (MEM) Edenville Project Concept Study already accepted and approved by Tanesc
Slide 13: Regional Power Landscape
Regional Power Landscape Planned New 400KV transmission line linking north- south within 7km of Rukwa Tanesco Planned National Grid System Part of “East Africa Power Pool” development plan, which will see a total of 2,302km under construction between Kenya, Tanzania and Zambia (ZTK Project) Co
Slide 14: Appendix 1 - Rukwa Coal to Power Project
Appendix 1 - Rukwa Coal to Power Project The Company’s core asset is the Rukwa Coal to Power Project, located in western Tanzania, ~25km by road to the north-east of the major commercial centre of Sumbawanga. The Rukwa Coalfields are comprised of the Mkomolo, Namwele and Muze deposits – historic
Slide 15: Geology Resource Statement
Geology Resource Statement The JORC Compliant Resource Statement completed in 2013 from Independent Consultants SMS outlined 173 Million Tonnes of which 61.5 Million Tonnes are in the Measured Category Deposit Classification Tonnes Measured 36,958,091 Mkomolo Indicated 93,414,982 Inferred 1,923,817
Slide 16: Extensive Outcropping of Coal
Extensive Outcropping of Coal Mkomolo – Old Surface Workings Diamond Drilling at Mkomolo Mkomolo Drill Core “Bar Code” Coal measures (seams marked in red) 1 metre Overburden at Namwele Mkomolo Prospecting Pit 16 www.edenville-energy.com
Slide 17: Appendix 2 - Tanzania Power & Country Statistics
Appendix 2 - Tanzania Power & Country Statistics Power & Electricity Overview Country Statistics Tanzania has total installed electricity capacity of around 1,500MW Population: 47.2m Presently, only 45% of urban areas are electrified and this falls to 2014 per capita GDP: US$912.7 below 5% for rural
Slide 18: Edenville Energy plc - Thank you
Edenville Energy plc Thank you Company Address: Aston House Cornwall Avenue London N3 1LF info@edenville-energy.com www.edenville-energy.com
Slide 19: Disclaimer
Disclaimer This presentation ("Presentation") has been prepared by Edenville Energy plc (the "Company") and is confidential and is only directed at persons who fall within the exemptions contained in Articles 19 and 49 of the Financial Services and Markets Act 2000 (Financial Promotion) Order 2005 (
Edenville Energy — Investor Presentation (October 2017) on 6ix