MONTREAL, Aug. 16 /CNW Telbec/ - SEMAFO (TSX - SMF) today announced the
successful start-up and return to full operation of the Samira Hill plant.
The Company completed the start-up of the mill during the month of August
on schedule. The gearbox arrived on site earlier in the month accompanied by a
team of specialists responsible for installation, alignment and commissioning.
The Samira Hill plant is now back in full operation. As previously announced
on June 21, 2006, the 2006 production forecast has been revised to 65,000
ounces.

<<
Semafo took advantage of the shut down period to

-   complete an overall mechanical review of the mill that should improve
    future operations
-   complete a general maintenance program of the plant that included an
    overhaul of the power plant
-   undertake preventative maintenance of major equipment previously
    planned for later in the year
-   continue mining whereby some 600,000 tons of ore have been
    stockpiled as ore feed to the mill

The Samira Hill Gold Mine ownership is held 40% by Semafo, 40% by Etruscan
Resources Inc. and 20% by the State of Niger. However, Semafo is entitled to
recover all funding it has provided to bring the Samira Hill Gold Mine into
production and any working capital needs it may have advanced from Samira's
production cash flows on a preferential basis.

The common shares of Semafo are traded on The Toronto Stock Exchange
under the symbol "SMF".

FORWARD-LOOKING STATEMENTS

This press release contains "forward-looking statements", including, but
not limited to, the statements regarding the Company's expectations as to the
market price of gold, strategic plans, future commercial production,
production targets, timetables, mine operating costs, fixed assets expenses,
mineral reserve estimates and to the company's perspectives. Forward-looking
statements express, as at the date of this press release, our estimates,
forecasts, projections, expectations and beliefs as to future events or
results. Forward-looking statements are reasonable, but involve a number of
risks and uncertainties, and there can be no assurance that such statements
will prove to be accurate. Therefore, actual results and future events could
differ materially from those anticipated in such statements. Factors that
could cause results or events to differ materially from current expectations
expressed or implied by the forward-looking statements include, but are not
limited to, factors associated with fluctuations in the market price of
precious metals, mining industry risks, uncertainty as to calculation of
mineral reserves, risks related to the grade of reserves, risks related to
hedging strategies, risks of delays in construction and requirements of
additional financing.

 Semafo is a mining company whose mission is to explore, develop and
 mine major gold deposits in West Africa. Semafo currently operates
   the Kiniero mine in Guinea, the Samira Hill mine in Niger and
           is developing the Mana project in Burkina Faso
>>

SEMAFO Inc on 6ix

Earlier from SEMAFO

Later from SEMAFO

All SEMAFO news releases