Synex International Inc.TSX: SXI

Synex International Inc. third quarter of fiscal 2005

· Issued by Synex International Inc. via CNW
TSX: SXI

VANCOUVER, May 5 /CNW/ - For the three months ended March 31, 2005,
revenue increased to $854,094 as compared to $452,532 for the corresponding
period in the previous year, while net income was $199,529 as compared to a
net loss of $7,866. For the nine months ended March 31, 2005, revenue
increased to $2,112,550 as compared to $916,161 in the first nine months of
fiscal 2004, while the net loss decreased to $101,526 from a net loss of
$159,251. The Company has two active divisions, namely, the power division and
the engineering division. The increase in revenue for the nine months ended
March 31, 2005 as compared to the corresponding period in the previous year is
primarily because the power division did not commence selling electricity from
plants in British Columbia until January 26, 2004 or from plants in Michigan
until April 1, 2004.

Power Division: For the nine months ended March 31, 2005, revenue
increased to $1,530,576 from $385,140 for the corresponding period in the
previous year and operating income was $43,140 as compared to an operating
loss of $78,038. The primary operations of the power division are the sale of
electricity from the 3.8 MW Mears Creek Hydroelectric Plant on Vancouver
Island, British Columbia and four hydroelectric plants totaling 10 MW located
on the Tittabawassee River near Midland, in mid-Michigan, USA (the "Plants").
During the first nine months of fiscal 2005, revenue and generation of the
Plants was $1,289,765 and 28,403 MWh respectively. For the nine months ended
March 31, 2005, actual electricity generation was 80% of the estimated
generation for the period, primarily due to unfavourable weather conditions in
both coastal British Columbia and mid Michigan.
In late December 2004, the power division invested $500,000 for a 12.5%
share of the Upnit Power Limited Partnership. The Limited Partnership was
formed to develop, own and operate the 6.5 MW China Creek Hydroelectric
Project to be located near Port Alberni, British Columbia. The $13.7 million
project is currently under construction with a projected commercial operation
date of October 2005.
The power division is currently constructing a 45 km mixed
overhead/submarine cable powerline, which will provide electricity to the
residents of Kyuquot and nearby areas. The $3 million project is about 15%
complete with a projected operation date of January 1, 2006.

Engineering Division: The engineering division was active on a number of
assignments for the power division and others. For the nine months ended  
March 31, 2005, revenue from external customers increased to $554,141 from
$490,840 for the corresponding nine months in fiscal 2004 with segment
operating profit decreasing to $38,139 from $70,813.

OUTLOOK

The Company presently owns and operates 14 MW of hydroelectric capacity.
The Company expects to be profitable for the fiscal year ending June 30, 2005
unless unfavourable weather patterns continue in both British Columbia and
Michigan.
The Company is currently advancing two new projects; the Kyuquot
Electrical Utility and the Cypress Creek Hydro Project. In addition, the
Company holds over 1.3 million shares of Coast Mountain Power Corporation, a
public company trading on the TSE Venture Exchange (symbol MW). Based on the
closing price on March 31, 2005, the market value of the shares of Coast
Mountain held by the Company was nearly $1.9 million. The value of the
investment is recorded on the balance sheet of the Company at its cost of
$39,305.


(signed)
------------------------
Greg Sunell, President
400 - 1444 Alberni Street, Vancouver B C V6G 2Z4
Phone (604) 688 8271  Ext. 309 Fax (604) 688 1286
E-mail: gsunell(at)synex.com Web Site: www.synex.com/
%SEDAR: 00002435E

Synex International Inc. on 6ix

Earlier from Synex International

Later from Synex International

All Synex International news releases