Vali and Odin on schedule for first gas
Filed with ASX · · 4 pages · English
Summary by 6ix AI
Metgasco Ltd provides an operations update on the Vali and Odin gas projects, confirming they are on schedule for first gas delivery. Siteworks at the Vali field are progressing as planned, with flowlines and export pipelines installed and pressure tested. Work has begun on the accelerated connection to the Odin gas field, with flowline installation expected to start soon.