Robust Scoping Study on the Mt Ida Magnetite Project
Filed with ASX · · 6 pages · English
Greg Durack Robert Benussi Charles Guy Issued Capital: Shares: 1,486,756,465 Deferred Shares: 262,255,799 Unlisted Opts: 6,000,000 Currently Developing: • Iron Ore • Manganese ROBUST SCOPING STUDY DELIVERED ON THE MT IDA MAGNETITE PROJECT KEY POINTS • Scoping Study based on a 20 year mine life, mining 25 mtpa to produce 10 mtpa of Magnetite concentrate • Base Case capital cost is $1,583 million, a