MONTREAL, May 8 /CNW Telbec/ - Semafo Inc. (SMF: TSX) today provided an update on the construction progress at its Mana Gold project in Burkina Faso. The update is based on the status of construction at the end of April 2007.
- Principal road construction, including 8km of the 10km road to the
Nyafe pit, is completed
- Foundation works for the plant are near completion.
- Steel erection is scheduled to commence in the first week of June.
Structural steel for the project is currently being fabricated in
Senegal.
- All plant equipment including the laboratory has been ordered.
- Relocation of the Somona village is undergoing and is scheduled for
completion in September.
- Drilling of the water wells for pit dewatering and plant supply is
completed.
- Stripping of the Wona pit has begun using our own mining fleet and
operators.
- Waste material from the Wona pit is being used for the water dam and
tailings dam currently under construction.
- The power generating equipment is in transit and scheduled to arrive on
site this month.
- First deliveries of the CIL tanks are scheduled to arrive on site in
early July.
- The crushing circuit is scheduled to arrive on site in June.
- The apron feeder is scheduled for delivery in August.
- The elution package and regeneration kiln are scheduled for delivery in
early August.
- The 2,000 ton per day temporary ball mill is scheduled for delivery in
September.
- The 4,000 ton per day permanent ball mill is scheduled for delivery in
December.
Funding of the US$70M capital expenditures for the Mana Gold project is
via existing corporate cash resources and a five year US$45M term loan from
Natixis Banque Populaires. The Mana gold project is fully permitted.
Commissioning of the plant is scheduled for year end.
The common shares of Semafo are traded on The Toronto Stock Exchange
under the symbol "SMF".
FORWARD-LOOKING STATEMENTS
This press release contains "forward-looking statements", including, but
not limited to, the statements regarding the Company's expectations as to the
market price of gold, strategic plans, future commercial production,
production targets, timetables, mine operating costs, fixed assets expenses,
mineral reserve estimates and to the company's perspectives. Forward-looking
statements express, as at the date of this press release, our estimates,
forecasts, projections, expectations and beliefs as to future events or
results. Forward-looking statements are reasonable, but involve a number of
risks and uncertainties, and there can be no assurance that such statements
will prove to be accurate. Therefore, actual results and future events could
differ materially from those anticipated in such statements. Factors that
could cause results or events to differ materially from current expectations
expressed or implied by the forward-looking statements include, but are not
limited to, factors associated with fluctuations in the market price of
precious metals, mining industry risks, uncertainty as to calculation of
mineral reserves, risks related to the grade of reserves, risks related to
hedging strategies, risks of delays in construction and requirements of
additional financing.
Semafo is a mining company whose mission is to explore, develop and mine
major gold deposits in West Africa. Semafo currently operates the Kiniero
mine in Guinea, the Samira Hill mine in Niger and is developing the Mana
project in Burkina Faso
More extensive information on Semafo can be found on our home page at http://www.semafo.com