Angus Energy, a UK oil and gas company, said an instrumentation fault that caused repeated false shutdowns (spurious trips) of the booster compressor at its Saltfleetby Gas Field has been resolved. The field has returned to stable production, with current rates in line with the company's expectations.

Key details

  • The compressor problem disrupted Saltfleetby production for about a month, leaving production for that period approximately 7% below forecast. Production optimisation work is ongoing.
  • At the Brockham Oil Field, arrival of the rig for the planned BRX4Z workover (work on an existing well) is delayed because the rig is still deployed on another operation that is taking longer than anticipated.
  • Angus Energy says workover preparations at Brockham are complete, the delay is outside its control, and it is ready to start operations when the rig arrives.

What’s still pending

  • The start of the Brockham BRX4Z workover depends on the rig's arrival, and the company expects operations to begin within weeks; Angus Energy will update the market once operations are underway.

6ix AI wrote this summary from the release below and checked it against the release.

Angus Energy PLC
19 November 2026

THE INFORMATION CONTAINED WITHIN THIS ANNOUNCEMENT IS DEEMED BY THE COMPANY TO CONSTITUTE INSIDE INFORMATION AS STIPULATED UNDER THE MARKET ABUSE REGULATION (EU) NO. 596/2014 AS IT FORMS PART OF UK DOMESTIC LAW PURSUANT TO THE EUROPEAN UNION (WITHDRAWAL) ACT 2018, AS AMENDED. UPON THE PUBLICATION OF THIS ANNOUNCEMENT VIA A REGULATORY INFORMATION SERVICE, THIS INFORMATION IS CONSIDERED TO BE IN THE PUBLIC DOMAIN.

19 November 2026

Angus Energy PLC

(“Angus Energy”, the “Company” or together with its subsidiaries, the “Group”)

(AIM:ANGS)

Saltfleetby Production and Brockham Update

  • Saltfleetby instrumentation fault identified and resolved, with stable production restored at rates in line with the Company's expectations.
  • Brockham BRX4Z workover preparations complete, with rig mobilisation delayed due to its ongoing deployment elsewhere.

The Company is pleased to provide the following production and operations update.

Saltfleetby Gas Field

Production at the Saltfleetby Gas Field was disrupted over the past month by repeated spurious trips of the booster compressor, resulting in production for this period being approximately 7% below forecast. Investigation traced the cause to an instrumentation fault, which has now been resolved. The field has returned to stable production, with current rates in line with the Company’s expectations. Production optimisation work is ongoing.

Brockham Oil Field

Further to the Company's previous announcements, mobilisation of the rig for the planned BRX4Z workover programme has been delayed due to its ongoing deployment on another operation, which is taking longer than anticipated.

Whilst the delay is outside of the Company's control, the Company is ready to commence operations upon arrival of the rig. Operations are expected to commence in the coming weeks, and the Company will update the market once operations are underway.

END

For further information please visit www.angusenergy.co.uk.

Angus Energy Plc

Carlos Fernandes

Finance Director                                                                          Via Flagstaff

SP Angel Corporate Finance LLP (Nomad and Broker)         www.spangel.co.uk

Stuart Gledhill / Jen Clarke / Richard Hail                                    Tel:+44 (0)20 3470 0470

Flagstaff PR/IR angus@flagstaffcomms.com

Tim Thompson / Fergus Mellon / Alison Alfrey                             Tel:+44 (0) 207 129 1474

About Angus Energy plc

Angus Energy plc is a UK AIM quoted independent oil and gas company. Angus is the leading onshore gas producer in the UK and has ambitious plans to grow onshore production and diversify internationally. Angus Energy has a 100% interest in the Saltfleetby Gas Field (PEDL005), majority owns and operates conventional oil production fields at Brockham (PL 235) and Lidsey (PL 241) and has a 25% interest in the Balcombe Licence (PEDL244). Angus Energy operates all fields in which it has an interest.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.

END

Angus Energy PLC on 6ix

Story so far

Earlier from Angus Energy

All Angus Energy news releases